Anyone able to get a hold of anyone at Bison. Tried the email provided on the CNSQ website bit it was returned invalid. At least we have an operational update. Better than anything we get from SGR. Maybe SGR should move to the CNSQ that way they will have to be more transparent.

http://www.cnq.ca/Storage/1242/111979_Form_7_-_OCTOBER_09.pdf

Join the conversation about Cougar Minerals Corp.

Reply

Replies

  1. Bid
    # Orders # Shares Price
    1 500 0.215
    2 15,000 0.20
    1 15,000 0.19
    1 10,000 0.18
    2 115,000 0.15
    Ask
    Price # Shares # Orders
    0.245 10,000 1
    0.255 10,000 1
    0.27 10,000 1
    0.35 10,000 1
    0.45 20,000 1

    Market Book For BGE

    the bid side is building , the ask side is thining, Long On The Greens. Traps7

    1. Central Manitoba and Cryderman

      Location: Rice Lake greenstone belt, 25km South East of Bissett, Manitoba

      Project Area: 26 mining claims, 12.2 sq miles

      Holdings: 100% Interest

      •

      The Bissett Gold Camp has a history of exploration dating back to the 1930’s. The claims

      cover the site of past producing mines with nine mine shafts and known gold mineralization.

      •

      Within these claim boundaries, the Central Manitoba mine produced 137,817 oz Gold at an

      average grade of 0.36 oz/t and the Rockland-Ogama mine produced 45,445 oz Gold at an

      average grade of 0.33 oz/t.

      •

      The Rice Lake/Bissett Gold Mine is located on this greenstone belt and operated continuously

      from 1932 to 1968. It has produced 1,462,055 oz Gold at an average grade of 0.26 oz/t. and it

      recommenced production in April 2006.

      •

      The primary goal of the most recent exploration programs on the Central Manitoba and

      Cryderman Properties was undertaken by Placer Dome under the terms of an Option

      agreement with Mid-North.

      •

      2003 exploration comprised; Aeromagnetic Survey - Rock & Soil Geochemistry -

      Biochemistry.

      •

      Geological report for Placer Dome (B. E, Mitten - dated Dec 18, 2003) identifies expenditures

      of $190,000.

      •

      The Diamond Drill Program in 2004 intersected grades 20 to 165 grams/t Gold.

      •

      The Geological report for Placer Dome (J. W. P. Lengyel) dated Sept 7, 2004 identifies

      expenditures of $415,000.

      •

      On August 20, 2004 Placer Dome advised Mid-North of its decision not to continue with the

      option, resulting in Mid-North regaining 100% ownership of the properties.

      •

      Geological Report (NI 43-101) for Mid-North (G. S. Carter - dated June 17, 2005) and for Bison

      (G. S. Carter - dated December 29, 2005) has recommended expenditures of $575,000 stage (1)

      and a further $1,050,000 stage (2).

      Current Project:

      Bison is aggressively exploring and developing the Central Manitoba and

      1. CENTRAL MANITOBA

        Location: Rice Lake greenstone belt, 25km South East of Bissett, Manitoba

        Project Area: 26 mining claims, 10.9 sq miles

        Major Minerals: Gold

        Holdings: 100% Interest

        Exploration History

        •

        The Bissett Gold Camp has a history of exploration dating back to the 1920’s. The claims

        cover the site of past producing mines with nine mine shafts and known gold

        mineralization.

        •

        Central Manitoba mine produced 160,034 oz Gold at an average grade of 0.37 oz/t (1927 -

        1938) at depths to 200m.

        •

        Rockland-Ogama mine produced 45,440 oz Gold at an average grade of 0.33 oz/t (1942 -

        1943 and 1948 - 1951) at depths to 300m.

        •

        The Rice Lake greenstone belt and its equivalent in Ontario, the Red Lake greenstone

        belt, are important Archean lode gold mining areas. There are more than 200 gold

        occurrences in the Rice Lake greenstone belt, most of them associated with quartzveining

        in Neoarchean rocks, including the expected phases of brittle deformation.

        •

        The Rice Lake/Bissett Gold Mine is located on this greenstone belt and operated

        continuously from 1932 to 1968. It produced 1,462,055 oz Gold at an average grade of

        0.26 oz/t. Since 1994, over $120 million has been spent on the Bissett Gold Mine and this

        important gold deposit recommenced production in April 2006.

        •

        The primary goal of the most recent exploration programs on the Central Manitoba and

        on the nearby Cryderman Properties was undertaken by Placer Dome under the terms of

        an Option agreement with Mid-North Resources Limited.

        •

        2003 Exploration: Aeromagnetic Survey - Rock & Soil Geochemistry - Biochemistry.

        •

        Geological report for Placer Dome (Bruce E, Mitten - dated Dec 18, 2003) identifies

        expenditures of $190,000.

        3

        •

        2004 - 2,733m (8,880ft) Diamond Drill Program intersected moderate and high grade

        Gold at the Rockland-Ogama mine at 260m to 460m depth, and at the Valley Vein at 20m

        to 70m depth with grades up to 165 grams/t.

