Question re: Production date for Thacker Pass

I haven't seen the latest Jon Evans interview, but "Peter" on TOB did opine that Evans now says production at Thacker Pass is going to be in 2024.

If that is true then it again points to the fact that when LAC management mentions any date for something as critical as the date they go into production, you should take that statement with a considerable dose of salt and I don't mean " a grain " of salt, more like a pound of salt.

  LAC management has, again and again, moved the timeline on one issue or another and the direction of the timeline movement is always further away and without any clarification given.

Now, my overall positive view of LAC is still in force regarding most criteria for assessing LAC but in the specific area of truthfullness about projected calendar dates I would just point out that "truth" in this area is "Relative Truth" and subject to considerable change at the drop of a hat.

I don't mind, so much, the extension along a timeline if only management would step up to the plate and explain fully why their earlier estimates have now been moved back.  Of course it would be quite easy to just mumble "COVID-19" and let it go at that, but LAC management doesn't even go so far as to use that subterfuge as an explanation.  

OK, I have vented.  I still own the same number of LAC shares I owned yesterday, last week and last year.... but I don't like this type of repeated behavior on the part of LAC management in minimizing what is, in my opinion, a very important piece of information to investors:  the Timeline.

JMO   Okiedo 

    PS:  This is habitual behavior on the part of LAC management so it won't be the last time we will see this fluid Timeline maneuver occur before actual production occurs at Cauchari-Olaroz or at Thacker Pass.  In the words of one illustrious poster on TOB:  "You been warned!"   

OK, some of the steam, anyway, has been ventilated.   I feel better... sort of.

Join the conversation about Lithium Americas.

Reply

Replies

    1. That was my understanding also, but if the statement about what Jon Evans said is true then it fits a pattern as I noted in my post about the frequency of moving the Timeline.  Perhaps someone here listened to the entire Jon Evans interview and can comment on whether or not he did say production at Thacker Pass will start in 2024.  My hope is that your view is the valid one, but I have seen them do this over and over in the past.  Best wishes.   Okiedo

      1. Jon Evans exact words were that construction takes two years , so if they start construction later this year than  they can be on Li market by end of 2024.

         In mean time those gready Robins created problems for whole stock market:

        In Unprecedented Move, TD Ameritrade Puts "Restrictions" On Transactions In GME, AMC

         
        WEDNESDAY, JAN 27, 2021 - 12:22

        With the move higher in GME seemingly unstoppable...

        ... and with the SEC silent and refusing to step in and bailout the millions of shorts who remain trampled by the short squeeze stampede, the exchanges have decided to step in and moments ago TD Ameritrade was the first brokerage to announce that "in the interest of mitigating risk for our company and clients", the company has put in place several restrictions in GME, AMC and other securities.

         

        The brokerage said that it imposed these unprecedented unilateral - as in not mandated by either a regulator or the government - actions "out of an abundance of caution amid unprecedented market conditions and other factors."

        Expect many more exchanges to follow suit, because hedge funds clearly need to be protected when faced with the retail daytrading mob.

        Meanwhile, with nobody there to bail them out, the basket of top hedge fund favorites, the Goldman hedge fund VIP stock basket, is plumbing new lows as fears of wholesale liquidations grow as the Goldman basket of most shorted names keeps rising ever higher, a divergence that has made regular readers - who read our November hedge fund summary post - rich, after we said "our advice is to go long the most hated names and short the most popular ones - a strategy that has generated alpha without fail for the past 7 years, ever since we first recommended it back in 2013."

         

        1.  

          If I go well into the history of my comments on TOB, somewhere there is my first guesstimate on when Thacker Pass will start production, I was betting on 2026. I just wonder if that was not too bullish.

           

          Anyway, I am too getting bit nervous about LAC. It the light of recent news looks like my hedge position, which I have established at 30/35 was just not sufficient. The recent market craziness is unprecedented – hedge funds beaten by crazy robinhooders, many companies being inside a massive bubbles, the state of the US economy is not really great, COVID is doing great. That actually may result in another “black Friday”, all we need in few more kicks and I don’t have to remind you, that it is Thursday today.  

