Files Court Injunction Against GLR Resources

May 15, 2009
Linear Gold Corp. Files Court Injunction Against GLR Resources in Connection With Planned Acquisition of Goldfields Project
HALIFAX, NOVA SCOTIA--(Marketwire - May 15, 2009) - Linear Gold Corp. (TSX:LRR) ("Linear Gold" or the "Corporation") announces that it has received interim injunctive relief from the Nova Scotia Supreme Court to restrain GLR Resources Inc. ("GLR") from proceeding with an allegedly superior offer to acquire GLR's Goldfields Project.

On April 17, 2009, Linear and GLR signed a binding term sheet ("the "Agreement") providing the terms under which Linear would be entitled to acquire GLR's Goldfields Project. The terms specified the intended deal structure and the consideration due to GLR, as well as a right for Linear to match any superior offer received by GLR.

Linear has been constructively working with GLR since April 20, 2009 to complete the transaction substantively in accordance with the Agreement. Linear understands that GLR has recently accepted an offer for the acquisition of the Goldfields Project that Linear was not properly notified of in accordance with the Agreement.

Wade K. Dawe, President

Join the conversation about Linear Gold.

Reply

Replies



  1. Linear Gold to acquire Goldfields project



    2009-05-26 12:20 ET - News Release

    Mr. Wade Dawe reports

    LINEAR GOLD ACQUIRES GOLDFIELDS DEVELOPMENT PROJECT

    Linear Gold Corp. has signed a definitive purchase and sale agreement with GLR Resources Inc., whereby Linear will acquire a 100-per-cent interest in the Goldfields Project located near Uranium City, Saskatchewan, Canada. The acquisition of the Goldfields Project includes the Box and Athona deposits with the following highlights:

    - A total resource of over 1 million ounces with reserves of 601,007 ounces of gold stated in a National Instrument 43-101 compliant Technical Report by Bikerman Engineering & Technology Associates, Inc., June 2007, Revision 1-May 12, 2008. The resources and reserves are as follows:

    Box Deposit:

    - Proven and Probable Reserve - 10.9 million tonnes at 1.70 grams per tonne gold representing 601,007 ounces including:

    -- Proven Reserve - 1.7 million tonnes at 2.025 grams per tonne gold representing 109,619 ounces; and

    -- Probable Reserve - 9.3 million tonnes at 1.641 grams per tonne gold representing 491,436 ounces.

    - Measured and Indicated Resources (includes reserves described above) - 16.9 million tonnes at 1.39 grams per tonne gold representing 753,000 ounces including:

    -- Measured Resources - 2.4 million tonnes at 1.68 grams per tonne gold representing 129,000 ounces; and

    -- Indicated Resources - 14.5 million tonnes at 1.34 grams per tonne gold representing 623,000 ounces.

    - Inferred Resources - 3.7 million tonnes at 0.93 grams per tonne gold representing 111,000 ounces.

    Athona Deposit:

    - Indicated Resources - 10.9 million tonnes at 0.95 grams per tonne gold representing 333,000 ounces; and

    - Inferred Resources - 2.2 million tonnes at 0.83 grams per tonne gold representing 59,000 ounces.

    - Completed 2007 positive feasibility study on the Box Deposit with the following economics:

    -- NPV, discounted at 8%, of US$50.0 million at US$603.75 per ounce Gold revenues;

    -- Internal Rate of Return of 43.4% using US$603.75 per ounce Gold revenues

    - Planned production of 90,000 ounces per year based on a 5,000 tonne per day operation;

    - Excellent process recovery of 93% of the contained gold values;

    - Updated pre-operating capital expenditures estimated at US$63 million;

    - Environmental permit in place - no development delays anticipated;

    - Pre-feasibility study has been initiated on the Athona Deposit;

    - Both deposits are open pit mineable;

    - Both deposits are open at depth;

    - Excellent local infrastructure with airport, power, telecommunications, good road system, field office, core shack and living quarters and kitchen facilities for employees; and

    - Regional exploration upside including the Golden Pond target where previous drill results were reported as 16.57 grams per tonne of gold over 13.6 metres and 5.07 grams per tonne of gold over 15 metres.

    Wade Dawe, President and Chief Executive Officer of Linear, stated, "The Goldfields Project represents an exciting acquisition and an ideal initial development project for Linear. We look forward to working with thelocal communities as well as the Saskatchewan Government to advance the development of the project and believe that Canada's political stability represents a tremendous strategic advantage for the asset. With manageable remaining capital expenditures of approximately US$63 million and planned low cost production of 90,000 ounces per year, the Goldfields Project is expected to be an excellent platform from which Linear will be able to execute an aggressive growth strategy. In the short-term, we plan to update the engineering documents for the project, complete final permitting applications and recruit a senior operating executive to manage the development and operation of this exciting project. We are confident that based on current gold prices, the economics and overall value of this project is substantially higher than the already robust results returned in the 2007 feasibility study using gold prices that were capped at approximately US$600 per ounce."

