Thacker Pass...This Week?

If my math is correct, I think we should see the final TP EIS this week or next. Does that sound right? For the ROD to occur under current guidelines by 1/21/21, it'll have to be entered at least 30 business days before ROD. 

Join the conversation about Lithium Americas.

Reply

Replies

  1. "In the summer of 2019, Lithium Nevada Corporation (LNC) submitted a detailed plan for the Thacker Pass lithium mine project in northern Humboldt County, Nevada to the US Bureau of Land Management (BLM) and Nevada Division of Environmental Protection (NDEP).

    On February 5 of this year, the BLM published a Notice of Intent to Prepare a Draft Environmental Statement (DEIS) for the mine. Once the notice of intent was published, the agency has 12 months or fewer to process the EIS under a Trump Administration executive order that mandates a one year timeline.

    On July 29, the Draft Environmental Impact Statement was published, which started a 45-day public comment period that ends on September 11.

    Adding impetus to the approval of the mine is another Trump Administration executive order that gives the project strategic significance. Executive Order 13817 is dated December 20, 2017 and gives the Department of the Interior, in consort with the Department of Defense and other related agencies, the directive to create a list of critical minerals. Lithium is on the list.

    To meet the NEPA decision deadline, a Record of Decision must be issued by February 5 of next year. Lithium Nevada said it is prepared to begin a 2 year construction phase soon after."

    Further down at the end of the article is the following statement:  "After the 45-day comment period closes on September 11, to comply with the new one-year deadline for NEPA decisions, a Record of Decision is due out no later than February 5 of 2021."

    There are a lot of Trump Administration Executive Orders.  So, the question is: What will happen with those Executive Orders in the Biden Administration early on?  That is the kicker, or at least I would think it would be.  If the original due date hold up as a mandate then things haven't changed, but on 20 January 2021 there is more than a good chance that things will change and that "madate" may or may not still be in force, depending on the current U.S. President after 20 January 2021.  I'm not playing either side in that statement, just stating a fact.

    "a Record of Decision must be issued by February 5 of next year" and that would be by 5 February of 2021, if there is no rescinding of the original Executive Order.  I don't feel comfortable in concluding at this point that the original Executive Order will still be in place.  Things change.  Just sayin'

    The article below is where I took the above quotes.  It discusses that issue of the EIS and the ROD and, in addition, discusses the objections of people like Edward Bartell to what he and others view as possible water contamination they claim would be caused as a result of the acid leaching to be utilized at the Thacker Pass Processing Plant.  It really is a good article, although it is a little dated, published all the way back on 28 August 2020.    Okiedo

    Thacker Pass Lithium Mine - Draft Environmental Impact Statement reaction | The Sierra Nevada Ally

    Just to pay Devil's Advocate for a moment, a more optimistic view of the current situation would emphasize the words "or fewer" in the above statement:  "the agency has 12 months or fewer to process the EIS".

    Okiedo

    1. So, my understanding was it was within a year from announcement. I have that at 1/20/20...that's what IR told me too, but 2/5/21 could make sense. For ROD, they have to have the final EIS out for a period...30-45 days I think. My guess is the timeline doesn't change. 

      1. From what I understand, it is one year from when the announcement is officially published in the BLM National Register.  For LAC that occurred on 2/5/20.  The LAC final EIS will need to be published on or before 1/5/21 in order to allow for the required 30 day waiting period before the final record of decision occurs.  Everyone will want to avoid the year end holidays so I suspect the final LAC EIS will be published before 12/18.  Please let me know if anyone else has other thoughts on this timeline.  Go LAC!!   

            1. Replying to @okiedo

              See the below links for detail.  I know there is only a couple of weeks between 1/21 and 2/5 but shareholders should offiicially know the facts.  This is a very important fact to get straight one way or the other.  I believe the 1 year clock started on 2/5/20 but I would love for someone (preferably LAC if you are listening) to prove that it started on 1/21/20.  I own shares but much more importantly I own Calls in LAC with expiration dates of 2/19 and 5/21.  I hope I am wrong about the 2/5 date.  If so I would feel even better about my 2/19 calls.

