Skip to content
Sign in

Post

Lithium Americas

Treasurer4.8 rating from 7 members637 ptsRate

News

 

 

Lithium Americas Reports 2020 Full Year and Fourth Quarter Results

March 2, 2021 - Vancouver, Canada: Lithium Americas Corp. (TSX: LAC) (NYSE: LAC) ("Lithium Americas" or the "Company") has reported financial and operating results for the fourth quarter and year ended December 31, 2020.

This news release should be read in conjunction with Lithium Americas’ consolidated financial statements and management's discussion and analysis for the year ended December 31, 2020, which are available on the Company’s website and SEDAR. 

All amounts are in U.S. dollars unless otherwise indicated.

Highlights

Caucharí-Olaroz Lithium Project (“Caucharí-Olaroz”):

  • Construction activities at Caucharí-Olaroz continue to advance with enhanced COVID-19 health and safety protocols in place.
  • Capital expenditures for the Project remain on budget with $477 million (84%) of the $565 million committed, including $388 million (69%) spent, as of December 31, 2020.
  • Capital costs attributable to COVID-19 during the construction period, including costs for quarantine and extra camp capacity, are being assessed and now reported separate from the budgeted capital expenditures.
  • Significant progress has been made on the lime plant, solvent extraction plant and lithium carbonate plant.
  • The solar evaporation ponds are well advanced with sufficient brine inventory to support production ramp up.
  • The health and safety of the workforce and surrounding communities remains the highest priority with no positive cases of COVID-19 reported at site in over 130 days.
  • Based on the latest construction schedule, which assumes a reduced workforce at site in accordance with COVID-19 protocols throughout construction, the Company expects first production in mid-2022.
  • In Q1 2021, Marcelo Cabral was appointed General Manager responsible for the development and commissioning of Caucharí-Olaroz. Mr. Cabral was previously with Gold Fields Ltd. and responsible for commissioning MMG Ltd.’s Las Bambas copper project in Peru.
  • In H1 2021, the Jujuy Energia y Mineria Sociedad del Estado (“JEMSE”), a company owned by the Government of Jujuy province, is expected to complete the exercise of its 2012 participation right, at which point it will receive and hold an 8.5% interest in Caucharí-Olaroz.

Thacker Pass Lithium Project (“Thacker Pass”):

  • On January 15, 2021, the US Bureau of Land Management issued the Record of Decision following completion of the National Environmental Policy Act process.
  • All remaining state permits and water right transfers required to commence construction are expected later this year. 
  • The process testing facility in Reno, Nevada, continues to operate with enhanced COVID-19 protocols in place and has produced over 15,000 kg of lithium sulphate solution.
  • The Company continues to evaluate partnership and financing opportunities for Thacker Pass, including the possibility of a joint venture partner.
  • The Company contemplates that the feasibility study will include an initial production capacity greater than 20,000 tonnes per annum of lithium carbonate equivalent previously considered.  Based on ongoing discussions with potential partners and customers, the Company expects that a finalized development plan and timeline of the related feasibility study will be determined as the prospective commercial arrangements are advanced.

Corporate:

  • As at December 31, 2020, the Company had $148 million in cash and cash equivalents ($518 million as at February 28, 2021). 
  • On January 22, 2021, the Company closed an underwritten public offering of shares of its common stock and issued 18,181,818 common shares at a price of $22.00 per Common Share for gross proceeds to the Company of approximately $400 million (approximately $377 million net proceeds).
  • On November 30, 2020, Lithium Americas completed an at-the-market equity program (“ATM Program”) and issued a total of 9,266,587 common shares from treasury for gross proceeds of approximately $100 million ($97 million net proceeds).
  • As at December 31, 2020, the Company had $184 million in undrawn credit with $96 million drawn from the $205 million senior credit facility and $25 million from its $100 million unsecured, limited recourse, subordinated loan facility.
  • In February 2021, Ignacio Celorrio was promoted to President, Latin America to act as the Company’s representative in Latin America and oversee the management of the Caucharí-Olaroz project.
  • In November 2020, Lithium Americas published its inaugural 2019 Sustainability Report prepared with reference to the Global Reporting Initiative Standards, which includes reporting on the United Nations’ Sustainable Development Goals.

