Mining a clay material

If one wants to learn about mining spodumene, it is easy to research and even watch videos. If you want to know about lithium brine processing, there is plenty of graphic information available. But tell me, am I missing something or is mining and successfully processing a softer, and often claylike material a major unknown?  I have seen some graphics of cyclonic separators that might be used for this. And there may be scads of lithium per ton of raw material at Thacker Pass, but getting it out of the mined raw product in a scaled up manner still seems to be an expensive, secretive proposition. I believe that LAC is not in a great financial position without a major partner, and that management is just sitting on their hands, waiting for a white knight. 

Join the conversation about Lithium Americas.

Reply

Replies

      1. There seem to be the two uncertainties about the process, how you separate the liquids from the solids and whether the concentration of the lithium sulfate in the leachate is high enough for the process to be competitive with other downstream purification processes. The chemistry of the downstream process is not a large concern. It will likely be tailored to the chemistry of the leachate, but each step is standard on its own. 

        The details are a little sparce in the PFS, but pg 137 contains the following: 

        "After Ore Preparation, the ore will be transferred as a slurry to the Leaching circuit. Sulfuric acid will be mixed in with the slurry to liberate the lithium from the clay. The leaching process will take place in stirred reactors designed to (a) maximum lithium dissolution from the ore and (b) optimize sulfuric acid consumption. The lithium bearing solution, i.e. “lithium brine”, will be separated from the leach residue by filtration. The filtered residue will be washed to recover any remaining free lithium, and then conveyed to the clay tailings facility. The wash solution will be recycled to the slurry ore in the attrition scrubbers. Crushed limestone and residue from the neutralization filters (Section 17.1.3) will be added to the leach clay residue to produce a geotechnically stable clay tailings."

        Elsewhere in the PFS:

        "The properties of the claystone after leaching show acceptable settling and filtration rates. Washing of the spent clay showed very high lithium recoveries."

        Not sure what "acceptable" means...

         

        The article I posted on extracting lithium from clays may not be the most helpful. It appears to be from the late 1980's. It was written with regards to the McDermitt Caldera (Thacker Pass) and I hoped it might have some more details as to how to get the lithium sulfate leachate out of the clay. This article identified belt filtration which I believe may still be relevant technology. Maybe something like one of the following:

        https://www.youtube.com/watch?v=eBbPIxkYfPI

        https://www.youtube.com/watch?v=W2UIZqdkTyE

         

        I am optimistic about the progress being made.

        From the PFS pg 6:

        "The current flowsheet does not include an allowance for traditional ore upgrading, and further investigation of ore upgrading is recommended at the next engineering phase, although it is not necessary to the viability of the project.

        and from the recently released annual report:

        1. Process Engineering and Design Update

          A process testing facility and laboratory has been commissioned in Reno, Nevada to optimize the process (predominantly to reduce the consumption of sulfuric acid), prepare tailings samples for stability and geochemical analyses, and to provide feed samples to crystallizer vendors who will design the equipment and are expected to provide performance guarantees. The results of the pilot plant test work will be used to finalize the design of the front-end of the process where lithium is extracted (dissolved) from the ore. To date, Lithium Nevada’s process testing facility has produced over 15,000 kg of high-quality lithium sulfate brine at the Thacker Pass Project. The process has been optimized by upgrading the ore through a wet attrition process followed by a hydrocyclone to remove coarse material with relatively low lithium content. The process test work has demonstrated an increase in lithium feed concentration, which results in reduced acid consumption per tonne of LCE. In addition to optimizing acid consumption, the process testing facility has also generated tailings samples that are being used for stability and geochemical analysis, as well as feed samples to crystallizer vendors who will design the equipment and provide performance guarantees.

        AXP

        1. Again, AXP, thanks for your post.  Your focus on the reduction in the acid required per tonne of Lithium Carbonate Equivalent is well taken regarding the purpose of the Reno Processing Lab.