              Here is the update actual Federal Register notice dated 2/5/20

              https://www.govinfo.gov/content/pkg/FR-2020-02-05/pdf/2020-02247.pdf

              Here is the initial Federal Register notice dated 1/21/20

              https://www.govinfo.gov/content/pkg/FR-2020-01-21/pdf/2020-00851.pdf

              Random news acticle referencing the 2/5/20 start of the clock

              https://sierranevadaally.org/2020/08/28/thacker-pass-lithium-mine-draft-environmental-impact-statement-reaction/

              WB

              1. Replying to @WB DT

                If I get time, I'll try to call LAC's IR people and clarify on timeline again. Last time I spoke with them, they indicated the clock started running on 1/21/20. But, I think it makes more sense to toll from when it actually entered the Federal Register. Either way, I expect that it'll be announced in the next 10-14 days.

      2. Apparently the Scoping Letter from the Department of Interior went out on 22 Jan 2020, although the letter itself does not carry a date on the actual letter, but the internet address for the letter does ( I found that strange for a government document!).  The Scoping Letter has some interesting information in it about Thacker Pass and is a good reference:

        Thacker_Pass_EIS_Scoping_letter_2020-01-22.pdf (blm.gov)

        The actual Scoping Report does carry a specific date and is dated 11 May 2020 and it also has a lot of information:

        TP_Scoping_Report_2020-05-11_FINAL.pdf (blm.gov)

        In the final Scoping Report there is a reference to the period from 21 January through 27 February and that is in reference to the "scoping period".  The actual "scoping process" began on 21 January with the publication of a NOI ( Notice of Intent ) in the Federal Register.  Possibly that is where the 1/20/20 date comes from for the period "a year from announcement".  If 21 January is the marker for the period of "a year from announcement" then we stillhave to consider that it is one day after the official change of administration.  I would suspect that if it is the Biden administration that takes office on that date, as most people assume at this point, then it will be an administration that provides a continuous friendly state towards the development of domestic lithium resources and that amicable relationship would simply continue.

        I found it interesting that in the Final Scoping document there was a reference to 60 non substantive comments that were viewed as speculative or not within the scope of the environmental analysis:

        "Non-substantive Comments Summary Approximately 60 comments were submitted related to issues such as general opinions for or against mining, the viability of the product in the market, or requesting that the EIS analyze topics that are speculative or are not within the scope of this environmental analysis. These comments are not included in Table 5 or Appendix C summaries."

        The 11 May "Scoping Report" went on to say:

        " The final EIS is scheduled to be released in the fall of 2020. The BLM will prepare a Record of Decision (ROD) to document the selected alternative and identify any accompanying mitigation measures. The BLM will issue the ROD no sooner than 30 days after the notice of availability for the final EIS is published in the Federal Register."

        So it would appear, after all the delays from Covid-19 that we are still looking at a date 30 days or more ( "no sooner than 30 days AFTER the notice of availability") after the NOA befor the final EIS is published in the Federal Register.

        When I searced the Federal Register for Thacker Pass I did come up with several things, but the latest appears to be only:

        "EIS No. 20200156, Draft, BLM, NV, Thacker Pass Lithium Mine Project, Comment Period Ends: 09/14/2020, Contact: Ken Loda 775-623-1500."

        It does give the EIS Number and that may be helpful in saving time with future searches.

        The Federal Register:  Federal Register :: Document Search Results for 'Thacker Pass'

        When I ran a search on the Federal Register for:

        "Notice of Availability for the Final EIS on Thacker Pass in Humboldt County, Nevada" I came up with zero information, so I am assuming that the NOA has not been published at this time.

        Sorry, I could not find more at this time.    Okiedo

        1. Hey, guys, I am not the sharpest card in the deck, but unless that Notice of Availability has been published in the Federal Register it would seem that we have 30+ days the clock that starts after the NOA is published.  If it has already been published then let me know and I will sit back and enjoy the ride, but if it hasn't yet been published then we are still on the launch pad.  Okiedo

        2. Hey, guys, I am not the sharpest card in the deck, but unless that Notice of Availability has been published in the Federal Register it would seem that we have 30+ days the clock that starts after the NOA is published.  If it has already been published then let me know and I will sit back and enjoy the ride, but if it hasn't yet been published then we are still on the launch pad.  Okiedo

          1. Yea, so after the final EIS is posted the 30-day clock starts to run. I don't think that the NOA for the final EIS has been posted yet. That is likely to be a catalyst for stock run-up. It basically says that the BLM is giving the project the greenlight. Of course, groups could sue and appeal, but there doesn't appear to be broad or highly focused opposition.