    Transaction Details

    The Transaction is expected to be completed following receipt of court approval, which GLR has undertaken to seek on an expedited basis. Upon closing, Linear will pay GLR US$5.0 million in cash and issue 727,273 Linear Gold Corp. shares with a deemed value of CDN$800,000. In addition, upon completion and delivery of certain previously contracted equipment, Linear will reimburse GLR for deposits made in connection with the equipment contracts in the amounts of US$3.0 million and CDN$1.2 million.

    Linear Highlights Following the Transaction

    Upon completion of the Acquisition, Linear will remain a well financed and strategically positioned company with:

    - Over CDN$24 million in cash and cash equivalents;

    - 33.4 million common shares issued and outstanding, representing an attractive capital structure for continued growth and consolidation;

    - Planned annual production of approximately 90,000 ounces of gold following the development of the Box Mine;

    - Proven and probable gold mineral reserves estimated to be approximately 600,000 ounces, measured and indicated gold mineral resources estimated to be approximately 1.9 million ounces and inferred gold mineral resources of 0.5 million ounces. See chart at end of release for details;

    - Significant potential for growth through exploration outside of the current Box and Athona Deposits and continued exposure to Linear's promising Ixhautan Gold Project in Mexico and Ampliacion Pueblo Viejo, Loma El Mate and Loma Hueca Gold Properties in the Dominican Republic;

    - Management and board of directors with experience operating, developing, and financing mining companies;

    - Strategic position to leverage planned consolidation within the gold industry.

    The successful completion of the transaction would resolve the pending injunction proceedings.

    Peter Dimmell, P.Geo., a director of Linear and a qualified person under National Instrument 43-101, has reviewed and approved the scientific and technical information in this press release based on the 43-101 compliant report by Bikerman Engineering & Technology Associates, Inc., June 2007, Revision 1-May 12, 2008 on the Box Mine - Goldfields Project, Uranium City, Saskatchewan, Canada, a Technical Report filed Pursuant to National Instrument 43-101 of the Canadian Securities Administrators filed on SEDAR by GLR Resources.



    1. Linear Gold to go to court over Goldfields acquisition



      2009-05-28 09:10 ET - News Release

      Mr. Wade Dawe reports

      LINEAR GOLD RESPONDS TO SANTA FE ACTION

      Linear Gold Corp. has been informed that Santa Fe Metals Corp. has commenced an action against GLR Resources Inc. and Linear, in connection with Linear's acquisition of the Goldfields project.

      On April 17, 2009, Linear and GLR signed a binding term sheet (the original agreement), providing the terms under which Linear would be entitled to acquire GLR's Goldfields project. The terms included the right for Linear to match any superior offer received by GLR, and confirmed by an independent third party acceptable to GLR and Linear.

      On May 15, 2009, the Nova Scotia Supreme Court recognized Linear's contractual rights and granted Linear interim injunctive relief to restrain GLR from proceeding with an allegedly superior offer to acquire GLR's Goldfields project.

      Following the issuance of the interim injunction, on May 25, 2009, Linear and GLR signed a definitive purchase and sale agreement. The definitive agreement maintains and reflects Linear's rights under the original agreement. Under the definitive agreement, Linear will acquire a 100-per-cent interest in the Goldfields project, located near Uranium City, Sask., Canada. The definitive agreement included a representation from GLR that it was authorized to complete the contemplated transaction, and that the completion of the transaction would not result in the violation or breach of any other agreement.

      Linear plans to close the definitive agreement and will vigorously enforce its contractual right, including seeking damages and appropriate remedies from any person, including Santa Fe, that seeks to undermine its legal entitlement to acquire the Goldfields project.

      Throughout discussions and negotiations with GLR that commenced in March, 2009, Linear has conducted itself with the utmost integrity, and acted in good faith in all dealings with respect to the acquisition of the Goldfields project.





      1. Everton, Linear to drill Ampliacion Pueblo in mid-June



        2009-06-01 09:10 ET - News Release

        See News Release (C-EVR) Everton Resources Inc

        Mr. Andre Audet of Everton reports

        EVERTON AND LINEAR TO DRILL 8,000 METERS AT AMPLIACION PUEBLO VIEJO, DOMINICAN REPUBLIC

        Everton Resources Inc. and its partner Linear Gold Corp. plan to commence an 8,000-metre drill program in mid-June on the Ampliacion Pueblo Viejo II (Ampliacion PV) concession, situated adjacent to the Barrick/Goldcorp's Pueblo Viejo gold development project in the Dominican Republic.

