SUMMER 2008 MOL GROUP’S BUSINESS MAGAZINE


MOL has begun activites into a new area of exploration. Increasing crude oil and energy prices, coupled with the shrinking of hydrocarbon resources accessible via traditional methods, has led to a redirection of attention into unconventional energy sources. MOL and Exxonmobil have launched a joint exploration, targeting at developing unconventional gas resources in the Mako Basin.

Unconventional gas resources might exist within geological structures and conditions different from conventional ones, thus they are only accessible by applying new drilling and exploitation technologies which are incomparably more expensive than recently applied technologies. Some resources may be developed profitably by conventional methods, whilst others require far greater efforts and much more financing.

Hungary is in a fortunate position as there might be huge unconventional gas resources, which are worth developing due to the recent energy prices. ‘True, we have just started to make more serious efforts to explore these resources, but the preparation was begun years ago. As for the existence of unconventional gas resources requiring completely new production technologies, we have been aware of this since the 1970’s and 80’s,’ explains Attila Holoda, MOL’s Vice President of Eurasian Exploration and Production.

Early hopes

A number of exploratory wells were financed by the World Bank (e.g. near Algyő, Hódmezővásárhely and Makó), and the company found that there was a declining indication of gas from these wells, which eventually stops entirely and the traditional methods yield no gas at all. The explanation for this phenomenon is that the gas is held by extremely tight sandstone rocks, which are highly impermeable. Thus it is not enough only to drill into the targeted structure – a way needs to be discovered to allow the gas be collected from these microcaverns and be transferred into tubing. For this to happen, the layer needs to be fractured.

During the hydraulic fracturing, the layer will be filled with the special material called propant, which creates an artificial permeability between the rocks and the
well itself. Although the fracturing technology itself is well known and has been widely applied for a long time, the existing geological conditions, high temperature and high pressure, are so unique at this basin, that the known procedure required major extra development before application. Geological risks and expected costs were extremely high and the market price of hydro-carbons was far below the current level, therefore efforts and development were cancelled.

During the decades which have passed since then, many Hungarian and international companies have explored hydrocarbons in Hungary. Some also made efforts in the unconventional basins, but so far not a single commercially marketable molecule has been produced from any of these. This is how the attempts by TXM Ltd.(a daughter company of a Canadian oil company, Falcon Oil and Gas) ended, even though they claim to have spent over $300 million on a Croatian drilling rig, American fracturing services and a 3D geophysical survey in Hungary. This company raised the possibility of huge unconventional gas reserves amounting to 600 billion cubic metres (later they even spoke about 1200 billion at one time 1500 billion cubic metres) and that Hungary may well become self-sufficient in gas and, in time, may even be able to export a considerable quantity.

Joint efforts for success

Based on present information, MOL currently estimates a recoverable gas reserve of up to 340 billion cubic metres. ‘The discrepancy between the two estimates does not come from any calculating errors, explains Attila Holoda, but probably from the size differences of the geological structure considered. TXM has estimated the whole reserves existing in the total Makó basin, while MOL only calculated that the upper formation of the structure, promises real production. TXM had been investigating the possibilities of the Makó basin for four years, when in 2006 MOL also decided to return to its previously interrupted project and join in with the unconventional exploration.

Wishing to share the geological and technological risks and extremely high costs of this new kind of exploration with a partner, they negotiated with several experienced companies and eventually agreed, in 2006, to conduct a joint technical study in co-operation with Esso, the European subsidiary of ExxonMobil. In the meantime, from the end of 2007 onwards, TXM had also been seeking a strategic partner to continue and finance its previously started exploration projects. Eventually, in early April 2007, it also chose ExxonMobil for carrying out a multi-stage exploration program in the Makó trough. Since, in accordance with the agreement between MOL and ExxonMobil, the Hungarian company had an option on entering the venture, not much later, when MOL acquired a 50% share of ownership in ExxonMobil’s share of TXM-Falcon exploration block, the three companies joined forces. The operator of the joint efforts will be ExxonMobil

Long term plans

Attila Holoda explained that in the first phase, the project entailed practically no costs for MOL. ExxonMobile drills two new wells in MOL’s acreage this year
and during the same period will test two existing exploratory wells in the TXM area.

