Kirkland Lake Gold Inc.

KGI is an operating and exploration gold Company in Kirkland Lake, Ontario which is located in the Lower Abitibi Greenstone belt in northeastern Ontario.

Free
Message: 3rd Quarter Results

FINANCIAL RESULTS Q3 2011:

EXPLORATION PROGRAM ACTIVITY INCREASES &

MINE EXPANSION ON TRACK FOR 180,000 - 200,000 OUNCE ANNUAL RUN RATE BY

NOVEMBER 2011

Kirkland Lake Gold Inc. (‘Kirkland Lake Gold’ or the ‘Company’), an operating and exploration gold

mining company located in Ontario, Canada, announces its third quarter fiscal 2011 results for the

three months ended January 31, 2011. All amounts are in Canadian dollars unless otherwise noted.

Mr. Harry Dobson, Chairman, commented, “The third quarter has not been without its challenges with

slightly lower than anticipated grades and difficult choices being made affecting short term production

to ensure we remain on track to achieve the target rate of production by November 2011. After

meeting all operating costs, spending $16.0 million on capital expenditures and $2.7 million on

exploration, total cash resources (including short-term investments) as at January 31, 2011 were

$47.4 million.”

KEY HIGHLIGHTS:

20,231 ounces of gold were produced in the quarter - 58,394 ounces year to date; a record year to

date production figure for the Company.

Net income for the quarter was $4.2 million or $0.06 per share, and this was reduced by $1.0

million due to higher exploration spending.

Cash flow generated from operating activities during the quarter was $6.2 million.

The year to date head grade of 0.397 ounces per ton is higher than the budgeted grade of 0.382

ounces per ton, and very close to the long term average head grade target of 0.4 ounces per ton.

Operating costs in Q3 2011 decreased to $258 per ton ($743 per ounce) from $365 per ton ($809

per ounce) in Q2 2011; total cash costs also decreased to $275 per ton ($794 per ounce) from

$390 per ton ($866 per ounce) in Q2 2011.

Year to date operating costs of $44.3 million are lower than budgeted ($50.2 million).

The number of ore mining faces available for production was maintained at 28 while the number of

ore mining faces in the development and planning stages increased from 23 to 26.

A record mill throughput of 635 tons of ore per day was achieved.

The total workforce increased by 48 to 648 employees.

DETAILS OF THE THIRD QUARTER

Mine Expansion and Production

A total of 20,231 ounces of gold were produced in the quarter, which was lower than that targeted

and lower than that required to reach the Company’s production target for the year of 90,000 to

100,000 ounces. This was due to a decision taken during the quarter to reduce support for near

term production activities due to hoisting constraints in order to allow other higher priority longer

term activities to continue.

The quarterly head grade of 0.362 ounces of gold per ton (“opt”) was also lower than expected. In

some mining areas, lower grade ore was unexpectedly encountered along with the known higher

grade ore, resulting in a blended grade being mined. This is a very common occurrence in this

- 2 -

type of gold deposit, and is the main reason that the Company’s long term plans are based on an

average long term head grade of approximately 0.4 opt despite a blended reserve and resource

grade of over 0.5 opt. The year to date head grade of 0.397 opt is very close to target and slightly

higher than the budgeted head grade of 0.382 opt. The higher than expected gold price has

reduced cut off grades in most areas to below those budgeted.

Work to increase the hoisting capacity of the No. 3 Shaft continued in the quarter. The new

service hoist was commissioned by the end of January after electrical design problems related to

uneven input voltages were overcome. The working platform required to complete final headframe

work and carry out shaft upgrades was also installed by the end of the quarter. A decision was

made in the quarter to move forward and complete some shaft electrical and shaft air line

installations utilizing the working platform rather than the new cage due to better working

conditions. As a result, installation of the new cage is now targeted for June 2011. Shaft upgrade

work continued in the quarter focused primarily on the headframe and the shaft services

compartment and the shaft stations and loading pockets. However, this work was based on the

existing conveyances rather than the new hoist and working platform and contributed significantly

to the shaft overload. Shaft crews were also utilized on other shaft maintenance work that was

brought forward because of the delay. This work also utilized the existing conveyances.

Excavation of the truck loading chutes and stations below the 5300 Level and the underground

haulage ramp between the No. 3 Shaft and the South Mine Complex (SMC) mining area

continued.

