...that MOL and Exxon have a 4th well on the go. The Foldeak-1 didn't spud until February.



In Hungary, out of the 6 wells tested in 2008, Földes-ÉK-1, Körösújfalu-3 and Dombegyház-DNy-7 wells were classified as gas producers, Sülysáp-É-1 as an oil producer and İrtilos-1 as a gas and oil producer.
Only Jászberény-Ny-4 well was qualified to be dry. There were 8 wells in drilling or testing phase. The spudding of Vízvár-S-1 and Zsáka-1 wells, and a further 3 wells drilled in Makó Basin (unconventional gas accumulation) in partnership with ExxonMobil and TXM were in progress at year-end. The Jánoshalma-D-1 well in Hungary and the Dravica-1 well in Croatia (drilled in partnership with INA) are awaiting well tests. Okány-3 well is scheduled for additional well operations (this well was deepened in partnership with Hungarian Horizon Energy).

(From MOL 2008 Q4 report, published today)



Join the conversation about Falcon Oil and Gas Ltd.

Reply

Replies

  1. >...that MOL and Exxon have a 4th well on the go. The Foldeak-1 didn't spud until February.

    I assume the fourth well is at Kopáncs, as it was mentioned in the February 7th addition of the delmagyar.hu


    "We also learned - and not from Szabó – that MOL started exploring 1500 meters from highway 47 at Kopáncs"

    http://maps.google.com/maps?f=q&...

    1. >I assume the fourth well is at Kopáncs, as it was mentioned in the February 7th addition of the delmagyar.hu

      Same here



      >The Foldeak-1 didn't spud until February

      I need a vacation :)

      Falcon is pleased to announce that ExxonMobil, as operator, began drilling the Földeák 1 well on January 14th 2009

      But anyway, what I said still applies.





      1. Interested in this?

        From MOL's 27 February 2009 Drilling update

        We continue our joint exploration activities with ExxonMobil in the Makó-Trough with drilling of one additional well and testing of drilled wells in 2009. In 2008, MOL and ExxonMobil conducted a joint evaluation of one of the largest European potential unconventional gas resource base, the South-East Hungarian Makó and Békés basins and started joint exploration project in the area, which will be continued with drilling of one additional well and testing of drilled wells in 2009.

        http://www.mol.hu/en/about_mol/inves...







        1. Same Drilling update, another mention:

          In 2008 significant steps were made to evaluate and explore the unconventional exploration potential of Hungary, having several hundreds bcm combined original gas-in-place resource potential. Based on the positive results of a technical study completed by MOL and ExxonMobil by the end of 2007, ExxonMobil launched an unconventional exploration program in the Makó basin covered by exploration licenses owned by MOL. As a result of the agreement signed with TXM in April 2008, MOL and ExxonMobil gained further share of interest covered by the production license of TXM in the Makó basin. As a consequence MOL has positions in all acreages of the Makó basin: in Makó-West (MOL-Esso with 50% Mol share) and Makó-East (MOL-Esso-TXM with 33,5% MOL share) interest areas. Based on technical study activity started with drilling of two exploration wells in 2008 operated and financed by ExxonMobil. The program will continue with drilling of one additional well and testing of drilled wells in 2009. MOL decided to check the unconventional potential of Békés basin by drilling of one well in 2009 to prove the area for next activity. There are several other geological formations located in the Pannonian basin (in the Derecske, Dráva and Zala basins), where exploration of unconventional hydrocarbon can be pursued. The evaluation of these basins potential is ongoing process.

          1. Can't get it to copy in a format that is easy to read so go to page 7 for a list of their Hungary wells. Conventional - 16 wells. Unconvnentional - 3 wells.

            Unconvential

            Name Status MOL Paying/participating % Partner

            Mind-3 Suspended 0/50 XOM

            Hod-1 Drilling in progress 0/50 XOM

            Foldeak-1 Drilling in progress 33/33 TXM-EM



            1. Replying to @BrunerFan

              Drilling update:

              >Based on technical study activity started with drilling of two exploration wells in 2008

              Q4 report:

              >and a further 3 wells drilled in Makó Basin (unconventional gas accumulation) in partnership with ExxonMobil and TXM were in progress at year-end.


              The two reports don't seem to say the same thing.

              I would be inclined to think that there are only 3 wells, the Mindszent-3, the HOD-1, and the Foldeak-1, but the editor of Delmagyar seemed quite sure of himself when he said there was drilling going on near Kopáncs.

              I suppose it's possible that the Kopancs well is a geothermic well. I saw an article the other day that there was going to be a few geothermic wells drilled in the area.

              John, can you take a look at that article?

              http://www.delmagyar.hu/hodmezovasar...










              1. Replying to @lanman1

                I agree with 4 wells -

                "We continue our joint exploration activities with ExxonMobil in the Makó-Trough with drilling of one additional well and testing of drilled wells in 2009."

                I think the confusion is related to the spudding of Foldeak. The list of wells that includes Foldeak has this as part of the heading: "Status as of end-2008". We are operating under the premise that it spudded in January per FO NR and this says it was "drilling in progress" at end of 2008 with one more well to come in 2009.

                1. Replying to @BrunerFan

                  >I agree with 4 wells

                  It certainly is a very strong possibility. Of course to add to the confusion, they are drilling an 'additional' well in the Bekes basin during 2009.

                  Of course if we go by the "Status as of end-2008" theory, then the HOD-1 was "still in progress". The Q4 report said there were 3 wells "in progress" at the end of 2008. The drilling update says the Mindszent-3 was 'suspended', the HOD 'in progress', and the Foldeak 'in progress' at the end of 2008.

                  It's as clear as drilling mud :)















              2. Replying to @lanman1

                >John, can you take a look at that article?

                The subject of the article is geothermal energy. They are inceasingly use more and more geothermal energy to heat public buildings and large apartment houses.

                Anyway, there is no mention of a new geothermal well being underway.

                Vásárhely most 10 termálkutat üzemeltet, ezek közül 2-2 használati meleg vizes és visszasajtoló, 6 pedig termelő kút. Legutóbb 2007-ben fúrtak egy-egy termelő és visszasajtoló kutat.

                Vásárhely operates 10 thermal wells, out of these 2-2 are using the recirculation method by repumping the water underground. The other six are production thermal wells. It was in 2007 when the last time they drilled one production and one recirculation type of well.