Welcome To the Goldstone Resources Inc.HUB On AGORACOM

Edit this title from the Fast Facts Section

Free
AGORACOM NEWS FLASH

Dear Agoracom Family,

I want to thank all of you for your patience with us over the past 48 hours and apologize for what was admittedly a botched launch of our new site.

As you can see, we have reverted back to the previous version of the site while we address multiple forum functionality flaws that inexplicably made their way into the launch.

To this end:

1.We have identified 8 fundamental but easily fixable flaws that will be corrected in the coming week, so that you can continue to use the forums exactly as you've been accustomed to.

2.Additionally we will also be implementing a couple of design improvements to "tighten up" the look and feel of the forums.

Have a great Sunday, especially those of you like me that are celebrating Orthodox Easter ... As well as those of you who are also like me and mourning another Maple Leafs Game 7 exit ... Ugggh!

Sincerely,

George et al

Message: Key Lake Property

15000 meters.. ?? 1 machine @ 35 meters per day = 428 days of drilling

or.. 2 machines = 214 days of drilling.

or 3 machines = approximately 142 days or so

regardless.. Cost at 120 per meter = $1.8 Million + assays ETC

Probably about a 2 million dollar budget ...IMHO.

And lets allow another million for drilling this fall back in the Beardmore area.

With little help.. I can see that 4 million can easily be spent this year..

This drilling and the results should put us in a far better position by this fall .. if not earlier.

SO--... LETS GET AT IT