Thank you Lanman for finding this article :)

http://www.magyarhirlap.hu/cikk.php?...


Gas storage defense.

Even in the coldest weather, the strategic facility guaranties supply protection.

By the end of the year, the construction of the 1.9 billion cubic meters capacity strategic gas storage facility in Szőreg will be complete, and then the era of gas blackmail will be history. In case of future supply disruption, the facility is capable to put 25 million cubic meters of gas daily into the network. Also by the end of the year, we should find out how much gas can we extract from the Makó trough.

Because of our gas dependence, we need to have the strategic gas storage (Fotó:Hegedüs Róbert)

According to the experts, this winter was the last time that we will be subjected to gas supply shortages due to disagreements between the Russian and Ukrainian gas transit partners. By the end of the year this facility not just only going to be finished, it also will be filled with gas to the full capacity. The storage safely can provide gas for 40 days.

E.ON already has 5 storage facility with 51 million cubic meters daily output if necessary, add to this the daily 25 million cubic meters output from the new facility, plus the imports we receive from the western suppliers, then we are approaching the daily 90 million cubic meters of gas output that can be pumped into the system. This amount is sufficient to cover the country’s needs even in the very cold weather of minus 20 Celsius.

The gas storage is an old depleted gas field, the gas surplus in the warmer months pumped underground into the depleted geological strata and it is stored there, of course, the pressure cannot be greater than as it was in the original gas field. Mol has numerous old gas fields that can be used for regional or European Union gas storage projects. The cost of the Szőreg storage was about 150 billion Forint ( Can$1 billion). Hungary is the most dependent on foreign gas energy supplies amongst the European Union member states. Therefore, this strategic gas storage will become Hungary’s bulletproof vest when the Russians and the Ukrainians are reverting to their annual gas war. Moscow and Kiev has no regards for the cold winter, and seemingly like to settle their differences in the dead of winter. This year we were lucky that we did not have the numbing cold weather of 3 years ago, when the Russians and the Ukrainians were fighting the same war. To maintenance of this bulletproof vest will add 1.5 Forint to the price of the gas, and it seems to be a small amount to pay when you consider it will help to eliminate the economical and political blackmail.

The domestic gas reserve can be increased by the amount of exploitable gas extracted by unconventional methods. With the traditional gas exploitation methods, you are extracting the gas that migrated near to the surface, and found in traps. However, in the Mako trough you have to drill deep into the source rock where the gas is still forming, ant then bring it to the surface.

According to the experts, by end of the year they will advance to the point when they can tell how much of the estimated 340 billion cubic meters of gas is recoverable. If this amount were economically recoverable, it would be a very significant development, in comparison, in the last 72 years 209 billion cubic meters of gas was extracted to date.

Szalontay Mihály





Join the conversation about Falcon Oil and Gas Ltd.

Reply

Replies

  1. Thanks for the translation John. The nice thing about the storage facility is that it is yet another plus to the infrastructure surrounding the Mako Trough.

    Here is a picture of the pipes for the pipeline, and the route.








    1. You are very welcome. That's a nice Google shot, by the way I think one of us should add that Google shot to our photo album :)

    2. ...so if this is in fact a real picture and not a stock photo from another website;)...obviously someone believes there will be gas coming from somewhere...and as we scrolled down and over we couldn't help but notice a four letter word...the one falcon uses alot...probably just a random pipeline to move onion scent from the fields...but our guess is someone knows the boyz will make these flow...taking on the worlds toughest challenges...wonder where the barrels will be stored...the summer of mab is on the way...it wont be long now...gofo and g'day

      1. >.so if this is in fact a real picture and not a stock photo from another website;)...obviously someone believes there will be gas coming from somewhere..

        Hate to burst your bubble pipe, but the purpose of building the strategic gas storage facility is so that if the Russian supplies get cut off again, Hungary will be able to hold out for a lot longer. It has nothing to do with the success or failure of the Mako Trough....but as I pointed out yesterday, it's certainly a good thing to have in the neighbourhood because of all the pipelines that are being built in the area.



        >.obviously someone believes there will be gas coming from somewhere.

        Yes, it will be coming from Russia for the first few years anyway.

