  1. Evans just concluded his potion of the live discussion today, and at lest from my understanding there were a few nuggets of new (or at least confirmed) pieces of information.

    1) He expects the record of descision for TP the 1st or 2nd week of Jan 2021, and expects construction to start by the end of the year

    2) He said they have multiple interested financing partners in America and also Asia and Europe. It will be interesting to see how much of the Lithium in TP is domestically designated, and how much may potentially be global (at least for the short term to faciliate the lack of full domestic battery supply chain in America.

    3) He confirmed our suspicions that they have been approached by multiple parties for offtake agreements, but they are focusing on securing a strategic partner first, since making any offtake agreements this early on could limit their potential partner options.

    4) Another interesting point (assuming I understood correctly) was that he said that at this time LAC are sticking to the initial stages of extracting the lithium. Once they have a partner secured they can adjust to the needs of that partner, where they could bring in more equipment to move further up the supply chain. 

     

    Early 2021 will be a very interesting year for LAC (and I suspect the SP will reflect this), especially once the spotlight is moved off of Covid-19.

     

     

    1. Those were the main points, thanks for posting them here.

       

      Q: did you also hear something about when he was discussing the Reno facility that they have shown that they can extract lithium from ore at scale. If so, is that something new? I mean, we haven't heard anything about Reno in, like, forever, so that sounds like a significant update. 

       

      (Maybe I'm wrong).

  2. WB DT, did you notice the change in the Timeline for production at Thacker Pass?  If you search for Lithium Americas home page and then enter under "Thacker Pass" and scroll down to the Timeline it shows: 

    Q3 2022 est.

    First Production Expected
    Targeted date to start production

       

     
     
     
     
    However, if you go to the 10 December 2020 document.... "Building a Lithium Supply Chain for the USA"...
     ...... the Timeline on that document does NOT show the same "First Production Expected...Q3 2022 est." information.
     
    In fact, for Thacker Pass, the Timeline is blank now on the 10 December 2020 "Building a Lithium Supply Chain for the USA" document for the entire year of both 2022 and 2023.   
     
    Subtle change?   Guess it depends on how you define "Subtle chage".
    1. Okiedo, I may have heard wrong, but I thought I remember Evans saying Thacker Pass would be in full production by 2024. Perhaps he was referring to the phase 2 production ramp up? 

      1. ElithX, you are way ahead of me... doesn't take much!... I haven't listened to the presentation yet.  I wouldn't be surprised if it is now up at 2024.  It isn't unusual for a mining company to keep shifting out ward the estimated dates for construction or production, but it still doesn't make it any easier for that companies investors.  Thanks for your input!   Okiedo