        The 40 to 50 hole drill program will test 10 to 12 newly discovered high-priority targets generated from the integrated and comprehensive surveys performed by Everton and Linear over the last two years. These targets are characterized by epithermal-related extensive composite soil anomalies in gold, silver, arsenic, tellurium, and mercury of up to 400 m x 1 km in size - one of which is located less than 300 meters from the westernmost pit of the Pueblo Viejo mine project (see news release of May 4, 2009). The soil anomalies are associated with large zones of advanced argillic alteration and massive silicification along N-S and NW-SE structures parallel to those of the Pueblo Viejo deposit mineralized system. North-South-trending chargeability anomalies are also observed on Ampliacion PV in the due north extension of the Pueblo Viejo Montenegro pit structures.

        Investor Relations Agreement

        Everton has retained Octabaan Consulting ("Octabaan") as its investor relations consultant. The agreement with Octabaan, effective June 1, 2009, is for an initial 3-month term with a performance evaluation by July 15, 2009 with the intentions of entering into a one-year agreement. Octabaan will be paid a monthly fee of $9,000. The Board has granted Octabaan 300,000 stock options priced at $0.15 per share, being the closing price of Everton's shares on the TSX Venture on May 29, 2009, for a two-year term. The stock options will vest on a quarterly-basis. In accordance with the Company's stock option plan and TSX Venture Exchange Policy 4.4, these options will expire within a period of 30 days should the agreement be terminated by Everton.

        Cost Sharing Agreement

        Everton has signed a cost sharing agreement with Adventure Gold Inc. ("Adventure Gold") (TSX VENTURE: AGE) which includes the sharing of the administrative and management costs related to their day-to-day operations. The terms of the agreement were approved by the Boards of Directors of both companies and are subject to the approval of the TSX Venture Exchange (the "Exchange"). Under the agreement, Adventure Gold will have the option to pay the Company for its share of administrative and management costs in common shares in lieu of cash, at a price per share equal to the greater of $0.11 or the Discounted Market Price (as such term is defined in the Corporate Finance Manual of the Exchange) of the shares of Adventure Gold at the end of each quarter upon which such costs are to be paid (See news release of Adventure Gold dated May 22, 2009, for more details on the Agreement).

        Amended and Restated Sale/Acquisition Agreement with Focus Metals Inc. (news release March 26, 2009)

        In reference to Everton's news release of March 26, 2009 under "Spin-off", the Company was to receive 6 million common shares of Focus Metals Inc. ("Focus Metals") at a deemed price of $0.08 per share, for an aggregate consideration of $480,000. The Company and Focus Metals have signed an amended and restated sale/acquisition agreement whereby the deemed price per share is set at $0.06 per share for an aggregate consideration of $360,000 (see news release for details).

        Stock Options

        Effective May 5, 2009, the Company has granted options to purchase up to 115,000 common shares of the Company to an officer and employees. Each option entitles the holder to purchase one common share of the Company at a price of $0.10 per share for a period of five years. The options vest over an 18-month period.

        Effective June 1, 2009, the Company has also granted options to purchase up to 50,000 common shares of the Company to a consultant. Each option entitles the holder to purchase one common share of the Company at a price of $0.15 per share for a period of five years. The options vest over an 18-month period.

        This news release was prepared under the supervision of Marc L'Heureux, P. Geo. and VP Exploration of Everton, who acts as Everton's Qualified Person as defined by National Instrument 43-101.



        1. Santa Fe files Goldfields lawsuit claim statement



          2009-06-10 20:35 ET - News Release

          See News Release (C-SFM) Santa Fe Metals Corp

          Mr. Ian Smith reports

          SANTA FE METALS FILES STATEMENT OF CLAIM

          Santa Fe Metals Corp. has filed a statement of claim against GLR Resources Inc. and Linear Gold Corp. alleging that GLR had purported to enter into an agreement with Linear for the sale of GLR's 100-per-cent-owned Goldfields project after a winning bid for the Goldfields project submitted by Santa Fe had already become a binding and enforceable agreement. The statement of claim also alleges that Linear had knowledge of the material terms of the Santa Fe/GLR agreement and induced the breach of or wrongfully interfered with the Santa Fe/GLR agreement by entering into the Linear agreement.

          Santa Fe had been constructively working with GLR to execute a definitive agreement with the intention of closing the transaction in June, 2009. Unknown to Santa Fe, on May 26, 2009, each of GLR and Linear announced in Stockwatch news that they had entered into a definitive agreement for the purchase by Linear of the Goldfields project.

          1. Everton and Linear sample 1 g/t Au at La Lechoza

            2009-06-23 09:39 ET - News Release

            See News Release (C-EVR) Everton Resources Inc

            Mr. Andre Audet reports

            EVERTON AND LINEAR GOLD DISCOVER A NEW MINERALIZED ZONE AT LA LECHOZA WEST ON THE AMPLIACION PUEBLO VIEJO CONCESSION, DOMINICAN REPUBLIC

            Everton Resources Inc. and its partner Linear Gold Corp. have discovered a new mineralized zone west of La Lechoza prospect on the northern portion of the Ampliacion Pueblo Viejo concession located in the central part of the Dominican Republic, adjacent to the Barrick/Goldcorp's Pueblo Viejo 22.4 million ounce gold deposit.