Despite the fact that MOL and ExxonMobil have targeted more easyto-explore and more easy-to-produce gas resources than TXM are interested in, they are more careful on speaking about the potential of further production. There is no talk of gas exports; they are not even saying that the available technology might be applicable for lifting the gas existing at 300°C and a pressure of nearly 100 bars using the fracturing technique. All they are claiming for the time being is that after the successful well-testing, they hope to start the production in the Makó trough between 2012 and 2014. This should be preceded by sustained preparations,as unconventional exploration is much more costly than the conventional one. The wells need to drill deeper and the required number of wells is much higher than in conventional cases. It is estimated that around 2000 wells are necessary to acquire the whole gas reserve. Based on existing drilling service capability, MOL is expected to drill around fifty new wells per year. Interestingly, currently there are around 8300 wells in the country, 5100 of which are owned and handled by MOL, only a few hundred of these are still producing crude oil or natural gas


Differences in costs

While the drilling costs of conventional gas wells are between $2–3 million, unconventional wells may reach three or four times this amount. On top of it, 50 unconventional wells will require some new surface facilities costing approx. $30–40 million. However, according to MOL’s estimates, producing one barrel of (oil-equivalent) gas will cost only $2–3 due to existing low production costs, as MOL is the most cost efficient upstream company in Europe. MOL would utilize a technology specially reapplied and adjusted to the Hungarian conditions, developed earlier by ExxonMobil for production of unconventional hydrocarbons. The technology was already widely applied in the USA , and might promise further success in Hungary as well. At the same time, conditions here are very different from American ones – temperature and pressure are much higher and the targeted structures are very different regarding their geological age.




Join the conversation about Falcon Oil and Gas Ltd.

Reply

Replies

  1. TXM had also been seeking a strategic partner to continue and finance its previously started exploration projects. Eventually, in early April 2007, it also chose ExxonMobil for carrying out a multi-stage exploration program in the Makó trough.

    Somebody ought to tell MOL Group Business Magazine get their facts straight :)

    1. >Somebody ought to tell MOL Group Business Magazine get their facts straight :)

      It's just a typo, going by the previous sentence.



      ...from the end of 2007 onwards, TXM had also been seeking a strategic partner to continue and finance its previously started exploration projects. Eventually, in early April 2007...













      1. Based on present information, MOL currently estimates a recoverable gas reserve of up to 340 billion cubic metres. ‘The discrepancy between the two estimates does not come from any calculating errors, explains Attila Holoda, but probably from the size differences of the geological structure considered. TXM has estimated the whole reserves existing in the total Makó basin, while MOL only calculated that the upper formation of the structure, promises real production.



        It's still unclear as to what MOL's number represents. TXM's numbers DO NOT represent the total of the Mako basin, they are the Scotia report numbers, which only represent the total of the area underneath the production licence.

        Do MOL's numbers represent the same area, just their area, or both?

        My guess is that MOL's numbers represent the technically recoverable gas of the Szolnok, in Falcons production licence area only. The reason being that at the time, they had yet to drill any holes in their area, and therefore hadn't even confirmed the existance of gas, never mind how much there might be in place.

        In any case, both numbers are close. 12 TCF from MOL, 15.7 from Falcon (P90) technically recoverable from the Szolnok, both conservative estimates.

        Thats a heck of a lot of gas.



























        1. Based on present information, MOL currently estimates a recoverable gas reserve of up to 340 billion cubic metres. ‘The discrepancy between the two estimates does not come from any calculating errors, explains Attila Holoda, but probably from the size differences of the geological structure considered. TXM has estimated the whole reserves existing in the total Makó basin, while MOL only calculated that the upper formation of the structure, promises real production.



          It's still unclear as to what MOL's number represents. TXM's numbers DO NOT represent the total of the Mako basin, they are the Scotia report numbers, which only represent the total of the area underneath the production licence.

          Do MOL's numbers represent the same area, just their area, or both?

          My guess is that MOL's numbers represent the technically recoverable gas of the Szolnok, in Falcons production licence area only. The reason being that at the time, they had yet to drill any holes in their area, and therefore hadn't even confirmed the existance of gas, never mind how much there might be in place.

          In any case, both numbers are close. 12 TCF from MOL, 15.7 from Falcon (P90) technically recoverable from the Szolnok, both conservative estimates.

