NR - Update on mine construction and progress on the RDM project
posted on
Oct 01, 2012 10:56AM
Romania, Hungary & Brazil - N.I. 43-101, 5.09 M oz & inferred 5.66 M oz of Gold plus 175.0 M lbs of Copper .
Text here
October 01, 2012 09:40 ET
TORONTO, ONTARIO--(Marketwire - Oct. 1, 2012) - Carpathian Gold Inc. (TSX:CPN) (the "Corporation" or "Carpathian") is pleased to report that it is in the process of finalizing documentation with Macquarie Bank Limited to increase the Project Loan Facility for its wholly owned Riacho dos Machados Gold Project (the "Project" or "RDM Project"), Brazil from gross proceeds of US$80 Million (see press release dated January 10, 2012) to gross proceeds of US$90 Million. This increase in the Project Loan Facility is to cover off a previous funding gap that existed on the Project. With this increase, the Corporation is funded for the construction and development of the Project. To date in 2012 the Corporation has spent approximately US$40 million of its own equity and has committed an additional US$35 million to the Project from cash it has on hand. The overall initial CAPEX budget for 2012/2013 for the Project currently remains the same at approximately US$160 Million.
The following provides an overview progress update on the development of the Project as of the date of this press release.
With essentially all major contract items signed off and/or ready to sign off, the overall Project budget is being optimized and updated monthly based on work completed and committed contracts to incorporate the additional scope of environmental work and the lining of the tailings impoundment area. The Project budget is monitored and adjusted where appropriate on a monthly basis to best incorporate the additional scope items to the Project.
Two on-strike exploration targets are currently being drill tested; Cinco Mil, approximately 2 km north of the open-pit and Mato da Roca 2, approximately 13 km south of the open-pit. Assay results are pending and will be reported when available. Several other targets have been identified on the Project and will be evaluated at a later date. The objective of the drill programs is to identify shallow open pit material to truck to the mill facility for either expanded yearly production and/or extended mine life.
The Corporation will continue to post regular updates on its website on the construction and development advancement of the Project.