            Recent field follow-up on soil anomalies from the 2007 survey led to the discovery of the La Lechoza west showing which consists of a series of limonitic to siliceous gossan floats and red ferruginous jasper with white quartz stockwork veinlets floats clustered over an area of 600 square metres. A composite rock sample from several floats on La Lechoza west returned up to one gram per tonne (g/t) gold, 6.7 g/t silver, 0.1 per cent copper and 0.12 per cent zinc. The La Lechoza west showing is situated 1.5 kilometres northwest and on stratigraphic trend to the La Lechoza prospect from which the best surface intercept in trench LT-11 returned 6.65 g/t gold and 18.8 g/t silver over 22 metres. In 2005, drilling performed by Linear at La Lechoza included a one-metre massive sulphide zone at 10.25 per cent copper and 5.71 g/t gold within a larger zone of 22 metres containing 1 per cent copper and 0.3 g/t gold.

            Everton and Linear just completed a 90-sample infilling soil sampling program to confirm the continuity between La Lechoza and La Lechoza west. A field mapping and rock sampling program is currently under way on La Lechoza west in preparation for the upcoming drill program announced by the partners in Stockwatch on June 1, 2009.

            This news release was prepared under the supervision of Marc L'Heureux, PGeo, and vice-president exploration of Everton, who acts as Everton's qualified person as defined by National Instrument 43-101

            1. Replying to @KingJames

              Lundin refreshes buy of Linear Gold

              Linear Gold Corp (C:LRR)
              Shares Issued 32,563,435
              Last Close 6/23/2009 $1.27
              Tuesday June 23 2009 - In the News

              Brien Lundin, in the June, 2009, edition of the Gold Newsletter, says buy Linear Gold Corp., recently $1.40. Mr. Lundin said buy Linear four times, between April, 2004, and February, 2006, at prices ranging from $1.50 to $7.70. He then said take some profits (sell half, perhaps) at $5.42 in July, 2005. Assuming an investment of $1,000 each time, selling half would have yielded a profit of $2,867. He said buy three more times between January, 2006, and September, 2007, at prices ranging from $2.27 to $6.09. The remaining investment ($5,000 cost) is now worth $2,366. The editor says Linear almost headed toward a legal dispute with GLR Resources Inc. The company started negotiations with GLR to purchase the near-production Goldfields project, but it was not yet ready to make an announcement. Then, according to Linear, GLR accepted a better offer from Santa Fe Metals Corp. On May 15, Linear won an injunction from the Nova Scotia Supreme Court to restrain GLR from proceeding with the other offer. Eleven days later Linear announced it had signed a definitive deal with GLR whereby it will pay $5-million (U.S.) and issue 727,273 shares, an exceptional deal according to Mr. Lundin.

              1. Replying to @KingJames

                Linear Gold director Flaherty resigns
                Ticker Symbol: C:LRR

                Linear Gold director Flaherty resigns

                Linear Gold Corp (C:LRR)
                Shares Issued 32,563,435
                Last Close 8/11/2009 $1.68
                Wednesday August 12 2009 - News Release

                Mr. Wade Dawe reports

                LINEAR GOLD CORP. ANNOUNCES RESIGNATION OF A DIRECTOR

                Linear Gold Corp.'s Kevin Flaherty has resigned as a director, effective Aug. 11, 2009. Linear wishes to thank Mr. Flaherty for his dedicated service to the company since July, 2002.

                � 2009 Canjex Publishing Ltd.

                1. Replying to @KingJames

                  Lundin refreshes Linear Gold buy

                  2009-08-18 20:21 ET - In the News

                  Brien Lundin, in the July, 2009, edition of the Gold Newsletter, refreshes his buy of Linear Gold Corp., recently $1.23. Mr. Lundin said buy Linear four times between April, 2004, and February, 2005, at prices ranging from $1.50 to $7.70. He then said take some profits (sell half, perhaps) at $5.42 in July, 2005. Assuming an investment of $1,000 for each of the four buys, selling half the $4,000 investment at $5.42 would have yielded a profit of $2,867. He said buy four more times between January, 2006, and June, 2009, at prices ranging from $1.40 to $6.09. Assuming a $1,000 investment for each of the four most recent buys, and taking into consideration the remaining $2,000 investment from the half sell, the total $6,000 investment is now worth $2,934. Even though there is legal drama surrounding the company's acquisition of the Goldfields project, Mr. Lundin expects Linear Gold to own the property shortly. The property, in Saskatchewan, has a resource of 1.2 million ounces in two deposits, Box and Anthona. The goldbug says a 2007 feasibility study showed a net present value, discounted at 8 per cent, of $50-million at $603.75 per ounce gold, a value that is considered conservative at today's gold price. The company plans to revise the feasibility study this year. Mr. Lundin continues to urge his readers to buy Linear Gold on weakness.

