Nevada Geothermal Issues Full Notice to Proceed to Ormat for the Blue Mountain 'Faulkner 1' Power Plant

VANCOUVER, British Columbia, Sept. 4 /PRNewswire-FirstCall/ -- Nevada Geothermal Power Inc. (NGP) (OTC Bulletin Board: NGLPF; TSX-V: NGP) and Ormat Technologies, Inc. (NYSE: ORA) announced today that NGP Blue Mountain 1 LLC (NGP 1) has issued a Full Notice to Proceed (FNTP) under its fixed-price, date-certain engineering, procurement and construction (EPC) contract with Ormat Nevada Inc. to supply and construct the Phase 1 49.5 MW gross 'Faulkner 1' geothermal power plant at Blue Mountain, Nevada.