Skip to content
Sign in

Post

Copper Fox Metals Inc.

VEEP3.0 rating from 72 members2K ptsRate

Nova Gold

Look Nova Gold is down $1.69, to $3.77, wow what happened.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

    1. From todays financial post...

      Barrick shares dropped 7% on Thursday morning as investors absorbed the disappointing Pascua-Lama update and Q2 results.

      Mr. Sokalsky has started a review of the company’s development projects and taken what he called a “more disciplined review” of capital allocation. As a result, he has found that Barrick’s next tier of projects, Cerro Casale and Donlin Gold, do not currently meet the company’s investment criteria. They have been effectively shelved for now. Barrick said it will look at ways to improve the economics at those projects.

          1. Donlin and Galore are now both in hiatus. Barrick and Teck have effectively spoken about their willingness to sink in capital for these rich, long life deposits. We don't want Teck buying NG- we want Teck to buy CUU. We need a mine built before the dream of district becomes a reality. Schaft Creek might be the one to do it.

            What is scary about this is how a few lines from Barrick basically pulled the rug out from NG. This is really unfortunate, let's hope we don't get the same treatment from Teck.

            1. Replying to @mudguy

              No question we want CUU sold first.

              I am not enitrly sure what you meant by this: "Barrick and Teck have effectively spoken about their willingness to sink in capital for these rich, long life deposits". I realize that Galore is much too expensive to build anytime soon but do you think Donlin is in the same catagory?

              What if Barricks bigest problem with Donlin is having Nova Gold as a partner? NG has essentially turned themselves into a one-trick pony and are at the mercy of the big players. I am sure Teck and Barrick are looking far into he future, but I am equally sure they have no problem using the current economic woes to manipulate deals to their benefit. It is unfortunate that companies like Barrick can do so much damage with a few printed words but it wouldn't be the first time a "partner" screwed their other partner(s).

              It has been mentioned many times that Teck likes to partner on big projects. What if Barrick and Teck want to partner up and do Schaft Creek, Donlin and possibly Galore?

              Cu63

              1. Replying to @Cu63

                I simply mean that Teck has put Galore into standby. It is not going to be developed in the foreseeable future until they can unlock the value from it.

                Donlin is fantastically expensive and complicated. It is remote which will pressure the costs even more.

                It would be nice for Barrick and Teck to realign all of this to build a larger district and group of mines they could partner on, but both are sending clear signals that big capex mines are under close scrutiny.

                All is not rosey around SC. There are headwinds for Donlin and Galore that seem to be growing, not diminishing. NG is unfortunately in the middle of both projects.

                1. Replying to @mudguy

                  hi mud

                  good seeing you back - i've been having concerns on the whole teck / galore situation since nova announced willingness to sell. course on the other side, it isnt unusual for companies to unload assets to re-invest in other parts of business.

                  do i see teck maniputing with cuu the way barrick may have done with donlin - possibly; except i believe the buy-in option could provide cuu some relief, the little i understand it.

                  jaf

                2. Replying to @mudguy

                  All is not rosey around SC. There are headwinds for Donlin and Galore that seem to be growing, not diminishing. NG is unfortunately in the middle of both projects.

                  Exactly why it is so important for Elmer to submit a bullet-proof BFS. If he also manages to keep the Capex anywhere near 3.5B, Schaft Creek will be irresistable.

                  1. Replying to @Cu63

                    I agree. Capex is everything and has been for some time, IMO.

                    So why can IMM build a copper mine with similar metal numbers in a similar location for $443M, when we hope to for $3.5B? We need to scale IMM up, say by a factor of 4 to get 120ktpd, so we are looking at a 2012 estimate of about $1.8B, assuming linear growth in costs.

                    Why are these numbers so different? Red Chris has been evaluated and updated, while SC numbers are estimated from a 2008 PFS. We will have numbers very soon, but they won't likely go down from $2.9B.

                    1. Replying to @mudguy

                      I crunched a bunch of numbers with newer metal prices, NPV discounted 5 or 8, increased CAPEX, increased OPEX, etc. ... there are so many variables here and that is why I find it so hard to predict the buyout prices. A multiple of IMM's CAPEX would be amazing, but this doesn't seem to be the case.

                      At this point, I've mostly stopped calculating the never-ending array of scenarios but firmly believe that in a worst case scenario I'll get all my money back + a little extra. I do think we'll see CAPEX and OPEX bumped up from the PFS, but hopefully this will be offset by the higher TPD. Teck's agreement a few months back with a few steelworkers unions (18% wage raise over 5 years??) is an example of the direction OPEX is going. Not going down anytime soon.

                      But, still very optimistic. Elmer and the others seem so confident in the project ... I think the draft BFS must be looking pretty good to them right now.

            2. Replying to @mudguy

              Putting Donlin and Galore aside, that leaves Red Chris and Schaft Creek as projects that still appear to be moving forward up highway 37. Here are some numbers for comparison, drawn from most recent RE and updates. Note CUU PFS (2008) are the most recent capex estimate available

              -Red Chris (http://www.imperialmetals.com/s/Development_RedChris.asp), M+I:

              2012 measured + indicated mineral resources (Copper Equivalent Cut-Off) CuEq Cut-OffTonnesCuEq %Copper %Gold g/tSilver g/tlbs Copperoz Goldoz Silver 0.5060.3200.3191.101 0.5170.3270.3271.114 0.5980.3740.3851.224
              >=0.1 1,260,268,2888,896,396,672 12,909,215 44,610,942
              >=0.2 1,218,017,6648,778,055,255 12,801,462 43,624,437
              >=0.3 936,210,4967,710,990,648 11,573,399 36,842,236

              Slightly higher grade of Cu and Au, lower Ag, no Mo.