          From your previous posts, I believe you have extensive history in the mining industry.  For those of us who do not, myself definitely included, would you elaborate in more basic language anything else you can tell us about what you have concluded in regard to your concerns and anything positive you have concluded along these lines for LAC.  Simple helps.   Thanks.    Okiedo

          1. The use of water at Thacker Pass is going to be a major hurdle, bigger than sage brush problems. Water use in mining is paramount to any process, and clay separation is still a drawing board to pilot project process. As indicated in various documents, there are still machines and equipment that needs to be designed and built to handle a process that has never been done before. Who is doing this designing and building of these so far phantom machines? What might they look like, how will they work, and ultimately what will the cost be for machinery used in a process that has never been accomplished before? I would surely like to hear from someone that knows more than I, but I maintain that LAC management has still not figured out how to move forward successfully, either financially or mechanically. They are going to need lots of money, and I don't believe that they are in the driver's seat but rather at the mercy of predators. As for the ranting from the environmentalists, well that is nothing new and would most likely be heard out and result in stock platitudes from the Feds and State regulators with proposals for tightening public safety measures. The mine will be built, some time, somewhere. The price of lithium will no doubt rise incrementally, but should be no more than a commodity. And there is always money to be made in commodities.  Go LAC..!?

            1. Replying to @clifford

              Clifford: "Who is doing this designing and building of these so far phantom machines?"

              Say, Clifford, I believe the Annual Report had something to say about that, although I am not certain after reviewing those statements in the Annual Report if it is specific to the actual ID of "Who is doing this designing and building" or not.  Is it Sawtooth or is it EXP or ITAC?  I get the impression that it is Sawtooth, but what is your interpretation?

              ________________________________________________________________________________________

              page 14: "The Company has engaged experienced crystallization vendors to develop the design and cost estimate for process equipment to be used to manufacture battery-quality lithium products from lithium sulfate, including lithium carbonate and lithium hydroxide."

              Commercial Agreements over on page 16 goes farther:

              "During Q2 2019, Lithium Nevada entered into a mine design, consulting and mining operations agreement with Sawtooth Mining, a subsidiary of NACCO Industries Inc. and North American Coal.  Sawtooth Mining has exclusive responsibility for the design, construction, operation, maintenance, and mining and mine closure services for the Thacker Pass Project, which will supply all of Lithium Nevada’s lithium-bearing ore requirements.  Sawtooth Mining has agreed to provide Lithium Nevada with the following (i) US$3.5 million in seven consecutive equal quarterly instalments, with the final payment received in October 2020; and (ii) engineering services related primarily to mine design and permitting.  During construction, Sawtooth Mining has agreed to provide initial funding for up to US$50 million to procure all mobile mining equipment required for “Phase 1” operations.  Excluding these Sawtooth Mining investments, Lithium Nevada bears all costs of mining and mine closure.  Lithium Nevada has agreed to either pay a success fee to the mining contractor of US$4.7 million upon achieving commercial production, or repay the US$3.5 million without interest if the final project construction decision is not made by 2024.

              Lithium Nevada has also entered into master services agreement with EXP, ITAC and M3.  EXP has responsibility for the design and costing of the acid plant; ITAC has responsibility for leading the engineering design of the chemical plant, water supply infrastructure and electrical infrastructure; and, M3 has responsibility for the civil and general site works and overall cost estimate of the feasibility study."

               

               






               

               

              16




              "
          2. @Okeido I have ZERO experience in mining. My background is in Biomedical Engineering and Chemistry and I have spent a few years working in R&D for specialty chemical produciton working at lab and pilot plant scale. I am familiar with a lot of the chemical processes proposed and some of the physical processes described in LAC's feasibility studies for Thacker Pass and C-O. This allows me some competence, but not expertise, in looking at the purification process proposed and the ability to go into more depth to fill in some of the blanks. What I do not possess as background, I source from reading and watching videos on mining for other chemicals as well reading feasibility studies written by other lithium developers. 