        •

        Geological report for Placer Dome (J. W. Patrick Lengyel) dated Sept 7, 2004 identifies

        expenditures of $415,000.

        •

        Geological Report (NI 43-101) for Bison Gold (G. S. Carter - dated December 29, 2005) has

        recommended expenditures of $575,000 stage 1 and a further $1,050,000 stage 2.

        •

        2006 - Systematic till sampling program of Cryderman & Central Manitoba claim groups.

        Five additional target areas identified.

        •

        Geological Report (NI 43-101) for Bison Gold (David J. Busch - dated April 26, 2006)

        identifies expenditures of $53,864 and has recommended diamond drilling to follow up

        on till sampling program results.

        •

        2006 - 1,010m (3,300ft) Diamond Drill Program at the Central Manitoba mine intersected

        a discovery in the Wentworth Vein with moderate and high grade Gold at 40m to 60m

        depth with grades up to 17.3 grams/t.

        •

        Geological Report (NI 43-101) for Bison Gold (Watts, Griffis & McOuat - dated January

        17, 2007).

        Current Project:

        Based on the positive results of the previous 2,700m drill program and the NI

        43-101 Geological Report, Bison Gold began a soil till sampling program to further develop the

        work previously undertaken by Placer Dome and to identify new targets for a future diamond

        drill program in the summer of 2006. Five additional target areas were identified and classified.

        The two top priority targets were selected for further ground geophysics. A subsequent diamond

        drill program of 1,010m (3,300ft) at the

        Central Manitoba mine

        area was completed in the

        summer of 2006. The cost for this program was approximately $200,000 and comprised nine

        short holes (50m to 76m) on the Wentworth vein (which lies roughly midway between the former

        producing Kitchener and Tene mines) and one deep hole (454m) under the Tene mine. The best

        results came from holes CM-06-1, -7 and -8, which intersected core lengths, based on weighted

        average analysis of;

        CM-06-1 4.13 g/tonne over 3.83m (0.12 oz/ton)

        CM-06-7 4.47 g/tonne over 2.01m (0.13 oz/ton)

        CM-06-8 3.63 g/tonne over 4.14m (0.11 oz/ton)

        Higher grades were intersected over narrower widths.

        Hole No. Interval (m) Core Width (m) Au (g/tonne) Au (oz/ton)

        CM-06-1 41.29 - 41.59 0.30 10.36 0.302

        43.93 - 44.28 0.35 17.31 0.505

        CM-06-7 40.85 - 41.48 0.63 9.00 0.262

        CM-06-8 53.36 - 54.03 0.67 9.27 0.271

        55.30 - 55.89 0.59 10.14 0.296

        These results suggest the presence of a shallow west-plunging mineralized shoot that warrants

        further drilling. In November 2007, Phase 1 drilling of 4,000m commenced. 1,000m of Phase 1

        drilling was completed in 2007. The best results came from holes CM-07-1, -2 and -3, which

        intersected core lengths, based on weighted average analysis.

        CM-07-01 7.1g/t over 0.43m (0.24 oz/t)

        CM-07-02 15.5g/t over 1.91m (0.54 oz/t)

        CM-07-03 7.0g/t over 2.79m (0.24 oz/t)

        During the first quarter of 2008, the company completed a 3242 meter drilling program on the

        Central Manitoba property. The drill program comprised 16 holes which ranged individually

        4

        from 62 meters to 452 meters in drill depth. Of these holes, six were stepouts extending the

        Wentworth vein along strike to the west, six were drilled between the Kitchener, Tene and Hope

        shafts along the Central Manitoba zone, three were drilled under the old mine workings, and one

        was a wildcat hole to the southeast along the prospective gabbro sill.

        Results were received on four of the 16 drill holes, including CM

        ‐08‐1, ‐2, ‐3 and ‐6. Hole CM‐08‐

        1

        was drilled directly under the old Hope mine workings, intersecting a strong shear zone, but only

        minor gold values including 1.0 g/t Au over a drill width of

        ‐.30m. Hole CM‐08‐

        2 was a wildcat

        hole drilled several hundred meters southeast of the Hope mine along the prospective gabbro sill,

        but no significant gold values were cut. Drill hole CM

        ‐08‐

        3 was collared between the Tene and

        Hope shafts, and intersected several strong shear zones, with minor gold values up to 1.1 g/t Au

        over a drill width of 0.62m.

        Drill hole CM

        ‐08‐

        6 was drilled between the Wentworth vein, which has been the focus of most of

        the company’s recent drilling, and the Tene mine. This drill hole, oriented at

        ‐

        50°/015° azimuth

        across the prospective zone, intersected a mineralized, quartz

        ‐

        veined shear zone that returned 6.0

        gAult/2.98m [truth width 2.41m] at 70.70

        ‐73‐

        68, including 10.4 gAult/1.55m [true width 1.26m]

        at 72.13

        ‐73‐

        68m down hole. This new intersection, being called the Tene West vein, appears to be

        a strike extension of the Tene mine veins.