Financial Results

Selected consolidated financial information is presented as follows:

 (in US$ million except per share information)

Year ended December 31, 2020

Year ended December 31, 2019

 

$

$

Expenses

(30.6)

(15.7)

Net (loss)/income

(36.2)

51.7

(Loss)/income per share - basic

(0.39)

0.58

 

 

 (in US$ million)

As at December 31, 2020

As at December 31, 2019

 

$

$

Cash and cash equivalents

148.1

83.6

Total assets

326.7

293.8

Total long-term liabilities

(127.3)

(119.2)

 

During the year ended December 31, 2020, total assets increased primarily due to the proceeds raised from the $100.0 million ATM Program, partially offset by a decrease as a result of closing the transaction with a subsidiary of Ganfeng Lithium Co. Ltd. (“Ganfeng”) and cessation of proportional consolidation of Caucharí-Olaroz with transition to equity accounting for the project investment. Cash increased due to the ATM Program proceeds and the $40.0 million of loans repaid to the Company upon closing of the transaction with Ganfeng partially offset by capital expenditures on Caucharí-Olaroz and operating activities, including exploration expenditures on Thacker Pass. Total long-term liabilities increased primarily as a result of a $24.7 million drawdown on the Company’s limited recourse loan facility and a $12.0 million drawdown on the Company’s senior credit facility, partially offset by the effect of closing the transaction with Ganfeng.

Net loss for the year ended December 31, 2020, was $36.2 million compared to net income of $51.7 million for the year ended December 31, 2019. Net income in 2019 was a result of the gain on dilution of interest in Caucharí-Olaroz.

Qualified Person:

The scientific and technical information in this news release has been reviewed and approved by Dr. Rene LeBlanc, a Qualified Person for purposes of NI 43-101 by virtue of his experience, education and professional association.  Dr. LeBlanc is the Chief Technical Officer of the Company. Information on the Company’s data verification and QA / QC procedures is contained in Lithium Americas’ current technical reports for Caucharí-Olaroz and Thacker Pass, available at www.sedar.com.

About Lithium Americas:

Lithium Americas is a development-stage company with projects in Jujuy, Argentina and Nevada, United States.  The Company trades on both the Toronto Stock Exchange and on the New York Stock Exchange, under the ticker symbol “LAC”.

For further information contact:
Lithium Americas Corp.
Investor Relations
Suite 300 – 900 West Hastings Street
Vancouver, BC, V6C 1E5
Telephone: 778-656-5820
Email: [email protected]
Website: www.lithiumamericas.com

Forward-Looking Statements:

Join the conversation about Lithium Americas.

Reply

Replies

  1. Thanks, Cornergrinders for posting this.  

    Lots of things in this release to take note of, but some that struck my attention immediately were:

    • Based on the latest construction schedule, which assumes a reduced workforce at site in accordance with COVID-19 protocols throughout construction, the Company expects first production in mid-2022.
    • In H1 2021, the Jujuy Energia y Mineria Sociedad del Estado (“JEMSE”), a company owned by the Government of Jujuy province, is expected to complete the exercise of its 2012 participation right, at which point it will receive and hold an 8.5% interest in Caucharí-Olaroz.
    • The process testing facility in Reno, Nevada, continues to operate with enhanced COVID-19 protocols in place and has produced over 15,000 kg of lithium sulphate solution.
    • The Company continues to evaluate partnership and financing opportunities for Thacker Pass, including the possibility of a joint venture partner.
    • The Company contemplates that the feasibility study will include an initial production capacity greater than 20,000 tonnes per annum of lithium carbonate equivalent previously considered.  Based on ongoing discussions with potential partners and customers, the Company expects that a finalized development plan and timeline of the related feasibility study will be determined as the prospective commercial arrangements are advanced.

    ______

    So, the time line is moved to "mid-2022" for Cauchari-Olaroz.  OK, I see the Corona virus factor, but it still is a move of the goal post, again.  This will slow the time before revenue starts coming in and remember that the revenue from Cauchari-Olaroz is supposed to help apply toward the development of Thacker Pass, so we are going to see a ripple effect on the timeline for Thacker Pass unless a "Sugar Daddy" can be found in the interim for Thacker Pass.  This just increases the importance of obtaining a Strategic Partner for Thacker Pass.

    What does JEMSE's 8 1/2 % do to the previously stated 49% interest of LAC at Cauchari-Olaroz?  On the face of it must reside a dilution effect.