             

            For Thacker Pass, there has always been the big question mark hanging in the air as to whether battery-grade lithium can be purified economically from a sedimentary or clay-like deposit. This was my motivation for researching the proposed physical and chemical processes. In my previous post, I brought up two concerns. The first was the physical processess of working with clay as an input to the process. I take for granted that most people are familiar with the propsed process of using sulfuric acid to dissolve lithium minerals out of the clay into the liquid acid solution. The concern would be removing the liquid from the clay. The particle size is very small and my sense is clay likes to hold onto water. Therefore, it could be perceived as difficult to remove the liquid phase containing acid and dissolved lithium (aka leachate or brine). Low efficiency would be a concern because that would mean high acid consumption, low lithium recovery, and hazardous sulfuric acid filled tailings. I looked into this process and there seem to be well-established technologies for processing clays such that I do not share these concerns. The second concern I brought up was the concentration of lithium in the liquid phase. I am not sure we have a value for what the percentage of lithium in the leachate is. For context, I tried to put this in the context of hard rock and brine operations. We know that spodumene is enriched from ~1.2 up to ~7% lithium oxide prior to roasting and acid leaching. By comparison, brine pumped out of the ground at Cauchari-Olaroz contains 600 mg/L (0.06%)% which is then concentrated through evaporation to 10.5 g/L = (~1%) prior to chemical processing.  I do not know what the concentration of lithium in the leachate from spodumene is as a point of comparison, but presuming it is proportional to the starting material, it likely falls somewhere above that of concentrated brine. The clay at Thacker Pass that will be processed is around 3500 ppm Li (~0.3%). The PFS indicates that the concentration of lithium in the leachate is ~0.3% (pg 80 of the PFS).This would put the concentration of lithium in leachate from Thacker pass ~ 3-fold lower than that of brine. This suggests to me that there might be more capital expenses associated with handling the larger volume of solution and energy required to concentrate and crystallize lithium. 

             

            Since the PFS, the planned process for Thacker pass now includes ore upgrading which will increase the concentration of lithium in the clay prior to acid leaching, but we do not know what the extent of upgrading will be or the final concentration of lithium in the new leachate. Taking the worst case, I am assuming no appreciable increase in concentration of leachate from clay above the 0.3% reportered in the PFS. The concerns for the downstream purification of lithium from the acid solution are whether lithium can be recovered from what I assume will be a relatively dilute lithium solution relative to other processes as well as expense of removing impurities relative to the leachate from spodumene or concentrated brine like that at Cauchari-Olaroz. Ultimately, we will have to wait and see how economical these processes are at scale.

            As a potential positive, I see the improvements brought by ore upgrading as coming in ways that might not be expected at a quick glance. Reduced sulfuric acid consumption will reduce cost, but the senstivity analysis for suggests the process is not very senstivite to the price of sulfur, so I would not expect an appreciable reduction in costs associated with sulfur. What is unclear from the Thacker Pass PFS are other savings associated with reduced acid consumption including reduced Capital Expenses (either a smaller sulfuric acid plant or same sized plant that has a higher capacitity for LCE produced), perhaps reduced chemical costs for acid neutralization, and maybe reduced costs for dealing with the tailings. 

            Another positive I have mentioned before is that the lithium in the clay at Thacker Pass does not require high temperature roasting prior to acid leaching. Roasting converts the lithium mineral from a form that can't be leached into acid to one that can. This in contrast to spodumene deposits and shale at Bacanora in Mexico. Not only is roasting energy intensive, expensive, and arguably not consistent with ESG. 

            Another concern brought up by I believe the CEO of Cypress Development is the sulfuric acid chemistry. Apparently this can cause build-up of mineral precipitates on equipment. I think he is proposing a hydrochloric acid baced chemistry for their process and stated this mineral build-up is not a concern. However, sulfuric acid leaching is used in the purification of metals, so I imagine there are plenty of solutions to this potential problem. 

