Another date to consider

CUU has to abide by the terms of the option agreement but won't disclose how they are doing just that. The timelines must observe the following conditions:

1) Teck has 30 days from receipt of the Feasibility Notice(FN) to declare what size of project is deemed to be a PBFS( as per section 5.5 b)

2) Teck has 120 days from the delivery of a FN to exercise their Back-in Right (as per section 8.1)

3) The FN is defined in section 5.4 as the PFS and a statement of the costs to generate the PFS

We know the date that the PFS was delivered but CUU refuses to discuss if the FN, which includes costs, was given to Teck. CUU has a requirement in the option agreement to itemize all of their costs from the previous year and deliver the statement to Teck by March 31 of each year(section 4.2). So it`s possible that these `discussions` that have been occurring could consist of Teck asking CUU to delay sending some of the information required in the FN. CUU may have responded by saying alright but we must hear from you no later than March 31. It`s a possibility that allows CUU to be onside with the agreement but also gives Teck more time if they need board approval. I doubt CUU will provide any useful information at the PDAC but hope they at least attempt to spread this story around and generate new investor interest.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. The requirement in the agreement (Sectio 4.2) to deliver itemized expenditures for the previous year by March 31st could be part of the reason our year end financial statements seemed to arrive a bit earlier than expected. CUU has to the end of March to deliver the expenditures but may well have delivered them earlier to try and push the ball back into teck's court (we can hope). That would start the 45 days that teck is given to review the expenses.

    I don't like that clause in 4.2 that affords Teck a full year to audit the expenses if they don't like the look of something. Ewe! Hopefully we have our accounting of such things in order and previous years' expenditures have been gated thru.

    1. This just gets WORSE as time goes on.

      until March 31st for itemized expenditures?

      45 days that Teck gets to review expenses?

      Clause 4.2 allows Teck a full year to audit expenses if they dont like the look of something?

      30 days.........................120 days?

      clock starts Dec. 21st

      clock starts Feb4th

      Now NTL in 2013 or 2014?

      1. To be fair, these clauses were written a decade or so ago and the Agreement is publicly available. We are only catching up to these clauses now and judging by the mixed message on the 30 days (or no 30 days) from Elmer and Jason during the VRIC and a week or two after, they are too LOL!

        I believe NTL was always slated to be completed in 2014. It isn't much matter since we won't be able to use any of that power till after though our space in the cue is critical. There is enough power for about 3 Schaft Creeks and Red Chris is not as power hungry as our project so there should be enough power to go around by the time we want to flip on the switch.

        BC hydro has the construction completion as spring 2014. http://www.bchydro.com/energy_in_bc/projects/ntl/construction_schedule.html

  2. "1) Teck has 30 days from receipt of the Feasibility Notice(FN) to declare what size of project is deemed to be a PBFS( as per section 5.5 b)"

    I don't read it that way

    The intent of this paragraph is to provide Teck with the flexibility "at their sole discretion" to accept any FS that may not conform to the 2 preset conditions for automatic acceptance ie

    1. One capable of producing 25,000 tons of copper metal production for 12 years with a NPV of 12%

    or

    2. One capable of producing 50,000 tons of copper metal production for 15 years with a NPV of 8%


    The language is not artful, but the intent is obvious

    A project that clearly satisfies either of these critera meets the incentive provision to earn the Teck interests

    A mine that meets only 2. is an automatic qualifier based on size and NPV

    A mine that falls between the 2, on either size or NPV, may be deemed by Teck at its sole discretion to meet the incentive provisions, however they reserve a 30 day review period to make that determnination

    If anyone can dissect that language and get any other understanding, I have yet to hear it

    1. The phrases at least and per annum apply to both sizes, so there is some overlap. Maybe someone here knows if 5.5 a applies where, in the case of a joint written agreement on parameters before hand, then all that is necessary is a NPV of at least $ 1.00. However, I'm more concerned about the status of the feasibility notice, which appears to be key to the timelines. I'm not trying to justify what CUU is doing but rather understand what's going on. Most are feeling the pain with the intensity a function of average purchase price.

      1. We might not have delivered the FS. That would be one of the points of discussion. Teck would be shrewd over what was applicable. I got a sense that it wasn't clear cut and final two weeks ago. But this should not cause panic. All the evidence supports movement towards a mine and that is the one thing any sale or deal will require. There has to be a reasonable assurance this will be mined.

        1. "We might not have delivered the FS. That would be one of the points of discussion."-Webgogs

          Ah geeze Web, what kind of can of worms would that open? I don't think it's even possible or else we have all been lied too.

          1. I didn't see an official statement outlining applicable expences nor notice of feas. What we did get was skillfully crafted to avoid telling us when the 30 days was up.

            They have an obligation to inform us of when the 30 day clock starts. Instead we get the broader 120 days. The 120 days seems to be governed by the acceptance clause yet this detail was omitted because the company seems to consider it a slippery slope and cited underlaying agreements we are not privy to that will govern the final outcome. Omitting the details of these agreements might seem like lying but it isn't.

  3. Plausable for sure. Probable? Shoot me! As, in this case, the clock would NOT be started. And, as alluded to before, IMO, IF I were Teck, I'd be using every last trick in the book to delay any start of a 120-day clock and by extension the contractual necessity to officially hand over Liard shares, in order to further derisk (not to mention while watching the X-day moving average drop even further). Please, please, please let that scenario NOT be reality. Why would we lose our tempers, indeed? We're getting so much entertainment value losing our money?! Please don't let this be the scenario. I can't wait another ice age. NEED ROI NOW!

    Fretting, I know, but what else can a guy in the dark do?!