Quick question

Does anyone know if KRY is receiving any credit or reimbursement from the Chinese for the millions spent on social projects as required by the MOC?

TIA

Join the conversation about Crystallex International.

Reply

Replies

  1. The Chinese are paying for 2/3 of billable items. At least that is what I have gathered from others here.

    1. My sense of the agreement is that KRY's past expenditures on social programs (e.g. the medical facility, roads, etc), required to remain compliant under the terms of the MOC, do not figure in the agreement and therefore have been absorbed by KRY shareholders.

      While this shortcoming is not a dealbreaker by any means, I would think that CRRC should have been pinned to 2/3 of the compliance costs - easier said than done, no doubt.

      1. "My sense of the agreement is that KRY's past expenditures on social programs (e.g. the medical facility, roads, etc), required to remain compliant under the terms of the MOC, do not figure in the agreement and therefore have been absorbed by KRY shareholders."

        Actually the "Final Binding Primary Agreement" is very clear on the past expenditures question.

        Section 3c on page 4 states that:

        "CRRC acknowledges that Crystallex has commissioned a detailed report by SNC Lavalin, updating the capital and operating cost estimates set out in the Feasibility Study (the “Updated Cost Report”). The out-of-pocket costs associated with obtaining the Environmental Permit and associated consents and the Updated Cost Report shall be borne as to one-third by Crystallex and as to two-thirds by CRRC with the Crystallex obligation to be funded as part of the loan obligations under the Joint Venture Agreement."

        In my opinion the ".. The out-of-pocket costs associated with obtaining the Environmental Permit and associated consents and .." clause would include the disbursements necessary for all social projects, infrastructure (roads, airport, water, etc), and anything else that Venezuela had required from KRY. Based on the section quoted above CRRC would be obligated for 2/3's of these costs.

        1. I'm not at all certain that the clause mentioned is backward-looking except on the actual cost of obtaining the Updated Report.

          Anyone corresponding with RM may wish to clarify this point.

        2. I agree fully with your clear reading of the primary agreement, of course the detailed work to decide what expenses are "associated" with obtaining the permit is still pending. IMO pretty much everything we've spent in VN will qualify.

          RM has no more understanding of the details than the plain wording of the agreement at this point, so those who want to discuss it with him will probably find no help at this point. The fine details remain to be negotiated, but I doubt there are any material amounts not agreed to in principle.