Exploration

More diamond drills moved to a seven day per week operating schedule as the contractor added

drillers to the workforce as requested by the Company. Exploration expenses increased by $1.0

million over the previous quarter.

An exploration drift has been advanced to the edge of the Amalgamated Kirkland - Queenston

joint venture property of the Company and Queenston Mining Inc. in preparation for driving a drift

onto that property in order to establish a central diamond drilling station in the second quarter (Q2)

of fiscal 2012. The Company is awaiting authorization from the Ministry of Northern Development,

Mines, and Forests to proceed with this development.

Financial Results

Net income for the third quarter (Q3) ended January 31, 2011 was $4.2 million or $0.06 per share,

which compares to a net income of $8.6 million for the previous quarter (Q2) of fiscal 2011, and a

restated net loss of $4.9 million for Q3 of fiscal 2010.

Operating costs were $258 per ton ($743 per ounce), compared with $365 per ton ($809 per

ounce) in the prior quarter, and $306 per ton ($900 per ounce) in Q3 of fiscal 2010. Total cash

costs were $275 per ton ($794 per ounce), compared to $390 per ton ($866 per ounce) in the prior

quarter and $316 per ton ($930 per ounce) in Q3 of fiscal 2010. The Company’s target is to

reduce the operating costs to less than $250 per ton by upgrading mine infrastructure and

increasing production.

Cash flows generated from operating activities were $6.2 million in Q3 of fiscal 2011 compared to

$16.0 million in Q2 of fiscal 2011 and a use of $6.3 million in Q3 of fiscal 2010.

Gold poured in the quarter was 18,331 ounces, which compares to 23,419 ounces for the previous

quarter and 5,817 ounces for the same period in the previous fiscal year.

- 3 -

After meeting all operating costs, spending $16.0 million on capital and $2.7 million on exploration,

total cash resources (including short-term investments) as at January 31, 2011 were $47.4 million.

As at March 14, 2011 this number had increased to $51.0 million.

Health and Safety

The Company completed calendar year 2010 with the lowest accident frequency in the Province

of Ontario in the Large Mines category.

OUTLOOK

The production forecast for fiscal 2011 has been reduced to 80,000 to 85,000 ounces of gold because

of the issues outlined above. Higher grades are expected in the fourth quarter and attaining those

higher grades is essential to meeting this forecast.

The Company’s expansion activities will continue to take priority, and the available resources will be

managed accordingly. The tonnage of ore to be hoisted and mined will be managed to meet these

targets, provided higher priority activities are not hindered. The Company will continue to prioritize the

work and investment required to meet our goals of attaining five million ounces in total gold reserves

and resources and of reaching a profitable production rate of 180,000 to 200,000 ounces of gold per

year by November 2011.

The expected completion date of the current expansion project remains November 2011, and that is

the first month in the current plan in which production is expected to exceed the 1,200 ton per day

threshold. The Company is currently reviewing its plans as part of the 2012 fiscal year budgeting

exercise, but that target date still appears feasible with some re-arrangement of activities and

schedules. Production is planned to be in the range between 1,200 to 1,400 tons of ore per day after

November 2011. Planning and engineering studies related to a potential further production expansion

will continue with no decision expected until the latter part of fiscal year 2012.

There are some risks to the expansion project timeline that the Company will attempt to manage, but

which are not totally within its control. These include risks related to:

1) late delivery of equipment from suppliers;

2) delays in commissioning equipment due to problems experienced by suppliers or outside

installers; and

3) recruiting and retaining skilled labour as activity in the mining industry continues to pick up

and competition for skilled, experienced, and qualified workers and staff increases.

These issues may or may not act to extend the expansion project timeline, but they will not affect the

ultimate completion of the project. The near term impact of these problems to date has been to reduce

production while slowing overall spending and lowering operating costs.

“Despite the delays with our hoisting capacity project resulting in our annual guidance being reduced

to 80,000 to 85,000 ounces, the long term plan of reaching a profitable production rate of 180,000 to

200,000 ounces remains the Company’s higher priority and is on track to be completed by November

2011. Fiscal 2012 production guidance is forecast to be 120,000 to 140,000 ounces of gold,”

concluded Mr. Dobson.

