WRN BFS is good

IRR 20% and 1.8 billion after tax. Copper $3 the rest, the same.

Did they low ball some of the development figures? A little bit.

2 years for enviro is a bit short.

Overall it is pretty good.

Sp responding like it should

93 million shares out.

Doesn't have a major back in deal like cuu.

Does have funding.

Does depend a bit on future technology for transport.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. It is amazing how comparable the two projects are, especially the milling operation:

    • 965Mt P&P mill reserves
    • 120ktpd mill
    • 22 year mine life
    • Same recoveries, concentrates produced
    • Similar opex per tonne
    • Same prices used (Cu $3.00/lb)

    The big reason WRN has a much better BFS is because capex is so much lower. Including a heap leach operation ($139M) a 120ktpd mill costs them only $2.9B versus CUU $4.5B. The grade is actually worse at Casino. You can ignore negative cash costs for polymetalic deposits as they are misleading whenever a by-product is more than 10-20%.

    Another point I don't understand is why does WRN have a $135M market cap? It has good research coverage and institutional ownership.

    Shaft Creek Casino
    Strip Ratio 2.0 0.59
    Tonne Ore 941Mt 965Mt
    Cu % 0.27% 0.20%
    Au g/t 0.19 0.24
    Ag g/t 1.72 1.74
    Mo % 0.02% 0.02%
    Mill 130ktpd 120ktpd
    Initial Capex $3.3B $2.5B
    Sustaining $1.2B $0.4B
    Total Capex $4.5B $2.9B
    Cash cost Cu/lb $1.15 ($0.81)
    NPV 8% $0.07B $1.8B
    IRR 8.30% 20.10%
    Payback 6.8 3.0
    1. this kind of junior explorer where cash will always be an issue (99% of them I guess) would accept a 25% premium on SP buyout tomorrow morning, not us.

    2. If we add the 171 million tonnes then it starts to look a little more interesting.

      http://agoracom.com/ir/CopperFoxMetals/forums/discussion/topics/558197-some-math/messages/1756617#message

      Shaft Creek Casino
      Strip Ratio 2.0 0.59
      Tonne Ore 941Mt 965Mt
      Cu % 0.27% 0.20%
      Au g/t 0.19 0.24
      Ag g/t 1.72 1.74
      Mo % 0.02% 0.02%
      Mill 130ktpd 120ktpd
      Initial Capex $3.25B $2.5B
      Sustaining $1.2B $0.4B
      Total Capex $4.5B $2.9B
      Cash cost Cu/lb $1.15 ($0.81)
      NPV 8% $1.9B $1.8B
      IRR 14.88% 20.10%
      Payback 6.8 3.0
      RabidTiger

      Reply in Copper Fox Metals Inc.

      Okay I redid the numbers assuming our waste rock has value. Our NPV increases from $513M to $1885M. Our IRR increases from 10.13 percent to 14.88 percent (huge improvement). For those interested, the economic numbers seem to indicate first year profit of 205M followed by 20 ye...

  2. VANCOUVER, BC: Western Copper and Gold Corporation ("Western" or the "Company") (TSX:WRN; NYSE MKT:WRN) announces that the Company and its wholly owned subsidiary, Casino Mining Corporation, have entered into a royalty sale agreement (the "Agreement") dated December 20, 2012 with 8248567 Canada Limited, an arm's length purchaser, (the "Purchaser") whereby the Purchaser agrees to cancel its 5% net profits interest royalty in the Casino Project and pay US$32 million in exchange for a 2.75% net smelter returns royalty in the Casino Project (the "Transaction").

    In accordance with the terms of the Agreement, among other things:

    1. The Purchaser will obtain a 2.75% net smelter returns royalty (the "NSR Royalty") on the future sale of any metals and minerals derived from the Casino Project;
    2. The Purchaser will agree to cancel the 5% net profits interest in the Casino Project that it already owns on certain claims held by Western; and
    3. Western will receive a cash payment of US$32 million upon completion of the Transaction for Casino Project development expenditures and general working capital.
    Western has the option to repurchase 0.75% of the NSR Royalty (resulting in a 2.00% remaining royalty) for the following amount:
    1. US$39 million if the amount is paid on or prior to December 31, 2013; or
    2. US$59 million if the amount is paid after January 1, 2014 but on or before December 31, 2017.

    1. WRN's royalty transaction closed in December so this royalty should be included in the FS numbers.

      The big reasons WRN's economics are better is because of capex ($1.6B savings versus SC and most upfront), strip, and heap leach project on top of 120ktpd mill. Grade at WRN is worse - especially Cu.

      Does anything think the drop in CUU share price has to do with WRN?

    2. Yeah, BFS is at least somewhat in line with what their PFS was.

      Will compare tonight....makes me think that CUU's PFS was either poorly done and BFS ultra-conservative.