        Also during March, Bison Gold acquired by staking a 41 hectare claim lying immediately south of

        the Central Manitoba zone dove claim. This claim will cover any down

        ‐

        dip extensions that may

        arise from deeper drilling on the south

        ‐

        dipping Central Manitoba shear structure. The previous

        holder of this claim was Icon Industries.

        In the second quarter of 2008, significant gold intersections were returned in holes CM-08-4, -6, -

        8, -9 and -10, from the 16 hole 2008 program. The remaining holes all intersected strong, locally

        quartz-veined, shear structures, with anomalous gold values, but grades in these other holes

        were generally less than 1gAu/t over mineable widths. The significant intersections are

        summarized below.

        Hole No. Interval (m) Core Width(m) True Width(m) Au (g/t)

        CM-08-4 190.92-193.35 2.43 0.83 42.5

        and 206.85-209.89 3.04 1.74 10.0

        CM-08-6 70.70-73.68 2.98 2.41 6.0

        including 72.13-73.68 1.55 1.26 10.4

        CM-08-8 21.57-22.79 1.22 0.86 4.3

        CM-08-9 29.08-30.37 1.29 0.83 3.7

        CM-08-10 38.22-40.14 1.92 0.66 6.1

        Estimated true widths for the above intersections were calculated from the core angles of veins

        and schistosity as noted during core logging. The weighted average grades for drill hole CM-08-4

        in the above table include assays which were in excess of 1 ozAu/ton (34.3gAu/t), and are uncut

        for this calculation.

        The most interesting results from this program were returned from hole CM-08-4, which was

        oriented at -55°/015° azimuth, and designed to intersect the Tene mine structure at a depth of

        roughly 200m at a point about 100m east of the ends of the deep exploration drifts from the 1930s.

        This drill hole intersected 42.5gAu/t across a core width of 2.43m at 190.92-193.35m, and a second

        intersection of 10.0gAu/t across 3.04m at 206.85-209.89. These intersections, termed the Tene East

        zone, occur in sheared gabbro that is quartz-veined and mineralized with chalcopyrite, pyrrhotite

        and local visible gold. It appears likely that this drill hole has intersected a southeast-plunging

        5

        extension of the Tene mine veins or possible new en-echelon vein within the Central Manitoba

        structure.

        Drill hole CM-08-6, which was reported in the company’s May 23/08 news release, intersected

        6.0gAu/t across 2.98m at 70.70-73.68, including 10.4gAu/t over 1.55m at 72.13-73.68. This

        intersection, called the Tene West vein, is situated between the Tene mine and Wentworth vein,

        at a point roughly 100m west of the west end of the shallow stopes in the Tene mine. This drill

        hole was oriented at -50°/015° azimuth and designed to test westerly extension of the mine

        structure at roughly 50m depth.

        Drill holes CM-08-8, -9 and -10 were all drilled from the same set-up, at -45°, -60° and -72°

        respectively, toward an azimuth of 015°, to test the westerly extension of the Wentworth vein.

        The Wentworth vein had previously been drilled in both the 2006 and 2007 programs. These

        holes in the 2008 program were collared at a point 40m west of holes CM-07-1, -2 and -3, which

        had intersected interesting gold values, including 15.5gAu/t over a core width of 1.91m. Drill

        holes CM-08-8, -9 and -10 cut 4.3gAu/t across 1.22m, 3.7gAu/t over 1.29m, and 6.1gAu/t across a

        core width of 1.92m respectively. Drill holes CM-08-11, -12 and -13 were drilled a further 80m

        west of holes CM-08-8, -9 and -10, and intersected a strong, quartz-veined shear structure, but

        gold values were low. From the 2006, 2007 and 2008 drilling, the mineralized zone along the

        Wentworth vein appears to have a strike length of about 120m and is open at depth. Drilling to

        date along this vein has been very shallow and has not tested below about 50m depth.

        Bison Gold intends to undertake a followup drilling program on the Central Manitoba property

        to test both the new Tene East and Tene West discoveries, further delineate the Wentworth vein

        to depth, and drill under the old Ogama-Rockland gold mine, situated about 5km southwest of

        the Central Manitoba mine. The Ogama-Rockland mine produced 45,440 ounces of gold at an

        average grade of 0.33 oz/t in its 1948-51 production period, and these veins are believed to

        extend well below the bottom of the mine workings at a depth of 200m.

        Recommendations for the scope of the next phases of exploration on the property are

        documented in the NI 43-101 Geological Report. For 2009, the following programs is budgeted:

        Phase 2 Drill Program Budget Estimate $500,000

        CRYDERMAN

        Location: Rice Lake greenstone belt, 20km South East of Bissett, Manitoba

        Project Area: 5 mining claims, 1.3 sq miles

        Major Minerals: Gold

        Holdings: 100% Interest

        Exploration History

        •

        Close proximity to Central Manitoba property hosting;

        1. Apparently the amount to be drilled has increased from 9000 M to 13,000 M due to a good price on drilling from Wynne drilling.

  2. That is one of the things I really like about the CNSX. It appears that they require listing companies to issue the Form 7 every month which is a complete update of any material changes or lack there of. Maybe moving to the TSX -V might not be a good thing after all. I suppose the ability to trade online at discounted fees will be a good thing however.