Please view the new video of the plant, aerial photos of the Catanava project and surrounding area, and the most recent photos in “Plant Sequence” from last week’s site visit:
· Working on slurry pump and choke for cyclone
· Constructing Guard Tower and equipment storage room for tools, equipment, motors, supplies
· Constructing cement columns for room
· Laid out PVC pipe for tailings trough
· Plant offices are complete with upcoming Internet connection
· Military visit re Explosive permit is expected in July
· Preparation at Camino Shaft Surface