Timeline
I just read through the MD&A and noticed that 2 peer reviews are required. The sequence of events is:
1. Complete the mine plan - DONE
2. Review the mine plan with peer group and external group
3. Complete the economic analysis
4. Review the entire Feasibility with peer group
It sounds like we are only on #2. If that is the case then we badly missed the Sept deadline of completing the feasibility. It appears Elmer hid a fairly major delay from us.