Skip to content
Sign in

Post

Colossus Minerals Inc

Prez3.6 rating from 57 members40.3K ptsRate

CSI Corporate Update

Quite a turn around. SMF

Colossus Minerals Provides Corporate Update

Thursday November 14, 2013, 2:38pm PST

Colossus Minerals Inc. (TSX:CSI,OTCWX:COLUF) provided a development update for its 75% owned Serra Pelada gold-platinum-palladium Mine along with its financial results for the interim periods ended September 30, 2013. As of November 14, 2013, the Company had completed approximately 2,300 metres of total development on Serra Pelada.

As quoted in the press release:

As of November 14, 2013, the Company had completed approximately 2,300 metres of total development; 1,500 primary and 800 metres secondary development. On July 15, 2013, the Company announced that some dewatering wells (bores) and pumps were not performing to design specifications and, as a result, the Company required additional dewatering capacity in order to mine the Central Mineralized Zone (“CMZ”) in a sustainable, effective and efficient manner.

As disclosed in September 2013, several bores and pumps have been repaired and six bores are now operating. Refurbishment of three additional bores was not successful. Total dewatering capacity is currently at 790 m3 per hour. Three more bores are in the process of being refurbished. Two additional bores with a capacity of 250 m3 per hour each are being established. Installation of this equipment has been delayed due to issues of mobilizing drill rigs to site and equipment supply. It is currently expected that the first of the two new wells will be operational by early December 2013.

Results of Operations for the three months ended September 30, 2013
Net income for the three months ended September 30, 2013 was $9.8 million ($0.07 per Common Share) compared with a net loss of $14.1 million ($0.13 per Common Share) for the comparable period in 2012.

Join the conversation about Colossus Minerals Inc.

Reply

Replies

  1. Strange that they explained their process, and progress. Dumped on severely by the market. Not shocking, but strange. When one looks at the images of all the plant and mine progress, I can see progress albiet slowly achieved. This is great rock. I look forward to production.

    1. The water issue certainly was of concern in september. With the new bore holes, they are getting back to what they need. I still wonder what he market was flinching over.

      "The rate of recharge to the bore field has been observed to be approximately 20% higher than anticipated during the period September and October 2013. This is being investigated by our hydrological consultants. It is considered likely that this is the result of interconnection with an aquifer. Recently, the rate of recharge has reduced to the rate expected from the hydrological model and the bore field water level has resumed its anticipated rate of drawdown. Prior to this observation, in the third quarter, the Company decided to build contingency into its dewatering program by drilling the second of the two new wells referenced above. Establishment of this well is already underway and it is expected to be operational by mid December 2013. The Company has concluded that certain wells are not salvageable. Total capacity, upon completion of the two new wells and the refurbishment program, is expected to increase total flow to the range of 1300 - 1400 m3 per hour. The Company's hydrology consultants continue to monitor recharge rates and water table drawdown and the Company believes that the targeted dewatering capacity has sufficient contingency to remove the volume of water necessary to allow sustainable mining in 2014. Infrastructure development in the red and grey siltstone has not been impacted however and continues to progress according to plan. The resources of the Company are focused on mine infrastructure development and additional dewatering in order to achieve the Company's plans of delivering ore to the process plant during the second quarter 2014".

      September 17 November 14
      Total Project 92 % 95 %
      Process Plant
      Engineering 100 % 100 %
      Procurement 99 % 99 %
      Civil construction 100 % 100 %
      Structural steel fabrication 100 % 100 %
      Structural, mechanical, piping & electrical installation 88 % 95 %
      Power house 100 % 100 %
      Ventilation upgrade Phase I 100 % 100 %
      Ventilation upgrade Phase II 55 % 60 %
      Tailings impoundment facility 80 % 95 %
      Rehabilitation of dewatering bore field 85 % 90 %
      Expansion of dewatering capacity 30 % 80 %
      1. To be fair, and not just a chearleader. The problems they face, are more time and more money. More time: they plan of completing the flotation circuits by Q3 1014. More Money, here is their excerpt:

        The Company has historically relied on financing to fund the exploration and development of the Serra Pelada Mine. The Company will need additional capital in 2013 or 2014 to fund the completion of the development and the ramp-up of production and to meet existing obligations of the Serra Pelada Mine. The Company is currently investigating this financing and alternatives to strengthen its balance sheet to have further flexibility should other unforeseen circumstances or production delays occur.

        They have certainly raised a ton of money, and have spent a good deal of time (and all that money). There is good progress and good looking infrastructure in place. They have a work force. What's left? More money and a couple more quarters of development just to get to ramp-up and mill refinement. This isn't quick and easy either. Lets hope they come up with a non-dilutive, not sell my soul type financing arrangement. It would be a shame to come this far, and stall out within a couple of quarters. They wouldn't be the first. But maan, this rock is good, let's get it done people...