           

          1. I see the ol' Pavel is back ;) 

            In all seriousness, the market is just in a very volitile place at the moment. Nothing has changed with LAC, but I personally will be waiting to see when things bottom out before adding shares.

            My personally feeling is that we will see support hold between $17-$19 USD, if not we may be heading back to the ATM days of $10-$12.50 USD. 

             

            As an aside I have to give credit to LAC's management team for raising their $400 million at the perfect time. If this downturn is to continue, they are in a great financial position to weather the storm. 

            I think it may be best for my health to step away from my computer for a few weeks and lets this ride as is. 

            1. Replying to @ElithX

              I am not here to throw water on my own position in LAC. But I would like to know a lot more about LAC's processing method for their large deposit. A major part of their construction has to be their method of processing the so called clay material. Could they be moving the goal posts because they have not perfected their unique  process for this material? Also, they do not have a firm commitment from the locals for water, which must be a major part of handling the clay soil. Prototype processing on the kitchen table does not always scale up for high volume methods. Are they having trouble with their process??

                     ...just sayin'

               

              1. Replying to @clifford

                Perhaps I am too trusting and optimistic, but despite clay/sedimentary being non-traditional, LAC seems to be implementing some straightforward methods. Starting with their resource, according to their lead geologist, Tom Benson, the concentration of lithium in the clay at thacker pass is comparable to the best hard rock deposits in Western Australia. John Evans said in an interview that they will employ a hydrocyclone to separate lithium rich particles from lithium poor. This technology is very straightfoward and works based on the size and density of the particles. I don't believe this setp was included in their PFS and this should reduce the upstream capital expenditures required for the plant, or potentially allow a higher rate of production (if this is a rate limiting step). Unlike spodumene, they do not need to employ a high temperature/high cost roasting step to convert the lithium to a form that is leachable. But like a spodumene, everything downstream in the processing is quite similar, not necessarily the same, beginning with sulphuric acid leaching. I am not an industry expert, but have spent a lot of time scrutinizing their process to identify weakness and nothing jumps out as concerning to the point where it will make or break the underlying investment thesis. Sure, they may go over budget with capital expenses for thacker pass, production may be delayed operating expenses might be more costly, etc. There is not one step I see where operating costs should skyrocket. They will still be a low cost producer, but maybe not the lowest.

                 

                AXP

                1. Replying to @archibald x proctor

                  AXP regarding the hydrocyclone equipment contemplated by LAC for use at Thacker Pass:

                  " John Evans said in an interview that they will employ a hydrocyclone to separate lithium rich particles from lithium poor. This technology is very straightfoward and works based on the size and density of the particles. I don't believe this setp was included in their PFS and this should reduce the upstream capital expenditures required for the plant, or potentially allow a higher rate of production (if this is a rate limiting step)."

                  Microsoft Word - 207071-00100-00-GE-REP-0005_RA_NI 43-101-2018-08-01 FINAL (lithiumamericas.com)

                  This link is the PFS from 1 August 2018 on Thacker Pass by LAC.  Pages 135-141 covers the proposed processing as of the release of the PFS.  Additional references include, in the same document, pages 76-84 and on pages 5-8.

                   Drawing your attention to page 76 of that document, under part 13 ( titled:  " Mineral Processing and Metallurgical Testing" ):  "In 2017, LAC decided to pursue an alternative approach that would reduce overall operational and capital costs, and leverage the physical properties of the soft claystone. To this end, a new process flow sheet that uses conventional leaching and industry-proven purification technology has been developed. Technical indicators obtained from tests so far are encouraging and support continued optimization, pilot testing, and engineering."

                  And for emphasis, look again at that last sentence in the paragraph above:  "Technical indicators obtained from tests so far are encouraging and support continued optimization, pilot testing, and engineering."

                  That continued optimization, pilot testing and engineering is, if I am not mistaken, the purpose of the Reno "Process Research Facility".  So, what has been learned since 1 August 2018 when the PFS was released?