              Capex for 30ktpd $443M, NPV ranges from a few hundred million+, depending on metal and discounting.

              Permitting advanced, but pending. Power 120 km from Bob Quinn, along public right of way. Project 23 km from paved Hwy 37, 80 km from town of Dease Lake.

              Schaft Creek: (http://www.copperfoxmetals.com/s/SchaftCreek.asp?ReportID=269883)

              Robert Morrison - Ph.D., MAusIMM (CP), P.Geo., Effective Date: May 23rd, 2012

              Resource
              Category
              Cut-off
              CuEq (%)
              TonnesCopper
              %
              Molybdenum
              %
              Gold
              (g/t)
              Silver
              (g/t)
              Measured 0.15 146,615,300 0.31 0.017 0.24 1.78
              Indicated 0.15 1,081,939,500 0.26 0.017 0.18 1.68
              Measured & Indicated 0.15 1,228,554,800 0.26 0.017 0.19 1.69
              Inferred 0.15 597,191,300 0.22 0.016 0.17 1.65

              Cu eq cut-offs are not directly comparable, but not a big issue. More Ag and Mo in SC.

              Both reflect similar metal values.

              Capex: $2.9B in PFS (2008), 80ktpd. Word is we can expect scale up of operation in BFS.

              Permitting: Enivronmental- Q4 2012, BFS due Q3 (late summer),

            3. Replying to @mudguy

              Has anyone stopped to consider the possibility of Barrick and Teck wanting to short-term shelf these two projects to partner on shaft creek? I asked this because this was something that was brought up by webgogs on a few occasions.
              1. Replying to @ldubs

                I would put other potential partners for TCK ahead of Barrick - like some of its existing partners in South America. Barrick made the bold step into copper last year with its purchase of Equinox so it is plausible that they flesh this strategy out and get involved with a greenfield project to go along with that copper producer.

                For a deposit as big and rich as the Donlin project, its economics aren't that sexy. Their Capex seems to be the big delfator there. If CUU can keep Capex reasonable, I think SC could beat it handily. Some of those shallow results from 2011 drilling (eg DDH419) should do a lot to improve the starting pit(s) scenario. The bump in grade from the 2011 drilling isn't going to hurt either.

                Capex is becoming such a wicked game. Improving metal prices go hand in hand with increased Capex costs. Projects shelved due to economics change the metal supply equations and we have a closed loop. Energy costs are a big variable too.

                From what I've seen, SC is a fairly straightforward project and a good fit for TCK. No underground operations like Pumpkin hollow - TCK can do what it does best and is set out to dominate: truck and shovel operatons. No tunnel like Galore. No fish like Pebble. And a more reasonable climate than some of those Artic porjects like Ambler and Pebble. All situated in TCK's back yard (BC) with its other interests at Galore and Teckland plus at least two other TCK exploration projects in the Dease area.

                1. Replying to @chappy726

                  Hard to see Barrick wanting to greenfield a copper project. Comments today suggest they would like to get out of copper mines altogether, with thinly veiled mention of the Equinox properties not living up to expectations. I suspect the new CEO will be steering clear of copper unless the economics are compelling, and there is a lot of gold in the mix.

                  It will be interesting to see if CIC will be involved through Teck. CIC had a terrible year in 2011, mostly due to it's commodity exposure. They have done well by Teck but that massive pot of money may be tougher to get access to compared to a few years ago. They don't seem to be backing into the Chilean projects that Teck has and is struggling with.

      1. http://www.marketwatch.com/story/barrick-announces-second-quarter-2012-results-2012-07-26-7173219

        PROJECTS IN FEASIBILITY AND PERMITTING

        Barrick is evaluating its next tier of projects. Cerro Casale and Donlin Gold do not currently meet our investment criteria, primarily due to their large initial capital investments, and under our disciplined capital allocation framework we would not make a decision to construct them at this time. However, they contain large, long life mineral resources in stable jurisdictions, have significant leverage to the price of gold, and therefore represent valuable long-term opportunities for the company. We will maintain and enhance the option value of these projects by advancing permitting activities at reasonable costs which, in the case of Donlin Gold, will take a number of years. During this time, we will monitor the attractiveness of these projects and evaluate alternatives to improve their economics. This will provide the company with the option to make construction decisions in the future should investment conditions warrant.

        Exploration

        In Nevada, over 50 drill rigs are currently operating, 12 of which are located at Goldrush. Overall, the robustness and continuity of the Goldrush system continues to be demonstrated. The limits of the entire system still remain open in multiple directions. Based on results to date, a significant increase is expected by 2012 year end to the already defined indicated resource of 1.3 million ounces and inferred resource of 5.7 million ounces(7).

        Copper

        The Zaldivar copper mine in Chile produced 73 million pounds at C1 cash costs of $1.56 per pound in the second quarter. The Lumwana mine in Zambia produced 36 million pounds of copper at C1 cash costs of $3.53 per pound.