How long can they delay?

What worries me a bit is that the feasibility study is a time sensitive document. The longer they spend reviewing the data, the more out of date the data becomes. If Teck takes the whole project, it's no loss to us. If not, delaying much longer may not be in Copper Fox's best interest. Releasing a feasibility study that is months old would not impress many shareholders.

March 2012 - "Fortunately the other components of the feasibility study outside the Mine Plan are well advanced."

Sept 2012 - "The majority of the sections of the feasibility study have been drafted and reviewed."

Sept 2012 - "Moose Mountain Technical Services has completed the "Mine Plan" for the Schaft Creek project. The optimized plan will be used to complete the economic analyses and project sensitivity. All other aspects of the Feasibility Study are complete."

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. I'm trying not to worry about the Feasibility RT. I still think it will be very good, but don't like it being under wraps for so long either. I've heard some rumours that Tetra Tech didn't price the FS as nicely as CUU would have liked initially due to rising capex and there was some back and forth on this ... but who knows, they are rumours.

    That said, I would be utterly shocked if we didn't have a better FS than the PFS of 2008. At the end of the day, NPV matters a lot more than capex, especially when were talking multiple billions capex anyway. Schaft, Galore, KSM ... these are mines for the majors and it takes their deep pockets to release the multi-billion dollar profits locked up in the ground.

    I'm getting antsy for sure. Want to see those final feasibility NPV numbers once and for all to remove any lingering doubts.

    1. I'm very curious to see how things compare to the 2008 PFS. I would be quite happy if we were able to hit the 2008 numbers. We've got a few things working for us and against us.

      3 Year Trailing Metal Prices

      In 2008, each tonne of ore had a value of $42.55 using trailing 3 year prices.

      In 2012, this same ore has a value of $40.99 using trailing 3 year prices.

      Grades

      Our 2012 RE had roughly similar grades to the 2008 RE. I suspect our recent drilling will improve our starter pit versus 2008. The starter pit could provide a huge boost to the NPV.

      Operating Cost

      The 2008 operating cost was $12.49/tonne. The increased mill rate versus 2008 will lower our operating cost, but this effect may be somewhat offset by inflation over the past 5 years.

      Capital Costs

      The 2008 capital cost was $2950M for a 100,000 tpd operation. We've got the effects of inflation and the increased mill rate working against us. The bright spot is that 2008 prices were also at a commodity peak, so the inflation effect may be muted.

      Metal Recoveries

      The recovery rate for the various metals has changed since 2008. I don't think we have enough info to determine whether this impacts anything.

      1. If the recovery rate for the various metals has changed since 2008, I don't think your metric of "same ore" value of $42.55 in 2008 vs. $40.99 in 2012 is meaningful.

        I believe a more accurate comparison is the training prices of the metals which I find is:

        PFS: LME as of August 29, 2008

        Copper (US$/lb) 3.12

        -------------------------------------------------------------------------
        Molybdenum (US$/lb Cochilco) 33.00
        -------------------------------------------------------------------------
        Gold (US$/troy ounce) 692.85
        -------------------------------------------------------------------------

        Silver (US$/troy ounce) 13.09

        2012 - 3 year trailing metal prices:

        Copper (US$/lb) 3.68

        -------------------------------------------------------------------------
        Molybdenum (US$/lb Cochilco) 13.00
        -------------------------------------------------------------------------
        Gold (US$/troy ounce) 1473
        -------------------------------------------------------------------------

        Silver (US$/troy ounce) 28.46

        1. I don't know ppcguy, there are so many variables here we're guessing at, it makes one's head spin. I guess we don't know how much of each metal will be extracted per tonne precisely, so we don't really know the amount of ore to multiply by price per lb either. And how is Teck going to look at this in the end - NPV5 or NPV8, or somewhere in the middle?

          Good points earlier regarding the escalation issues for quotes, and the 30 day limit on pricing (some EPC's ask for 60 or 90 days, but 30 is the norm in my experience). The more I see of budget quotes for feasibility studies firsthand, there is a big margin for error/miscalculation. Suppliers need to cover their butts by not pricing too low, engineering firms need to cover their butts by adding in contingency, then the miner adds in more contingency ... and then most of the projects still run over when they get built, save a few! Very difficult exercise especially when a large feasibility study takes years to complete.