          Thats a heck of a lot of gas.

          Hi lanman

          When the MOL figures cited in this article were first published (link: http://www.google.co.uk/search?hl=en... )

          I rang up MOL and asked them a number of questions. One of the questions was whether the 340bcm was the total risked resource for the whole trough and they said it was but it was very conservative. Here is a link to a long post where I set out the substance of those conversations and a model.

          http://boards.fool.co.uk/Message.asp...

          I agree, of course, that either way we are discussing a "heck of a lot of gas".

          HTH

          KoD



          (Below is the text of my linked post)

          28 April 2008

          Introduction

          As many followers of Falcon will be aware, a couple of weeks ago MOL, the national Hungarian oil and gas company who is now part of the JV with Falcon and Exxon, published a presentation on the Mako trough. Here is a link: http://www.mol.hu/en/about_mol/inves... .

          Much of the presentation is pretty standard background stuff but pages14-16 provided some figures which have sparked some pretty hard work on the part of Hallucigenia and me over the last fortnight. This post is the culmination of that work. I must straight away pay tribute to H’s incredibly hard work which has helped me enormously in writing this post and invite you to rec everything he writes for the next month in partial thanks if you find this post useful.

          This post falls into two main parts. Firstly, I will be discussing the detective work that has gone on to try and understand, model and in some cases correct the figures given out by MOL. Falcon has not exactly been free with its well information over the last few years and it has been a revelation to have some figures to actually work upon. Anything that MOL say is likely to be derived from their joint study undertaken with Exxon last year. As a result it is not clear how far their figures relate to Falcon’s data room or from analogy with US BCGAs particularly Exxon’s holding in Piceance basin. Secondly, I attempt to explain the modelling I have undertaken to value this stock along with other cruder valuation methods.

          The Detective Story

          When H and I first spoke on the phone about the MOL presentation, a number of issues immediately arose. Before addressing them, it would probably be useful to set out the facts and figures that MOL put in the presentation in summary form

          MOL’s assumptions:

          1. The Mako Area has been arbitrarily split in two, labelled Mako East and Mako West (pg4)
          2. The total resource contained in the basin is 2000mmboe or 12tcf (pg15)
          3. 30% of the resource could be recovered in 30 years at 50 wells per year
          4. The total resource could be drained by 2000 wells
          5. 2-3 wells per sq km implies well spacing at 80-120 acres
          6. Payback is 2-3 years for a well
          7. Total acreage under licence was 1567 sq km
          8. Acreage split 40% MOL, 40% Exxon, 19% Falcon
          9. Oil services in Hungary would have to grow
          10. Surface facilities: USD22-28m + USD6-11 per year
          11. OPEX: USD2-3/boe or USD0.33-0.5/mmcf
          12. Well cost: USD8-12m each
          13. High initial production
          14. Rapid production decline to a relatively low but sustainable level
          15. Total production 0.15-0.225 MMcm
          16. 30 year lifetime for wells (graph pg 16)?


          Four major issues arose:

          1. The total acreage was clearly wrong.
          2. It was not clear if the figures were gross or net to MOL
          3. The total production per well was wrong by a factor of a 1000
          4. No indication was given as to whether the figures were risked or not

          So I decided to ring them up.

          If you look back at the Falcon board and the IV board over the last couple of weeks, you will see a number of people tying themselves up in knots trying to make sense of the figures in the presentation. There is no substitute for getting the bull by the horns and actually doing some DD yourself sometimes. And then passing that on to the TMF readers, naturally.

          MOL IR Dept

          Charming group of people. Unfailingly polite, they immediately apologised for the confusion and promised to get back to me very quickly. When contact was made, they not only apologised for getting it wrong but then amended the presentation immediately! You will understand that H and I have been feeling somewhat smug for the last week or so.