                2. Replying to @KingJames

                  Lundin refreshes Linear Gold buy

                  2009-08-18 20:21 ET - In the News

                  Brien Lundin, in the July, 2009, edition of the Gold Newsletter, refreshes his buy of Linear Gold Corp., recently $1.23. Mr. Lundin said buy Linear four times between April, 2004, and February, 2005, at prices ranging from $1.50 to $7.70. He then said take some profits (sell half, perhaps) at $5.42 in July, 2005. Assuming an investment of $1,000 for each of the four buys, selling half the $4,000 investment at $5.42 would have yielded a profit of $2,867. He said buy four more times between January, 2006, and June, 2009, at prices ranging from $1.40 to $6.09. Assuming a $1,000 investment for each of the four most recent buys, and taking into consideration the remaining $2,000 investment from the half sell, the total $6,000 investment is now worth $2,934. Even though there is legal drama surrounding the company's acquisition of the Goldfields project, Mr. Lundin expects Linear Gold to own the property shortly. The property, in Saskatchewan, has a resource of 1.2 million ounces in two deposits, Box and Anthona. The goldbug says a 2007 feasibility study showed a net present value, discounted at 8 per cent, of $50-million at $603.75 per ounce gold, a value that is considered conservative at today's gold price. The company plans to revise the feasibility study this year. Mr. Lundin continues to urge his readers to buy Linear Gold on weakness.

                  1. Replying to @KingJames

                    Linear Gold completes purchase of Goldfields

                    2009-08-20 16:58 ET - News Release

                    Mr. Wade Dawe reports

                    LINEAR GOLD COMPLETES ACQUISITION OF GOLDFIELDS DEVELOPMENT PROJECT

                    Linear Gold Corp. has completed the acquisition from GLR Resources Inc. of all of its interest in the Goldfields project located near Uranium City, Sask. The acquisition of the Goldfields project, initially announced on May 26, 2009, includes the Box and Athona deposits.

                    The Goldfields project is host to a total resource of over one million ounces of gold with gold reserves of 601,007 ounces as stated in a National Instrument 43-101-compliant technical report by Bikerman Engineering & Technology Associates Inc. (June, 2007, revision 1, May 12, 2008). The resources and reserves of the Box and Athona deposits are as follows:

                    Box deposit

                    • Proven and probable reserve - 10.9 million tonnes at 1.70 grams per tonne gold representing 601,007 ounces including:
                      • Proven reserve -- 1.7 million tonnes at 2.025 grams per tonne gold representing 109,619 ounces;
                      • Probable reserve -- 9.3 million tonnes at 1.641 grams per tonne gold representing 491,436 ounces;
                    • Measured and indicated resources (includes reserves described above) -- 16.9 million tonnes at 1.39 grams per tonne gold representing 753,000 ounces including:
                      • Measured resources -- 2.4 million tonnes at 1.68 grams per tonne gold representing 129,000 ounces;
                      • Indicated resources -- 14.5 million tonnes at 1.34 grams per tonne gold representing 623,000 ounces;
                    • Inferred resources -- 3.7 million tonnes at 0.93 gram per tonne gold representing 111,000 ounces.

                    Athona deposit

                    • Indicated resources -- 10.9 million tonnes at 0.95 gram per tonne gold representing 333,000 ounces;
                    • Inferred resources -- 2.2 million tonnes at 0.83 gram per tonne gold representing 59,000 ounces.

                    The Goldfields project is a development ready project with the following highlights:

                    • Completed 2007 positive feasibility study on the Box deposit with the following economics:
                      • NPV, discounted at 8 per cent, of $50.0-million (U.S.) at $603.75 (U.S.) per ounce gold revenues;
                      • Internal rate of return of 43.4 per cent using $603.75 (U.S.) per ounce gold revenues.
                    • Planned production of 90,000 ounces per year based on a 5,000-tonne-per-day operation;
                    • Excellent process recovery of 93 per cent of the contained gold values;
                    • Updated preoperating capital expenditures estimated at $63-million (U.S.);
                    • Environmental permit in place -- no development delays anticipated;
                    • Prefeasibility study has been initiated on the Athona deposit;
                    • Both deposits are open-pit minable;
                    • Both deposits are open at depth;
                    • Excellent local infrastructure with airport, power, telecommunications, good road system, field office, core shack and living quarters and kitchen facilities for employees;
                    • Regional exploration upside including the Golden Pond target where previous drill results were reported as 16.57 grams per tonne of gold over 13.6 metres and 5.07 grams per tonne of gold over 15 metres.