        "the gas surplus in the warmer months pumped underground into the depleted geological strata and it is stored there"







        1. ...pop our bubble mrLanman...no chance...as we cant get much higher than cloud 9...your and johnthegreats finds continue to be stellar...gofo and g'day

        2. Even more infrastructure on the way.....they'll have to make a little detour around the Magy and Mako-4 locations :)



          EC proposes 30 million euro for the Arad – Szeged gas pipeline

          Date: 29-01-2009



          Romania and Hungary could receive 30 million euros for the Arad-Szeged pipeline to interconnect the gas grid of the two countries, as part of the financing package of 3.5 billion euros for investment in energy infrastructure proposed on Wednesday by the European Commission to the member states.
          As a result of the recent gas crisis between Russia and Hungary and as an answer to the financial crisis, the European Commission formulated the proposal to allocate 5 billion euro from the EU budget which was not spent on energy projects, development of broadband networks and ecology projects of rural development.
          Most of the money – 3.5 billion euro – could be for gas pipelines and electricity grids, marine wind energy projects and CO2 storage technology. Among the projects selected by the European Commission is the interconnecting gas pipeline between Hungary and Romania to whom the European executive allotted 30 million euros, if the member states approve these proposals during the Spring Summit of 19-20 March.
          The total value of gas grid interconnection from Romania and Hungary was estimated in the autum of last year at 73 million euros, the Romanian party investment to be worth 35 million euros.
          The total length of the pipeline will be 109 km and will have a diameter of 700 mm. On Romanian territory, the interconnecting pipeline has an approximate length of 62 km between Horia ( near Arad) and Csanadpalota ( Nadlac) at the border between Romania and Hungary.
          The pipeline will be finalized until January 1 2010 and will have a capacity of 4.4 billion cubic metres per year, corresponding to an average flow of 500,000 cubic metres/hour, according to the data of the Transgaz officials.



          1. This is why all of this new infrastructure is a very good thing:



            Under the HGA, the system operator (to the extent it is necessary to ensure the
            stability of the system), the public utility wholesaler, the public utility suppliers, the
            traders, the gas producers (to the extent of their production) and the eligible
            customers (to the extent of their own consumption) have a right of Third Party
            Access (“TPA”) to the free capacities in the transmission, distribution and
            storage systems. Access must be granted on a non-discriminatory basis to all
            operators.

            1. Replying to @lanman1

              >This is why all of this new infrastructure is a very good thing:

              You can never have enough infrastructure, and if the Asians cannot fill this pipeline, then Mako sure can help :)



              Nabucco envoy presses for signing of intergovernment agreement
              Friday 9:58, February 20th, 2009
              An intergovernment agreement on the Nabucco gas pipeline as well as an agreement on support for the project by companies in the consortium that want to build it must be made in the coming months if funding available right now is to be used for preparations for the project, Hungary Nabucco envoy Mihály Bayer said.

              The intergovernment agreement is expected to be signed by the end of May, allowing Parliament to ratify it before the end of the spring session, Bayer said.

              Oil and gas company MOL representative Benjámin Lakatos said the board of the project company for the pipeline, Nabucco Gas Pipeline International (NIC), had accepted the company's €50 million budget plan for 2009. MOL has committed €8.8 million to the amount, he added.

              MOL is participating in the project company with Austria's OMV, Romania's Transgaz, Bulgaria's Bulgargaz, Turkey's Botas and RWE of Germany.

              Benjámin said he was sorry the EU had decided to provide just €200 million in support for the first steps of the Nabucco project, rather than the earlier announced €250 million. He said he was happy that the Commission now proposed €20 million in EU support to finance an interconnector between gas lines in Hungary and Croatia.

              An examination of the costs of the 3,300-kilometer Nabucco pipeline will be completed in three or four months, Lakatos said.

              The €7.9 billion price tag is likely to be lower because of the falling cost of base materials, Bayer said.

              Bayer termed a Nabucco summit held in Budapest in January a success, especially the Budapest Declaration it produced. The document, signed by some of the participants at the summit, laid down a cost-based delivery method for the entire length of the pipeline, which even Turkey approved. The declaration says the EU must make the project a priority and that an intergovernment agreement on the project should be signed in the first half of the year. (MTI – Econews)

  2. Thanks for the translation Soly. Hopefully, there will be so much gas flowing out of the Mako in the future that Hungary won't need a bulletproof vest for protection against the Russians. FO will shield the fine people from all supply shortfalls caused by their neighbors to the east.

    Corter

    1. >Hopefully, there will be so much gas flowing out of the Mako in the future that Hungary won't need a bulletproof vest for protection against the Russians.

      You are welcome Corter, and I'm sure there will be so much gas that we'll sell it to the Russians. Only kidding, but not about all that gas :)