I don't quite agree that Teck's recent issue with dumping tailings for about 100 years into a transnational waterway (Columbia River system shared by BC and Washington state) is inconsequential to CUU.

Schaft Creek flows into the Stikine. The Stikine is a transnational waterway. TN waterways are covered under a treaty between the USA and Canada and gives each country a say in how those waterways are managed.

Also, the port of Stewart is at the head of a very long inlet which straddles the USA/Canada border along its length.

Any critics of Schaft Creek being developed by TCK would look at these issues in unison. I think TCK has seen how Enbridge is continuing to fumble the ball wrt social licence and is taking a much higher and well thought out road. See oil leaks, and First Nations for an idea of how not to garner public confidence with our resources and communities.

I think TCK is coming clean and facing it's responsibility in order to provide a basis for the considerable public licence it will need to develop a project like Schaft.

I dont' think it will cost TCK that much money over time to clean up the Columbia. They have spoken for $20 for more studies. Others have said that cleanu-up costs could reach $1 billion. That $1B would be spent over decades so I think that figure would be easily digested.

We saw quite a few posts on the QB2 cancellation and extrapolated that as a positive for CUU. QB2 is a full hemisphere away from CUU. The Columbia River is arguably 'just down the river' (figuratively speaking) from Schaft. If TCK makes a mess of its role in the matter it could seriosly hamper any of its future developments.

jmho

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. Yes, but the pollution of the Columbia River started back in 1896 and there weren't any rules at that time. When the rules were established Teck was in compliance. They still dumped a lot of pollutants into the river, but have admitted it, and have been doing studies costing millions of dollars since 2004 to establish what damage was made and what the costs of restitution will be.

    Apparently, recent studies have shown that the beaches are safe for swimming, the water quality meets the US and Canadian standards and the fish is as safe or safer to eat than others in waterways in Washington State. Teck claims that the cost of clean-up will not be anywhere near $1 billion, but they are admitting culpability and are prepared to pay whatever costs can be justified.

    The fact that they are not in an adversarial position with regards to prior polluting has to be a positive sign for their plans to mine in BC going forwards.

    1. Also worth mentioning is Teck can reprocess the waste and recover the cost of cleanup. A steam plant engineer I know who worked for Teck says it will essentially cost them nothing.
        1. Civil contractor (USA) at RTA Kitimat has petitioned the gofc for allowing importation of foreign workers (labourers/carpenters) already.(2 months ago)

          There is soooo much work out there so BC projects are really getting hammered for personnel.

          RTA engineer Bechtel are begging GC's (Gen Contractors) to bid because no one is interested.

          There RFQ's are to ONT/QB companies cause everyone out here is too busy and "chaos is cash" in the construction industry.

          They are only working 6x10's whereas other job sites are 14x10's on/4 off, 21x10's/7 off...

          remote sites like SC have camps (as does RTA), some good, some bad, some "hot bunking" for thos who know what that is (old submariners term)

    2. Prospekt, once again, I completely agree with you. I should have stated my point a bit better. Teck could have gone on for another few years or decades fighting the allegations tooth and nail. Instead they saw the evidence for what it was and chose to start facing the music (or at least study it some more LOL!). The few dollars they will have to spend cleaning up its legacy of dumping (legally or otherwise) is rather small compared to the magnitude of its projects going forward.

      Other companies would have taken the litigation route. Exxon comes to mind with their big Valdez spill. The cost of the legal fight far surpassed their clean-up and compensation efforts and the litigation goes on still. Exxon many not be fighting the spill allegations in themselves but rather trying to set a precedent for the event of future spills. Fight every battle hard so the future battles are easier. That is my take.

      Enbridge's biggest hurdle in BC for their Gateway pipeline project is demonstrating good corporate responsibility and accountability for its past (and seemingly ongoing) follies. They might have the best project on paper going forward but their legacy is pulling it down hard and fast.

  2. Hey Chappy,

    Has QB2 been cancelled or just delayed due to permitting issues.

    Everyone talks of cancellation but Teck has said recently that they have growth in their internal pipeline to double CU output. Someone posted earlier that they consider back-ins part of their pipeline but sometimes I feel we are all assuming a little too much on QB2 re cancell or just delayed due to regulatory requirements.

    SB2

    1. I haven't followed it over the last couple of weeks but I think QB2 is a little of both. TCK got the project numbers back and then decided to withdraw the proposal. I think they are giving the project some more thought. The economics on the project are not that great. For almost what it cost to build SC, the QB2 project has a pretty low IRR.

      PS. Folks should remember that this IS the Off Topic forum so off topic discussion is the order of the day in here.

    2. As far as I can tell this was the last statement on the QB2 project: "Teck is in the process of reviewing comments by the regulators, after which the application will be resubmitted" From a BofA document: "We understand Chilean regulators want to obtain more information on hydrology and vegetation in the project area, and go on to say that, financing options are under consideration with the potential for an additional funding partner." It looks like they are still planning on going forward with QB2, but maybe they are looking to dilute their ownership.

      I had a short email from Teck investor relations and was told: "We wouldn't consider our decisions to exercise our back in rights on our exploration ventures as acquisitions." This might be the reference that you were looking for earlier, Skibum

      [Here's a quick summary of the project: QB2 capex is estimated at $5.6 bn (100% basis) including 13% in contingencies. The project's base case metrics include: 135 ktpd throughput, 200 ktpa copper production (0.49% grade), 5 ktpa moly production (0.018% grade) at $1.38/lb C1 cash costs]