             

            AXP

             

            Lithium Americas Corp.

            Technical Report on the Pre-Feasibility Study for the Thacker Pass Project, Humboldt County, Nevada, USA

            Four different grades of lithium claystone, which combined are representative of the entire ore body, were leached at the process conditions established by previous tests (Lithium Americas Corp. 2017b). The solids were filtered then washed with water. The total leachable lithium was measured for extraction efficiency (both in filtrate and wash water). The results are summarized in Table 13-1.

             

            The data shows that leach recovery and acid consumption can be dependent on ore type. This information was used in the process model.

            13.2.1.4 Acid Recycle

            Experiments were performed to examine the potential for recycling the leach solution, which would work towards improving recoveries and reducing the operating costs (Lithium Americas Corp. 2017c). Using identical leach conditions as described in Section 13.2.1.1, the recycled leach solution was readjusted to the target acid concentration and the required volume by adding more acid before injection to the next successive leach. Each test was run in triplicate to verify reproducibility.

            The results demonstrated that the leach solution could be effectively recycled to improve recoveries and reduce processing costs. The concentration of elements in solution, including lithium, increased as the number of leaches increased. After the second recycle, the solution formed a precipitate (MgSO4*7H2O) as it cooled, which is advantageous for removing unwanted magnesium in the solution. The amount of acid consumed over the recycle experiments was 22.82 g H2SO4/g LCE. These tests demonstrate that a major benefit of recycling the leach solution is generation of a liquor that is more concentrated in lithium, and uses less acid overall per unit lithium, than a single pass leach.

            The filtrate of the final recycle leach liquor was saved and used as the ‘mother liquor’ for further testing (see Section 13.3.2).

             

            1. Replying to @archibald x proctor

              Archie, thank you for the extensive explanation and education. I can only hope that the basic mining and more involved chemical processes can be done at scale and economically. But my instinct and experience with lead times cause me believe that there will be no major production results for.... years. It has already been a decade to this point indicated by LAC's own documents. The capital going into salaries over this time is considerable, and there does not seem to be an end very soon. As for the hold up due to the environmentalists, that is probably a small hurdle. The decimation of our environment over time, such as coal recovery mountain top removal shows that anything goes. And the beat goes on.....

            2. Replying to @archibald x proctor

              Terrific.  I have some background in Chemistry eons ago, though the recovery of that long ago instruction is somewhat akin to squeezing lithium out of clay, so I was able to generally follow your flow in your response.  Certainly I was able to harvest much more information from your reply than ever was included in a PR concerning the work being done at the process research facility in Reno.

              I appreciate the no sugar coating writing style you utilized in expressing your concerns on the processing of lithium clay, the leach solution, the leachate and the recovery and reutilization of the sulfuric acid.

              I know it took a little time to make your reply, time that is much appreciated.  Thanks!  Okiedo

              1. Replying to @okiedo

                Thanks AXP.  On a personal note I use to work with component similar to sulfuric acid, that required special safety precautions and regular inspections, wish  in a future they would improve process to something less corrosive, eventually.

                AS MUCH AS T-P IS IMPORTANT FOR LAC’s FUTURE  C-O REMAINS NUMBER ONE TARGET IN MY BOOK.

                 That constant moving of goal post really aggravating. I know that Argentina is in worse shape Covid wise then US , so understandably company is having hard time. Still, all attention needs to be focus there, I think. Company needs to become a producer ASAP. As they say : learn how to walk before starting to fly.

                  Until LAC becomes a producer it is still a junior miner and without revenue its SP is open to huge swings.