                  Page 6 of the  document includes this statement:  "The current flowsheet does not include an allowance for traditional ore upgrading, and further investigation of ore upgrading is recommended at the next engineering phase, although it is not necessary to the viability of the project."  So the PFS doen't allow for upgrading, but "further investigation of ore upgrading is recommended at the next enginnering phase".  Is the Reno Lab the "next engineering phase" and prior to the DFS?  Just asking.

                  Back to the reference to "hydrocylone" that AXP mentioned in his post today, Yup, there was no reference to the use of the hydrocyclone in the PFS of 2018.  AXP notes a reference to a statement of Jon Evans.  I don't know when Evans made that statement, but an updated Thacker Pass note from LAC, dated 25 September 2019, does in fact make reference to the hydrocyclone technology.  I don't know whether that addition came from LAC directly or from the partner they revealed that year as being the company that would be operating the mine at Thacker Pass:  Sawtooth Mining Company, LLC.

                  The following paragraph from the 25 September LAC NR Update on Thacker Pass does, infact, give reference to the hydrocyclone:

                  "Process Engineering & Design Process Testing Facility The Thacker Pass process optimizes and reconfigures several commercially-proven techniques in extractive metallurgy designed specifically for the processing of lithium bearing clays. To date, Lithium Nevada’s process testing facility located in Reno, Nevada has produced over 3,000 kg of high-quality lithium sulfate brine (“lithium sulfate”) from Thacker Pass ore. The process has been optimized by upgrading the ore through a wet attrition process followed by a hydrocyclone to remove coarse material with relatively low lithium content. The process test work has demonstrated an increase in lithium concentration by over 25% which results in reduced acid consumption per tonne of LCE."

                  Highlights added by me and not in the original paragraph.

                  So, what, exactly, is a hydrocyclone and what does it do?

                  I have poste some time way back about the use of the hydrocyclone on this Hub, but it is worth repeating:

                  The hydrocylone as used in mining dates all the way back to the late 1800's and is anything but new technology.  It is used to separate the big stuff from the smaller stuff, just using plain English to simplify the whole thing.

                  The hydrocyclone establishes internal to its architecture a cetrifugal vortex that is used to separate the discharge from the hydrocyclone into two parts:  an overflow and an underflow.  Ideally this separation will separate fine particles from coarse particles when pressure, volume and internal diameters at key points of the hydrocyclone are all optimized.

                  Anyone wanting to delve into the subject in a little more detail, but not so detailed as to be difficult to understand, should take a quick look at the following link:

                  Hydrocyclone Working Principle (911metallurgist.com)

                  Hydrocyclone is a term that really tells us what happens with this particular piece of equipment.  A water suspension of minerals is pumped, under pressure, into a device where this slurry is separated by the use of a "cyclone" ( that is where the vortex comes into play ) into big particles and small particles.  "Hydro" in reference to water and "Cyclone" in refernce to the internal vortex created inside the separating device.

                  Bottom line:  The addition of Sawtooth Mining Company, LLC has undoubtedly resulted in suggestions and maybe even requirements for modifying the original plans for processing of the lithium clay into lithium hydroxide and lithium carbonate.  So, what modifications in that processing have been proposed.  More to the point:  What modifications have been adopted?

                  Thanks, Clifford, for bringing up the Reno Lab again and thanks to AXP for mentioning the addition of this old technology, the hydrocyclone, as an addition to the processing originally proposed back in the 1 August 2018 PFS.  

                  Okiedo

                   

              2. Replying to @clifford

                Work at the mine site is expected to begin the first quarter of 2021 or so says an article from Desert Fog, linked below.

                I mention this time frame because of Cal's reference to a possible 2024 production date and that it might take 2 years for finalizing construction once it has begun.  If it is indeed 2 years post initiation then we would be looking at 1st Quarter of 2023.  This whole conceept of exactly when production is supposed to start is quite nebulous and seems to depend on which article is being featured at the moment.  LAC management could easily stop this whole confusion by coming out with a definitive statement regarding the estimate for beginning production..... Light Bulb Moment:  maybe they will do that when they publish the "Definitive" Feasibility Study.  Inquiring stockowners want to know:  What and When is really "Feasible"???  We shouldn't have to speculate on a "Definitive" estimated date for the start of production at Thacker Pass.