          The corrections:

          1. The total acreage is now listed as 2769 sq km, although the percentage stayed the same
          2. The total resource is gross for the Mako trough
          3. The 0.15-.225MMcm was changed to 150-225MMcm=5-8bcf
          4. The 2000mmboe was stated to be a risked figure
          5. Other things were confirmed in the conversations and some of those will become clearer later in this post

          H does a Sherlock Holmes

          If you look at the presentation, it is pretty clear that all the figures are risked. The only exception to that is items 10-12 above – it makes no sense to “risk” capex and opex costs. H then worked out (and I took a while to understand this) that the $2-3/boe and the $8-12m per well could give us a rough idea of the risking that MOL had applied. If we take the most expensive well ($12m) and the cheapest OPEX ($2/boe), and divide the $2/boe into $12m, you get a maximum total of 6mboe per well which is roughly 36bcf total production. If you take the other extreme of $3m/boe and $8m cost of well then you get 2.7mboe which is 16bcf. The best guess is towards the lower end of that range. So the unrisked total projected production of an average well according to MOL is16bcf-36bcf

          Deducing MOL’s risking

          If you take the total production of the basin as 2000mboe=12tcf and divide that by 2000 wells you get 6bcf per well which nicely matches the graph on page 16 which says total production ranges between 150bcm-225bcm which is roughly 5-8bcf risked.

          If we take 6bcf as the risked figure we can then see that the 16-36bcf per well figure unrisked suggests a risking applied by MOL of 16-38%. The 5-8bcf graph suggests a slightly tighter risking of say 22-31% risking. The average for both these ranges is 27% so I think a general risking of 25% may not be too wide of the mark as to what MOL are thinking.

          Total resource in the basin

          Armed with that risking figure, we can start to have a stab at how MOL think the play could be modelled and valued. If they are saying that the total risked resource of the play is 12tcf then MOL are suggesting the total unrisked resource in the trough could be 32tcf-72tcf but lets say 48tcf.

          If we split the Mako resource in half (even though it is arguable that more of the resource is in the East) we get gross unrisked P50 of 16-36tcf, say 24tcf. Falcon own 1335sqkm outside the Production Licence (note the graph says areas under licence) and 33% of the JV area plus 100% of the remainder of the PL totalling around 500sqkm in the PL. This may explain the pie chart because 500sqkm is indeed around 19% of the expressed new total of 2769sqkm. This presentation therefore ascribes no value to any gas in the other 1335sqkm owned by Falcon.

          If we say, then, that Falcon own 33% of 75% and 100% of 25% of the PL, that is 50% and discount that a bit because presumably Exxon have tried to get the best chunk of the PL, then a conservative percentage of the PL net to Falcon would be 45%. Therefore Falcon could be said to have net 45% of 16-36tcf which is 7-16tcf, say an unrisked gross recoverable resource to Falcon of 10tcf.

          The full 10tcf could to take 100 years to extract, so you have to take a view as to what would be recovered in the initial licence phase (disregarding the option to extend at this stage) and in addition what production is material on a discounted NPV basis. MOL assume a 30% recovery over 30 years (assuming 50 wells per year) which suggests 3tcf recoverable P50 net to Falcon.

          Risk that 3tcf at 25%. Therefore, MOL’s assumptions as set out in their presentation suggest that Falcon has a net 750bcf risked P50 recoverable resource.

          Modelling

          This was where I took over. I spent a considerable amount of time after conversations with H discussing these issues attempting to put a model together.

          Here are the assumptions I set out at the beginning of that model:

          • The model is driven from the MOL presentation and the conservative estimates in there
          • The model assumes that each well drains roughly 20bcf
          • The model flexes the decline rates in four different ways to reflect slow and rapid rates of decline
          • The outcomes are very sensitive to well numbers. MOL are sceptical about the ability to drill more than 50 wells per year. The NPV is very sensitive to this bottleneck in particular
          • Total resource extracted over 30 years from the basin is around the high teens tcf
          • The percentage owned by Falcon assumes 50% split Mako West/East and 45% of the remainder owned by Falcon
          • Discount rate is 10% - economics are far better at 8%
          • This model puts no value on the Basal Conglomerate
          • The gas price is assumed to be $7/mcf which is low but then the cost of drilling is assumed to be constant as a counterbalance to that
          • The $0.5 per bcf is very arbitrary - we are still waiting to get better comfort on that number from MOL
          • The initial flow rates are worked backwards assuming various decline rates and flat rates of gas after time so that the total is 20bcf
          • The data table on the first page flexes the gas price and the well cost (not including the tie-in figure of $3m which is constant)
          • Royalty is set at 12%+5% for Gustavson (Prospect Resources). Corporation tax is 16%
          • Production is presumed to run for 30 years
          • All figures in USD - I have assumed parity with C$ for the per share valuation
          • Version 1.2 - I have moved the whole project out by a year so the 50 well per year programme now starts in 2010, I have arbitrarily assumed they do a third of that in 2009
          • MOL calculates the payback period as 2-3 years which suggests low but steady flows. 50 wells per year producing 30% over 30 years is consistent with that. Whether that is correct will only be determined by testing
          • Version 1.3 type 3 models a flat production with no decline