                 Here is latest video:

                Cauchari-Olaroz Lithium Project - Construction Update Feb 20 2021 - YouTube

                1. Replying to @cal

                   Thanks, Cal.  As I watched that video I had to ask myself:  "How fast could I work at 13,000 plus feet elevation?"  To complicate things, as we proceed into Spring here in North America, they will enter Autumn in South America... with Winter not all that far away.  How fast could you work in Winter at 13,000 plus feet?   When you consider all the factors, they haven't really done too badly with the construction and a work force reduced by 2/3ds and a suspension of all work temporarily thrown in as a kicker.   Not too bad.  Onward through the FOG!    Okiedo

                  1. Replying to @okiedo

                    Thank you to everyone for quite interesting debate. To "wrap it up" on my side and to add few comments on the Annual Report, it seems to me, we still live on quite high doses of hoppium:

                    • Thacker Pass does not have green light to "disturb the land" on site
                    • The separation and purification process probably works in Reno on a "production line", constructed from an array of laboratory beakers, filtration papers and burners,  but nobody yet has scaled this operation up to receive 60k tons of an output.
                    • That is supported by following statement “…Engaged third-party vendors to engineer and design …evaporator and crystallizer...”. Here I sense sizeable amount of uncertainty and my translation to plain English is : “Well, we had talked to few companies about our process and needed equipment, but they all thougt, that we are complete whackers and have turned us down. But hey, do not worry, we still have few phone calls to make.”

                    Further points, taken from scanning the annual report:

                    • Eventually, C-O will start production. But the relative progress, reported via their  presentations is quite slow.
                    • Taking that into consideration, it is very unlikely, we will see first ton earlier than October-December next year. LAC says, that construction is on plan, but nobody knows, what their plans are, it can be whatever.
                    • They got about 2 months to work outside, unless they got something to finish inside those building, not even the locals would work trough the winter (6 months zero progress).
                    • LAC can swim in concetrated brine, thanks to repeated delays, the completed ponds are full.

                    • Thacker Pass development scares the siht out of me.
                    • LAC has contract with  diggers and probably a pipeline of those interested in the output. Minor issues: nobody knows how to process million tons of a clay into battery grade Lithium
                    • No reference, when the project may start (used to 2025 if I remember correctly).
                    • Considering growing price of agricultural products, management should consider use that land to grow cows and remote areas convert into a national park.

                    Take away:

                    • Never leave LAC report for weekend reading. Time is money and in case of LAC, the delay was quite expensive. The writing was on the wall.
                    • Robinhooders and other FOMO investors were reduced to ashes over past 2 weeks (you can read their testimonials on TOB) , those being short have made their money and should be closing positions
                    • My sophisticated evaluation model indicates fair price of $13/share (that does not yet include costs associated with building the farm and the welcome center), hence selling puts around $10 (6% on May strike) may either generate reasonable premium or provide reload position for next FOMO sprint.
                    • Unless my understanding of the report was horribly wrong, nothing will happen till the end of summer. Lithium price will move higher, so LAC share price should gradually drift toward $19, supported by reincarnated Robinhooders
                    • Next Cauchari-Olaroz project delay announced in September.  

                    Have a nice Sunday :-). And yes, I am still disapointed.

                    1. Replying to @pavel

                      @Pavel - Here is my response to your statement below:

                      • That is supported by following statement “…Engaged third-party vendors to engineer and design …evaporator and crystallizer...”. Here I sense sizeable amount of uncertainty and my translation to plain English is : “Well, we had talked to few companies about our process and needed equipment, but they all thougt, that we are complete whackers and have turned us down. But hey, do not worry, we still have few phone calls to make.”

                      In my experience in industry, I have worked on a project where we commisioned a crystallizer at production scale. The technology is no mystery, but tailoring it to a specific process or product is not without some challenges. There will definitely be a period of optimization once they start putting their lithium solution through it to make sure they are getting sufficient recovery AND purity. Any third party vendors contacted will look at their process and I expect will offer some minimal guarantees as to recovery, operating cost, and perhaps purity. No one is going to consider LAC "whackers", they just may have difficulty providing the guarantees that LAC requires. I struggle to see this aspect of the lithium recovery process as a significant hurdle. It may cost more than initially anticipated in terms of CAPEX and/or OPEX, but it is not going to be difficult at scale and should not on its own make or break the project.