- 4 -

SELECTED FINANCIAL INFORMATION & REVIEW OF OVERALL PERFORMANCE

Financial Highlights

(All amounts in 000’s of Canadian Dollars, except

shares and per share figures)

Three months ended,

Jan 31, 2011 Oct 31, 2010 Jan 31, 2010

(restated)

Gold Sales (ounces) 18,280 23,392 5,803

Average Price (per ounce) 1,391 1,300 1,064

Revenue 25,426 30,418 6,177

Operating Expenses 17,998 20,536 8,977

Exploration Expenditure 2,709 1,792 1,261

Net Income (loss) 4,206 8,565 (4,896)

Per share (basic and diluted) 0.06 0.13 (0.08)

Cash Flow from (used in) operating activities 6,169 16,046 (6,292)

Cash Flow from financing activities 5,655 2,379 817

Cash Flow from (used in) investing activities (953) (5,635) 11,184

Net increase in cash 10,871 12,790 5,709

Cash at end of period 37,033 26,162 10,198

Short-term investments 10,381 25,347 25,228

Total cash resources 47,415 51,509 35,427

Total Assets 191,675 179,809 128,848

Total Liabilities 22,340 20,367 13,740

Working Capital 41,049 45,147 34,291

Weighted average number of shares outstanding 68,116,420 67,763,116 63,415,452

Dividends per share NIL NIL NIL

About Kirkland Lake Gold Inc.

Kirkland Lake Gold Inc. is an operating and exploration gold mining company located in Ontario,

Canada. It purchased the Macassa Mine and the 1,500 ton per day mill along with four former

producing gold properties – Kirkland Lake, Teck-Hughes, Lake Shore and Wright Hargreaves – in

December 2001. These properties, which have historically produced some 22 million ounces of gold,

extend over seven kilometres between the Macassa Mine on the west and Wright Hargreaves on the

east and, for the first time, are being developed and explored under one owner. This camp is located

in the Southern Abitibi Greenstone Belt of Kirkland Lake, Ontario, Canada. The Company’s corporate

goal is to expand its gold reserves and reduce its operating costs to become a profitable gold

producer.

The Company’s common shares trade on the TSX (Toronto Stock Exchange) and on the AIM

(Alternative Investment Market) of the London Stock Exchange.

- 5 -

The Company’s senior management and Board of Directors have extensive experience in the natural

resource and mining sectors that include exploration, mining and marketing, as well as experience in

the legal and corporate finance areas.

For further information, please contact:

Brian Hinchcliffe Lindsay Carpenter

President Director of Investor Relations

Phone: +1 705 567 5208 Phone: +1 416 840 7884

Fax: +1 705 568 6444 Fax: +1 705 568 6444

E-mail:

[email protected] E-mail:

[email protected]

Philippe Polman

Pelham Bell Pottinger

Phone: +44 (0) 20 7861 3921

E-mail:

[email protected]

Guy Wilkes Katherine Roe / Callum Stewart

Ocean Equities Ltd. NOMAD: Panmure Gordon (UK) Ltd

Phone: +44 (0) 207 786 4370 Phone: +44 (0) 20 7459 5744

E-mail:

[email protected] Email:

[email protected]

Website:

www.klgold.com

Neither the Toronto Stock Exchange nor the AIM Market of the London Stock Exchange has reviewed and

neither accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Note Regarding Forward Looking Statements

This Press Release may contain statements which constitute ‘forward-looking statements’ including statements

regarding the plans, intentions, beliefs and current expectations of the Company, its directors, or its officers

with respect to the future business activities and operating performance of the Company. The words “may”,

“would”, “could”, “will”, “intend”, “plan”, “anticipate”, “believe”, “estimate”, “expect” and similar

expressions, as they relate to the Company, or its management, are intended to identify such forward-looking

statements. Investors are cautioned that any such forward-looking statements are not guarantees of future

business activities or performance and involve risks and uncertainties, and that the Company’s future business

activities may differ materially from those in the forward-looking statements as a result of various factors. Such

risks, uncertainties and factors are described in the Company’s periodic filings with he Canadian securities

regulatory authorities, including the Company’s Annual Information Form and quarterly and annual

Management’s Discussion & Analysis, which may be viewed on SEDAR at

www.sedar.com

. Should one or more

of these risks or uncertainties materialize, or should assumptions underlying the forward-looking statements

prove incorrect, actual results may vary materially from those described herein as intended, planned,

anticipated, believed, estimated or expected. Although the Company has attempted to identify important risks,

uncertainties and factors which could cause actual results to differ materially, there may be others that cause

results not be as anticipated, estimated or intended. The Company does not intend, and does not assume any

obligation, to update these forward-looking statements.

Share
New Message
Please login to post a reply