                Clifford posted the following partial comment:  "I am not here to throw water on my own position in LAC. But I would like to know a lot more about LAC's processing method for their large deposit. A major part of their construction has to be their method of processing the so called clay material. Could they be moving the goal posts because they have not perfected their unique  process for this material?"

                Clifford, you know I have been raising the flag on the LAC "Process Research Facility" in Reno, Nevada for years now.  I will continue to ask, and I think the other LAC stockholders should also be asking, "What is going on at the Process Research Facility and exactly what progress have the made, if any, in regards to refining the processing of the lithium clay resource found in Thacker Pass?"

                I don't think we can possibly shine too much investor light on this question since no one has ever used lithium clay to manufacture lithium carbonate and lithium hydroxide on a commercial scale before.  LAC would be the first and there is just no way to underestimate the importance of the work that supposedly is being done at the Reno Process Research Facility.  LAC should be giving periodic reports on the nature and achievements of this laboratory, it is the arch stone for future success in regards to Thacker Pass.  Thanks to Clifford for bringing up again this topic.  I firmly believe that all retail investors should be equally concerned about it because it will either come back to bite us all in the butt or lead to our ROI dreams for LAC... and we have no news about it, not for quite a while has LAC even mentioned it.  In the words of Ricky Ricardo:  "  'Splain it to me, Lucy!!!"

                OK, the latest article from Desert Fog is pretty much a panaroma of historical developments that have occured and includes the most recent events as well regarding Thacker Pass.  I think it is worth keeping on file and I will post it separately in the Link Library.    Okiedo

                » Lithium Americas Thacker Pass Desert Fog

                1. Replying to @okiedo

                  Just for emphasis, I am repeating part of my previous long post:

                  "  LAC should be giving periodic reports on the nature and achievements of this laboratory, it is the arch stone for future success in regards to Thacker Pass."

                  1. Replying to @okiedo

                    I find that LAC speaks when they have something to say. Evans isn't saying something that is speculative. He waits to have the information that he feels is most solid and then shares it. Let's remember how quickly $450m in $22 shares got gobbled up last week. 

                2. Replying to @okiedo

                  Right now lac hands are tied waiting on approval from nevada the last few page's ( page 21? ) it state very clear they are not allowed to disturb any earth until they get water approval from nevada .

                  My hope is lac has private property close by and they are starting to stock pile equipment and material for starting construction .

                  As far as the refining process i have been reading about cyresses  process in the clayton valley . Cypress does have connections with lilac solutions . Cypress is building a sulfuric acid plant for electricity and sulfuric acid for processing ( better if you read it yourself on cypress web page )

                   

                  1. Replying to @Retiredcash2

                    Do you have any idea, when that water rights approval is due? Nevada has already given LAC some tax releave so it should bejust a formality, hopefully..

                     

            1. Replying to @Bassomatic

              I enjoyed the explanation from Arch on LAC's process. I looked at commercial and mining hydrocyclones. They are just like the air seprarators that we use in our woodshops for evacuating the dust and heavy sawdust and wood chips. I am wondering how large and powerfull these cyclones must be in mining in order to do the separating of water and elements. Then of course the further cooking and leaching to get to a finished lithium product. Which gets me back to the first observation...... how much ground can one get through one separator, and how can the company get to 10's of thousands of tons of finished lithium when they have to process multiples of that from the bare ground?

                  Without sounding Pavelish, I am amazed (curious) at the material they may have to handle to get to the amount of finished product they forecast. I mean, I wanna' see this badass place and and the machinery but I am stuck on the East Coast looking at snow flurries.

              Below is a link to a hydrocyclone separator manufacturer. Lots of neat info and graphics if you want to get down in the weeds.

              https://www.cccmix.com/separating-dewatering/?gclid=Cj0KCQiA3smABhCjARIsAKtrg6KpmIO-paLCaRYW465Yxk6uMWBNcGyZ3slKzQcSRcwZBj3ByesreFoaAheLEALw_wcB