          The steps of the model:

          1. Firstly I guessed a production curve for a typical well
          2. I assumed a total production of 20bcf per well
          3. I then worked backwards to estimate what initial production we could assume at different rates of decline
          4. I then multiplied that typical well by 50 across the basin
          5. Over 30 years
          6. I deducted OPEX, Capex, Royalty, Overriding royalty and Corporate tax
          7. I discounted the total back at NPV-10 rates
          8. Worked out Falcon’s percentage take (at 50%*45%).
          9. Added it up
          10. I divided by 600m shares out assuming no dilution which may be optimistic

          Copies of the model are available to those from TMF who I know, on request.

          Assessing the model

          The long and short of the model is that I pretty much confirmed the old adage that, give or take, 1tcf in the ground is worth roughly $1bn. My model came in slightly lower than that but more aggressive discounting (e.g. 8% as UPL use in their non-SEC compliant utterings) or a higher assumed gas price ($8.5/mcf) than the $7/mcf which I assumed, does raise it to that level.

          In those circumstances, Falcon can be said to have around 0.75tcf risked recoverable and my model suggests that on MOL’s assumptions, they would accrue around 3tcf if the play worked (i.e. the risking was removed). At 600m shares, that equates to $1.25 per share risked which is pretty close to the current SP (assuming C$ parity).

          MOL’s conservatism

          It is important to emphasise at this stage just how conservative MOL is in this presentation. The IR Dept consistently reiterated that these were merely approximate first iterations and that their concern was that they did not want to overpromise and underdeliver. One interesting point was that the Hungarian services industry is currently quite jejune so the 50 well per year programme is constrained by that fact, rather than any strategic view that 50 is somehow the optimum number. As I mentioned earlier, if the number of wells per year rises, the economics of the project (assuming it works) changes dramatically and the resource value rises rapidly.

          In addition, no value is ascribed for the remaining area owned by Falcon under an exploration licence nor, far more importantly, for the deeper Basal Conglomerate region of the play about which there was such excitement last year. Significant upside may lay in either or both of these areas.

          I want to thank H again for all his hard work on this and also to davjo for casting an eye over the model. JPGH is also having a look, so thanks to him.

          I found this an interesting and worthwhile exercise and it has certainly provided me with some comfort that the valuation of Falcon is underpinned on a hopefully conservative view of the resource, assuming it does actually flow.

          KoD


          1. One of the questions was whether the 340bcm was the total risked resource for the whole trough and they said it was but it was very conservative

            I remember your post, and have read it many many times since then. That was a nice piece of work. I'm still sceptical about their numbers though, and what it represents.

            "The discrepancy between the two estimates does not come from any calculating errors, explains Attila Holoda, but probably from the size differences of the geological structure considered"

            Probably? I think it's safe to assume that MOL's numbers only represent the Szolnok, but regardless of what they say, I think it's still questionable as to the area it represents. But we can all agree that in any case, the quantity of gas is enormous.

            I think there are just too many variables at this point to be trying to come up with exact figures. When you have a lot of variables, and start throwing in risk factors, the errors become exponential.

            For example, 4 X 4 = 16. Apply a 50% risk factor to the result, and you get 8.

            Now apply a 50% risk to both numbers. 2 X 2 = 4.

            The end result is now only 1/4 of the correct answer.

            On the other hand, if you have 3 or 4 variables, apply a risk factor to all of them, and STILL come up with valuation of $1.25 per share, that's quite promising :)

            Of course if they can't get the gas to flow economically, none of this really matters.
