    Really, this is all we learn about the Reno "process testing facility"?  15,000 Kilograms of "lithium sulphate" and advanced COVID-19 protocols?  I don't care whether they spell it "sulphate" or "sulfate", the core issue for me is still going to be:  What advances in extraction techniques of lithium have been discovered at the "process testing facility" above and beyone those anticipated back when the 2018 PFS was released.  Exactly what progress has been achieved over and above where we started?  What impreovements have been made in what will now be the final processing of lithum clay at the proposed Thacker Pass facility.  Telling me that 15,00 Kg of lithium sulphate has been produced is just a "misdirection play" in this football game where the goal posts keep getting moved back further and further.  

    I am glad to see that the company "contemplates" a greater than previously expected production of LCE will be included in the DFS, however the statement that "will be determined as the prospective commercial arrangements are advanced" in reference to the release of the DFS is just corporate double talk for "We ain't gonna tell you when we will release this DFS", in my opinion.  OK, I know that the company is going to use the same "COVID-19" argument for the further delay in releasing the DFS, they just haven't gone there yet, but they will.  

    The COVID-19 situation has had a real impact on all phases leading to the successful  conclusion of both the Cauchari-Olaroz facility and for the future Thacker Pass facility.  There isn't any doubt about that to investors,.  That doesn't particularly ease the frustration of seeing a moving target for timelines regarding both of these endeavors.  When contemplating timelines in reference to LAC I am always reminded of the Department of Defense contracts with companies that are in the defense industry and how they always extend repeatedly the timeline for finishing whatever product it is that they are building for the Department of Defense.  

    The good news is that things are moving forward at Cauchari-Olaroz and for Thacker Pass.  I should qualify the Thacker Pass situation since we have 2 law suits in progress over Thacker Pass, but I would suppose that most of us feel that those legal hurdles will be successfully overcome in the long view of things.

    It has been a long, long journey and we are not at the promised land just yet.  Onward through the FOG!

    Okiedo

    1. Of course, there will be a dilution of LAC's share in Minera Exar as noted in this footnote from the Annual Report:

      "Pursuant to the JEMSE Option Agreement, JEMSE will acquire an 8.5% equity interest in Minera Exar, which will dilute LAC’s direct and indirect interest in Minera Exar proportionately along with that of Ganfeng upon closing. For more information please see “

      Material Contracts – JEMSE Option Agreement

      Not anything new, we were expecting this, so once the JEMSE slice of the pie is reality then LAC's slice will be slightly less than 45% of Minera Exar and production will still be kicked down the road to mid-2022, another year from the previous timeline.  It will all come together in time.  Lets just hope that the market conditions are as favorable in 2022 for lithium as present predictions for the industry have indicated.  Putting another year on the fire.  

      Okiedo

       

      1. Concerning Thacker Pass, it was good to see this statement in the Annual Report:

        "The Thacker Pass TR was completed in August 2018.  Pursuant to the mine plan in the Thacker Pass TR, LAC contemplates developing an initial Phase 1 production capacity of 30,000 tpa of battery-grade lithium carbonate commencing in 2022 and increasing in Phase 2 to 60,000 tpa in 2026."

         So, we are not, so far anyway, watching that particular "can" being kicked anywhere for the present. 

         This presents a coincidental production date for both Cauchari-Olaroz and for Thacker Pass as 2022.  Now, if the company can just stick with that coincidence then 2022 will be the year we finally see real time production make its role in impacting the share price of LAC.

         In the meantime, and for "one more year" we sit on the side lines and wait for interim news items to make the scene and have their own impact on share price, be it good or bad.  Thank goodness there are a number of positive milestones that should be reached over the next year prior to actual production for both Cauchari-Olaroz and for Thacker Pass. 

         As it now is scheduled, subject to change of course, the "Perfect Storm" ingredients are in the mix:

         

         1) Anticipated higher prices for both lithium carbonate and lithium hydroxide during 2022

         2) Cauchari-Olaroz finally going into production, delayed as it is by COVID-19, but in production in 2022

         3) Thacker Pass in production in 2022, assuming that all water issues are resolved and that there is no adverse litigation result for LAC's Nevada Lithium .

         

         IF these 3 events occur during the same calendar year, 2022, then the "Storm" should be just in reference to how high the share price will be blown upward by that confluence of positive factors.   JMO

         Okiedo