          The NPV5 for the 2008 PFS was $4.79B and for the NPV8 was $2.76B (before tax). Greater throughput alone could "potentially" add another few billion to these numbers, IF all else stayed the same (eg. capex/opex). If, if, if ... so many variables, and of course a good more than you list, RT (don't want to list them all!).

          Can't think about it anymore, just need the big paper to drop. Please, pretty please, hurry up with the BFS, cash and/or Teck shares.

          1. We need this to wrap up now. Not in spring of 2013. Too much money sitting in this. All because we believe in the leadership and goods in the ground. Now "heads" we see the BFS and Teck buys us out. Or "tails"here is another delay and the negative word spreads across the world. I sure hope its "heads". My painful speculation.. GLTA (as I look for a divorce attorney) UET
            1. Replying to @unearththis

              No need to speculate when you already got a glimpse of a positive NPV from the PFS - it is then a question of how much better or worse from that reference point.

              If at minimum, NPV > 0, then there is economic value.

          2. Chops, i agree all the inputs can make one's head spin! But in Finance, i have been taught that NPV is a directional measure and not an absolute measure ie. NPV > 0 is critical, after that more is better than less but what is absolutely crucial is how the NPV for all your projects compare with each other under your company's assumptions on how the world works! Fortunately Teck has a portfolio of projects to compare to and I imagine schaft creek is on the top of the list once you consider the district logistics synergies ;)

            At the end of the day, if Cuu cannot agree to a value with Teck, they can take a page from the nhl and have Teck meet with EE with a compromise of getting Teck currency in exchange so that some future / potential value can be unlocked going forward!

            That to me would be the key to getting the deal done...

            1. Replying to @ppcguy95

              To finish, i would add that Teck would have some additional strategic value from owning schaft creek that would be on Teck's ledger but would never show up on Cuu's bfs.

              U can bet that elmer and EE are on top of that!

              GLTA

          3. I work for an EPCM firm in YYC. When we do estimates we go out for budgetary pricing and the venders Are aware of this. This creates budget pricing that is inherently heavy (maybe by 10%). The quote get updated prior to construction. A good EPCM firm working in their niche will have multiple projects on the go and we know what line items are worth fairly accurately. Then at the bottom often the very last line, there is a "contingency" line item. Depending on the class of estimate (accuracy) this contingency can be 5% to 25%. Also as projects get larger your estimate gets more accurate by %. More room for high and low items to cancel out and 5% on a Billion is still $50million
            1. Replying to @Wings737

              Wings737, I don't know if you agree but estimates are somewhat like the stock market. When there's front page stories of Barrick overruning estimates, suddenly all Project Cost Estimates get that little bump in conservatism.

              I know our estimators do the same thing.

              1. Replying to @ppcguy95

                I am the estimator. I know what I do. But yes there are surprises and yes there can be overruns. Actually there will be. That's why they are called estimates and we strive to do our best
        1. No, the NTL was always part of the plan. Without it there would never be a mine.

          "While generation of power on-site is a consideration, it is felt that it would have serious implications to the financial viability of the project. Therefore at this point in the project development, it is assumed that power will be supplied from the BC Hydro grid."

    2. I agree it's hard to recalculate with the optimization of all these parameters (capex, production rates, recovery rates, metal prices, etc.) but I do expect the overall NPV to better and at minimum NPV > 0 (which starts to Teck clock!)

      GLTA

  2. In my experience, all Capital Project Cost Estimates with future in service dates include provisions for inflation and escalation. In addition, contingency is calculated on all costs.

    In more sophisticated companies (such as capital-intensive mining co's), contingency is estimated using monte carlo simulation incorporating correlation between different heavy equipment supply and commodity prices.

    Most quotes used for direct costs in Project Cost Estimates expire 30 days from the time of quotation so unless you are willing to build as soon as quotes are sought, you will need to rely on forecasts on inflation, escalation and contingency in which case the data is not as time sensitive as we all presume.

  3. OK, thanks. If u can, please show me how the math carries over using the trailing prices I have indicated and the effect of the value per ton.