                    Wade Dawe, president and chief executive officer of Linear, stated: "The Goldfields project is a tremendous acquisition and an ideal development project for Linear. We look forward to working with the local communities as well as the Saskatchewan government to advance the development of the project and believe that Canada's political stability represents a strategic advantage for the asset. With manageable capital expenditures of approximately $63-million (U.S.) and planned low-cost production of 90,000 ounces per year, the Goldfields project will be an excellent platform from which Linear will continue a growth and acquisition strategy. In the short term, we are updating the engineering documents for the project and in the final stages of appointing a senior operating executive to manage the development and operation of this exciting project. We are confident that based on current gold prices, the economics and overall value of this project is substantially higher than the already robust results returned in the 2007 feasibility study using gold prices that were capped at approximately $600 (U.S.) per ounce."

                    Transaction details

                    The transaction closed in accordance with the definitive purchase and sale agreement dated May 25, 2009, subject to certain non-material amendments agreed between Linear and GLR. Santa Fe Metals Corp. has released Linear from all claims in connection with Linear's acquisition of the Goldfields project and Linear has provided a reciprocal release to Santa Fe. All legal issues related to the transaction have been successfully resolved.

                    At closing, Linear, through its subsidiary 7153945 Canada Inc., paid GLR $5.0-million (U.S.) in cash and issued 727,273 Linear shares as consideration for the assets. In addition, within 15 days of closing, Linear will reimburse a supplier $200,000 of certain costs and interest on behalf of GLR, and upon completion and delivery of certain previously contracted equipment, Linear will reimburse GLR for deposits made in connection with the contracted equipment in the amounts of $1.8-million (U.S.) and $1.0-million.

                    Linear highlights following the transaction

                    Upon completion of the acquisition, Linear will remain a well-financed and strategically positioned company with:

                    • Over $24-million in cash and cash equivalents;
                    • 33.4 million common shares issued and outstanding, representing an attractive capital structure for continued growth and consolidation;
                    • Planned annual production of approximately 90,000 ounces of gold following the development of the Box mine;
                    • Proven and probable gold mineral reserves estimated to be approximately 600,000 ounces, measured and indicated gold mineral resources estimated to be approximately 1.9 million ounces and inferred gold mineral resources of 500,000 ounces (see attached chart for details);
                    • Significant potential for growth through exploration outside of the current Box and Athona deposits and continued exposure to Linear's promising Ixhautan gold project in Mexico and Ampliacion Pueblo Viejo, Loma El Mate and Loma Hueca gold properties in the Dominican Republic;
                    • An updated Box mine technical report, incorporating current economic parameters, in progress and expected to be completed within the next eight to 10 weeks;
                    • The reinitiation of the Athona prefeasibility technical report that is expected to be completed within the next eight to 10 weeks;
                    • Management and board of directors with experience operating, developing and financing mining companies;
                    • A strategic position to leverage planned consolidation within the gold industry.

                    Peter Dimmell, PGeo, a director of Linear and a qualified person under National Instrument 43-101, has reviewed and approved the scientific and technical information in this news release based on the NI 43-101-compliant report by Bikerman Engineering on the Box mine/Goldfields project, Uranium City, Sask., filed on SEDAR by GLR resources.