            1. Replying to @lanman1


              The tone, avoidance and inaccuracies of the, “Summer 08” article confirm to me that MOL continues to suffer deep corporate embarrassment that it did not recognize the value of Mako until forced to do so by FO’s work and unconventional gas developments in the US and elsewhere.. What makes their chagrin bitter is that a tiny Canadian company (read- “incompetent”) run by an American promoter (a fool) with no management ability recognized Mako’s value and secured a Production License for a very large asset that really should belong to MOL.

              MOL first justified its mistake by contending that Mako was of NO economic value. When it realized that justification was untenable, it minimized Mako’s value, and disparaged FO and TXM’ work on Mako as incompetents who wasted $300Mil on the project before a World Class operator (XOM) was invited in by MOL to save Mako for the Hungarian people. Now it further justifies its mistake by emphasizing that Mako’s value is totally dependent on very recently developed MOL and XOM extraction technology (which is probably true, except for MOL’s roll)

              None of us know the economic value of Mako at this time. What should be clear to all is that MOL is incapable of providing unbiased recoveries or valuations on Mako by telephone or in writing. MOL’s objective is to preserve its public image in Hungary and to retain it preeminent relationship with the Hungarian government without admitting it made a major mistake in not sooner recognizing the value of Mako.

              Thanks to Lanman for posting “Summer 08”.

              Now if the “Steelers” beat those “hoods” from Baltimore, I will have had a great weekend.

              Best to All

              Dick


              1. Replying to @falcon4

                >MOL first justified its mistake by contending that Mako was of NO economic value. When it realized that justification was untenable, it minimized Mako’s value, and disparaged FO and TXM’ work on Mako as incompetents who wasted $300Mil on the project before a World Class operator (XOM) was invited in by MOL to save Mako for the Hungarian people.



                For those who may not have been around at the time, here are some words from the CEO of MOL in March 2007

                SUBJECT: RE: Hungarian Article - translation Posted By: petipajtas Posted Time: 3/26/2007 04:38 EST

                This is an interview with the president of the MOL. The FO related part:

                Question: What is your opinion on Falcon's operation at the Mako Trough? Do you think it is possible that we could export gas within a few years?

                Answer: I don't think this will happen in the near future. We know the Mako Trough for 30 years, 50% of its area belongs to MOL, so we hope FO will succeed, however, as we know, there is no way to exploit the gas in an industrial amount from that deep economically. I have to tell you there is no precedent for this kind of exploitation.

                And then a few months later:


                SUBJECT: RE: Hungarian Press 2 Posted By: petipajtas Posted Time: 5/29/2007 08:50 EST

                The Falcon related part:


                It was impossible not to notice Zsolt Hernadi having a smile under his mustache when he has been recently asked what his opinion was on Falcon's gas-find, which could satisfy Hungary's domestic consumption.




                1. Replying to @lanman1

                  The 3 partners have clearly moved on since those dark days in 2006 and 2007,not to say there were not still a number of disagreements last year.Exxon and Mol,aswell as Falcon are letting it be known that that is now very much behind them.

                  Re forward value,assuming Exxon has the technical expertise to frac the gas successfully in one of the 3 wells, and the 3D seismic work and mud tests do not prove misleading we wiill have something really to shout about before the end of April.Our shares will rise and build on gains probably already made on the back of speculation before the tests (see also the Macquarie Report and their USD3.50 target price). Thereafter, and clearly Mr Lanman is right, a good BoD will maximise value for shareholders by extracting the highest bid from predators.All important for them however will be timing but suffice to say even if we might argue fair value is USD20-30 or USD40 we will likely only obtain a fraction. Looking up from where we are right now, USD10-12 or even USD14 looks a long long long way away but it could be become realisic late 2011/early 2012 if Exxon comes up with the goods in the next few months



            2. Replying to @lanman1

              I think there are just too many variables at this point to be trying to come up with exact figures. When you have a lot of variables, and start throwing in risk factors, the errors become exponential.

              Hi lanman

              Thanks for the kind words, it took a VERY long time to put that model together.

              Whether or not MOL's numbers refer to just Szolnok or not, I of course agree that at this point it is very much "garbage in garbage out" - and MOL are to a very large extent just guessing. I cannot repeat enough how much the woman I spoke to wanted to emphasise that the numbers were "conservative" and first draft.

