Commercial Production Underway at G-9 Mine
Farallon reached an important milestone on April 1, achieving
commercial production at the G-9 Mine. The mine is now operating at
the full design production capacity of 1,500 tonnes per day.
President and CEO Dick Whittington said, “In a time of market
turmoil, it is a great achievement by management and staff to be
able to focus on the task at hand and reach our goal. Our next step
is to improve the efficiencies at the operation, as it is critical that
we perform on an optimal operational level through the next few
months. We are confident that the G-9 Mine can be sustained though
this difficult metal price environment, and enable the Company to
prosper when metal prices inevitably recover down the road.”
The G-9 Mine progressed through a successful commissioning phase
in late 2008 and increased production during the months of January
and February 2009, and sustaining full production capacity of 1,500
tonnes per day in early March.
Farallon Resources
G-9 Mine first quarter production results: 16.9 million
pounds of zinc, 1.2 million pounds of copper,
0.3 million pounds of lead, 229,500 ounces of silver
and 3,300 ounces of gold; on track to achieving
production targets and goals for the balance of the year.