                                    MINERAL RESERVE AND MINERAL RESOURCE
                               ESTIMATES FOLLOWING ACQUISITION GOLDFIELDS PROJECT
                    
                                               Box       Athona      Ixhuatan
                                         deposit(2)   deposit(2)    deposit(3)           Total
                    Mineral reserves(1)
                    Proven
                    Tonnes               1,683,717            -             -        1,683,717
                    Grade (g/t)              2.025          0.0           0.0            2.025
                                        ----------   ----------     ---------       ----------
                    Ounces                 109,619            -             -          109,619
                                        ----------   ----------     ---------       ----------
                    Probable
                    Tonnes               9,313,283            -             -        9,313,283
                    Grade (g/t)              1.641            -             -            1.641
                                        ----------   ----------     ---------       ----------
                    Ounces                 491,436            -             -          491,436
                                        ----------   ----------     ---------       ----------
                    Total proven and
                    probable
                    Tonnes              10,997,000            -             -       10,997,000
                    Grade (g/t)              1.700          n/a           n/a            1.700
                                        ----------   ----------     ---------       ----------
                    Ounces                 601,007            -             -          601,007
                                        ----------   ----------     ---------       ----------
                    Mineral resources(1)
                    Measured
                    Tonnes               2,401,000                  1,320,000        3,721,000
                    Grade (g/t)               1.68          n/a          4.80             2.78
                                        ----------   ----------     ---------       ----------
                    Ounces                 129,000                    203,000          332,000
                                        ----------   ----------     ---------       ----------
                    Indicated
                    Tonnes              14,500,000   10,878,000     8,050,000       33,428,000
                    Grade (g/t)               1.34         0.95          2.51             1.49
                                        ----------   ----------     ---------       ----------
                    Ounces                 623,000      333,000       648,000        1,604,000
                                        ----------   ----------     ---------       ----------
                    Total measured and
                    indicated
                    Tonnes              16,901,000   10,878,000     9,370,000       37,149,000
                    Grade (g/t)               1.39         0.95          2.82             1.62
                                        ----------   ----------     ---------       ----------
                    Ounces                 753,000      333,000       852,000        1,938,000
                                        ----------   ----------     ---------       ----------
                    Inferred
                    Tonnes               3,710,000    2,198,000     7,130,000       13,038,000
                    Grade (g/t)               0.93         0.83          1.63             1.30
                                        ----------   ----------     ---------       ----------
                    Ounces                 111,000       59,000       374,000          544,000
                                        ----------   ----------     ---------       ----------
                    Notes:
                    1. The mineral reserves and resources reported herein are based on the CIM
                    definition standards for mineral resources and mineral reserves adopted
                    by the CIM Council on Dec. 11, 2005. Mineral resources that are not
                    mineral reserves do not have demonstrated economic viability. Mineral
                    resources, as reported, include minable reserves, that is, reserves are a
                    subset of resources.
                    2. Mineral reserve and mineral resource estimates for the Box and Athona
                    deposits were prepared by Bikerman Engineering (June, 2007, revision 1,
                    May 12, 2008, Box mine/Goldfields project, Uranium City, Sask., Canada).
                    This report has been filed on SEDAR by GLR resources.
                    3. The independent qualified person responsible for the Ixhuatan resource
                    estimates is Gary Giroux, PEng, of Giroux Consultants Ltd. A technical
                    report prepared to National Instrument 43-101 requirements has been
                    filed on SEDAR.
                    4. Totals may not add up due to rounding.
                    
                    1. Replying to @KingJames

                      Linear Gold names Sylvestre as COO

                      2009-09-09 08:06 ET - News Release

                      Mr. Wade Dawe reports

                      LINEAR GOLD CORP. ANNOUNCES APPOINTMENT OF CHIEF OPERATING OFFICER

                      Linear Gold Corp. is appointing Mike Sylvestre as chief operating officer.

                      Mr. Sylvestre is a well-respected mining executive with a record of leading the operation and development of major international mine projects. Over the span of a 30-plus-year career with Inco Ltd. and ValeInco, Mr. Sylvestre has consistently demonstrated an ability to operate mines in a safe and sustainable manner and to manage responsibly new mine development and expansion projects including on-time and on-budget completion. Mr. Sylvestre's global experience includes operating and development responsibility for projects in Ontario, Sulawesi, Indonesia, Manitoba and most recently the South Pacific island of New Caledonia. Mr. Sylvestre holds MSc and BSc in mining engineering degrees from McGill University and Queen's University, respectively. Mr. Sylvestre has also studied at the Richard Ivey School of Business and MIT Sloan School of Management.

                      As chief operating officer for Linear, Mr. Sylvestre will be responsible for the operational activities related to the development of Linear's recently acquired Goldfields project located near Uranium City, Sask. Mr. Sylvestre will also play a lead role in the execution of Linear's continued growth and acquisition strategy.

                      Wade Dawe, Linear Gold's president and chief executive officer, stated: "We are delighted that Mike has agreed to join our team at Linear Gold. Mike's knowledge, experience and success in the development and operations of world-class mines will be invaluable going forward. Mike's personal desire and commitment to developing and operating safe, profitable and environmentally responsible mines are exactly the qualities we want in Linear's chief operating officer."



  2. Linear Gold to acquire Goldfields project



    2009-05-26 12:20 ET - News Release

    Mr. Wade Dawe reports

    LINEAR GOLD ACQUIRES GOLDFIELDS DEVELOPMENT PROJECT

    Linear Gold Corp. has signed a definitive purchase and sale agreement with GLR Resources Inc., whereby Linear will acquire a 100-per-cent interest in the Goldfields Project located near Uranium City, Saskatchewan, Canada. The acquisition of the Goldfields Project includes the Box and Athona deposits with the following highlights:

    - A total resource of over 1 million ounces with reserves of 601,007 ounces of gold stated in a National Instrument 43-101 compliant Technical Report by Bikerman Engineering & Technology Associates, Inc., June 2007, Revision 1-May 12, 2008. The resources and reserves are as follows:

    Box Deposit:

    - Proven and Probable Reserve - 10.9 million tonnes at 1.70 grams per tonne gold representing 601,007 ounces including:

    -- Proven Reserve - 1.7 million tonnes at 2.025 grams per tonne gold representing 109,619 ounces; and

    -- Probable Reserve - 9.3 million tonnes at 1.641 grams per tonne gold representing 491,436 ounces.