              Its also worth reiterating the bottleneck effect of the rig and pipeline capacity. Its a quality problem to have and there would be noone better positioned to solve it than Exxon but as ever with this play, its not all about the resource size.

              KoD


        2. In any case, both numbers are close. 12 TCF from MOL, 15.7 from Falcon (P90) technically recoverable from the Szolnok, both conservative estimates.

          Thats a heck of a lot of gas.

          Well said lanman, I could not agree with you more, and we are part of this. The only problem for FO is that it will need to eventually finance its percentage of expenditures, and initial cash flow will not be enough to cover those expenses. Dilution is a possibility, and not a great one for us. Giving away percentage ownership to be carried through by the wealthier partners is another possibility. Not a great one either. Getting a loan to pay our way in a couple of years may work onlyb id the credit markets and the global economy have recovered enough. I would not hold my breadth on this one. It may all work out just fine for us, but it sure looks murky at this point in time. Would you venture to say something about what the best case scenario may be (a realistic best case, not the pumping type which I know you are not)


          db

          1. >Would you venture to say something about what the best case scenario may be (a realistic best case, not the pumping type which I know you are not)



            At this point in time, I think the best case scenario is to sit back and let Exxon do their stuff, and if they are succesful, put up a big 'for sale' sign.



            Remember Duverney? Shell paid 6 billion, mainly because of their ~6 TCF of gas.

            CALGARY — Global energy giant Royal Dutch Shell PLC is acquiring Duvernay Oil Corp. (TSX:DDV) of Calgary in a rich C$5.9 billion deal that will nearly double Shell’s North American natural gas output.

            ....

            "Our interest in Duvernay relates to their tight gas assets and our ability to bring our operating experience in tight gas and our financial abilities to bear on those assets,”

            “We had built two very large uncoventional gas programs, one in B.C., one in Alberta that have multi-year drilling inventories ahead of them and significant production and reserve upside that and Shell recognized that,” Rose said in an interview with Business News Network, a cable TV business channel based in Toronto.

            “And hence the bid came.”



          2. >The only problem for FO is that it will need to eventually finance its percentage of expenditures, and initial cash flow will not be enough to cover those expenses.

            This issue has been brought up on several occasions, but I don't think anyone has actually come up with a ballpark figure on how much money Falcon will require if the project proceeds to the development phase. So this is what I come up with.



            50 wells per year @ $12mm = $600mm

            From MOL: "On top of it, 50 unconventional wells will require some new surface facilities costing approx. $30–40 million."

            So we're talking about $640 million in the first year, using these numbers. If Falcon has to pay 1/3, that's $213 million.

            Also from MOL:

            "Discounted payback period of a well is 2-3 year"

            So roughly that's $4mm in revenue per well, so Falcon gets $1.3 mm.

            At 50 wells, thats $65 million, so in the second year they need $213mm - $65mm, which is $148mm.

            In the third year, they now have 100 wells, giving them an income of $130mm, so by the third year they need an additional $83mm.

            In the fourth year, they now have 150 wells, giving them an income of $195mm, so now they need $18 million.

            By the fifth year, the project will be paying for itself. In order to get to that point, they need roughly $462mm.

            So overall, the amount of money that they will need seems enormous, but not outrageous. Hopefully by the time comes, credit will be more readily available. We already know that Maquarie was quite willing to lend them $250mm back in 2006, before they had even proved existance of the BCGA, so personally, I don't think money will be that big of an issue if Exxon decides to go ahead. Unless of course, they spend all their income elsewhere.













  2. Since, in accordance with the agreement between MOL and ExxonMobil, the Hungarian company had an option on entering the venture, not much later, when MOL acquired a 50% share of ownership in ExxonMobil’s share of TXM-Falcon exploration block, the three companies joined forces. The operator of the joint efforts will be ExxonMobil

    ...we extremely like this part...do you think mab said...surrender to the darkside...and Tillerson responded...

    ...use the Force mark...gofo and g'day

  3. After reading the article again, I just wanted to point out an interesting tidbit that I missed earlier.



    "Wishing to share the geological and technological risks and extremely high costs of this new kind of exploration with a partner, they negotiated with several experienced companies and eventually agreed, in 2006, to conduct a joint technical study in co-operation with Esso, the European subsidiary of ExxonMobil."