http://www.newswire.ca/en/story/1005393/canada-lithium-project-update-major-process-equipment-received-full-time-marketing-team-established-in-china

TORONTO, July 10, 2012 /CNW/ - Canada Lithium Corp. ("Canada Lithium" or the "Company") (TSX: CLQ) (OTCQX: CLQMF) announced today that major components of the process plant are now on-site at its Québec Lithium Project near Val d'Or, Québec, and the project is on schedule for year-end commissioning.

Long lead-time items ordered in 2011 will be installed in July and August. This includes crushers, flotation cells, kiln, rod mill and ball mill, high voltage transformers, conveyors and other equipment. Inside the process plant, the foundations and structural steel for the ball mills, rod mills and flotation circuit have been completed, and installation of the equipment will commence. The foundations for the hydrometallurgical kiln have been poured and welding of the kiln shell will begin. Foundations for the crusher circuit have been completed and the fine ore bin structure has been erected. In addition, high voltage transformers and switchgear have arrived on site and will be installed.

The mining fleet, composed of three 100-tonne mine trucks, hydraulic excavator, 992 front-end loader, grader and D9 dozer are on-site and operational. Pre-stripping of the deposit is scheduled to commence in late July.

As part of its focus on Asian lithium battery manufacturers, the Company has set up a marketing team in China, which will be opening a full-time marketing office in Shanghai in September to market battery-grade lithium carbonate products. The lithium carbonate will be sold under the trade name "Québec Lithium™."

Commissioning of the mine and spodumene plant is expected to occur late this year, while production of battery-grade lithium carbonate is anticipated to begin in the first quarter of 2013, building up to a 20,000-tonne-per-annum Li2CO3 capacity by the end of 2013. Project construction is currently on-time and on-budget. Recent photographs from the site can be viewed at the Company's website: www.canadalithium.com. Select the button "Click to view Photo Gallery".