    - Measured and Indicated Resources (includes reserves described above) - 16.9 million tonnes at 1.39 grams per tonne gold representing 753,000 ounces including:

    -- Measured Resources - 2.4 million tonnes at 1.68 grams per tonne gold representing 129,000 ounces; and

    -- Indicated Resources - 14.5 million tonnes at 1.34 grams per tonne gold representing 623,000 ounces.

    - Inferred Resources - 3.7 million tonnes at 0.93 grams per tonne gold representing 111,000 ounces.

    Athona Deposit:

    - Indicated Resources - 10.9 million tonnes at 0.95 grams per tonne gold representing 333,000 ounces; and

    - Inferred Resources - 2.2 million tonnes at 0.83 grams per tonne gold representing 59,000 ounces.

    - Completed 2007 positive feasibility study on the Box Deposit with the following economics:

    -- NPV, discounted at 8%, of US$50.0 million at US$603.75 per ounce Gold revenues;

    -- Internal Rate of Return of 43.4% using US$603.75 per ounce Gold revenues

    - Planned production of 90,000 ounces per year based on a 5,000 tonne per day operation;

    - Excellent process recovery of 93% of the contained gold values;

    - Updated pre-operating capital expenditures estimated at US$63 million;

    - Environmental permit in place - no development delays anticipated;

    - Pre-feasibility study has been initiated on the Athona Deposit;

    - Both deposits are open pit mineable;

    - Both deposits are open at depth;

    - Excellent local infrastructure with airport, power, telecommunications, good road system, field office, core shack and living quarters and kitchen facilities for employees; and

    - Regional exploration upside including the Golden Pond target where previous drill results were reported as 16.57 grams per tonne of gold over 13.6 metres and 5.07 grams per tonne of gold over 15 metres.

    Wade Dawe, President and Chief Executive Officer of Linear, stated, "The Goldfields Project represents an exciting acquisition and an ideal initial development project for Linear. We look forward to working with thelocal communities as well as the Saskatchewan Government to advance the development of the project and believe that Canada's political stability represents a tremendous strategic advantage for the asset. With manageable remaining capital expenditures of approximately US$63 million and planned low cost production of 90,000 ounces per year, the Goldfields Project is expected to be an excellent platform from which Linear will be able to execute an aggressive growth strategy. In the short-term, we plan to update the engineering documents for the project, complete final permitting applications and recruit a senior operating executive to manage the development and operation of this exciting project. We are confident that based on current gold prices, the economics and overall value of this project is substantially higher than the already robust results returned in the 2007 feasibility study using gold prices that were capped at approximately US$600 per ounce."

    Transaction Details

    The Transaction is expected to be completed following receipt of court approval, which GLR has undertaken to seek on an expedited basis. Upon closing, Linear will pay GLR US$5.0 million in cash and issue 727,273 Linear Gold Corp. shares with a deemed value of CDN$800,000. In addition, upon completion and delivery of certain previously contracted equipment, Linear will reimburse GLR for deposits made in connection with the equipment contracts in the amounts of US$3.0 million and CDN$1.2 million.

    Linear Highlights Following the Transaction

    Upon completion of the Acquisition, Linear will remain a well financed and strategically positioned company with:

    - Over CDN$24 million in cash and cash equivalents;

    - 33.4 million common shares issued and outstanding, representing an attractive capital structure for continued growth and consolidation;

    - Planned annual production of approximately 90,000 ounces of gold following the development of the Box Mine;

    - Proven and probable gold mineral reserves estimated to be approximately 600,000 ounces, measured and indicated gold mineral resources estimated to be approximately 1.9 million ounces and inferred gold mineral resources of 0.5 million ounces. See chart at end of release for details;

    - Significant potential for growth through exploration outside of the current Box and Athona Deposits and continued exposure to Linear's promising Ixhautan Gold Project in Mexico and Ampliacion Pueblo Viejo, Loma El Mate and Loma Hueca Gold Properties in the Dominican Republic;

    - Management and board of directors with experience operating, developing, and financing mining companies;

    - Strategic position to leverage planned consolidation within the gold industry.

    The successful completion of the transaction would resolve the pending injunction proceedings.

    Peter Dimmell, P.Geo., a director of Linear and a qualified person under National Instrument 43-101, has reviewed and approved the scientific and technical information in this press release based on the 43-101 compliant report by Bikerman Engineering & Technology Associates, Inc., June 2007, Revision 1-May 12, 2008 on the Box Mine - Goldfields Project, Uranium City, Saskatchewan, Canada, a Technical Report filed Pursuant to National Instrument 43-101 of the Canadian Securities Administrators filed on SEDAR by GLR Resources.