                       

                      For anyone unfamiliar with the chemistry described in the PFS starting on pg 136, I will try to offer a simplified explanation. The sulfuric acid leaching of the clay doesn't just remove lithium (Li+, 0.3%), but also other elements such as potassium (K+, 3.6%), magnesium (Mg+, 5.6%), and sodium (Na+, 1.2%) with percentages provided representing the percent by weight of these elements in the clay/ore. Other impurities will also be leached out, but for simplicity I will ignore these for the sake of this discussion.

                       

                      There are two options for purification, selectively remove lithium from solution or remove everything else leaving just lithium behind. LAC is using both approaches, first removing magnesium, then later removing lithium and leaving everything else behind. Removing something can be done by changing temperature, pH, or adding another chemical to the process. When adding chemicals to the process, the strategy is to add something to the solution that is relatively easy to separate from lithium in downstream process in order to remove something that is more difficult to separate from lithium in the downstream process. Sequentially, each step of chemical addition and removal should allow for separation of lithium at increasingly higher purity. 

                       

                      I will give a quick example relevant to the initial point of discussion on crystallization and my previous concerns about the relatively low concentration of lithium in solution in previous posts. In figure 17-4 of the PFS on pg 137 describes the process flow sheet. The last step describes removing Li+ in the form of lithium carbonate and leaving behind Na+ and K+ in solution. This is done by adding sodium carbonate to the solution. The way this works is that the sodium (Na+) and carbonate (CO3-) dissociate in solution and are free to react with other species. For reference, the solubility of sodium carbonate is ~35% weight per volume of water at room temperature and the solubility of lithium carbonate is ~1%. I presume the concentration of lithium at this step will be below 1%, lets presume 0.3% which was measured in the starting sulfuric acid leachate. When adding sodium carbonate, nothing should precipitate out if lithium carbonate remains below its limit of solubility. When this liquid is sent to the evaporator, heat (and maybe vacuum pressure) is used to remove water and increase the concentration of the lithium in solution. Once  the concentration exceeds the limit of solubility ~1%, lithium carbonate (Li2CO3) will spontaneously crystallize, precipitate out and can be removed by filtration. After lithium crystalls are filtered out the solution still contains ~1% lithium. They will cycle this stream back into the process per: "The zero-liquid discharge crystallizer will purge a small amount of barren lithium brine back to the liming system (Section 17.2.2) to maintain a predetermined lithium concentration in the crystallizer that will optimize lithium recovery." My concern is with the amount of energy required to remove the water during evaporation. If the concentration of lithium in solution is lower at this step, say 0.1% instead of 0.3%, this requires 3X more energy to remove the water. I don't know at what concentration of lithium the process becomes economically unfeasible. I have this same concern for direct lithium extraction methods. 

                       

                      I want to raise awareness about a detail of the lithium recovery process that may affect the ESG claims with regards to carbon dioxide generation. LAC touts their process as not generating carbon dioxide as they will generate an excess of electricity from their sulfuric acid plant. However, fossil fuels are not the only way carbon dioxide is sequestered out of the atmosphere or trapped in a non-gaseous form. Carbon dioxide can also precipitate out as minerals such as calcium carbonate, or limestone. I am making this point because their process utilizes limestone to neutralize their sulfuric acid leachate at a rate of 3.51 tonnes of limestone per ton of lithium carbonate. In other words, they are putting in 2.6 parts carbonate in the form of limestone for one part carbonate out in the form of lithium carbonate. This is in addition to sodium carbonate (a.k.a baking powder) added prior to crystallization where carbonate should be swapped 1 for 1 between sodium carbonate and lithium carbonate. Here is what happen when limestone (a.k.a CaCO3 or calcium carbonate) is added to a sulfuric acid solution. The carbonate spontaneously changes to carbonic acid, carbonic acid and interconverts to carbon dioxide, but the amount of carbon dioxide will exceed the solubility of the gas in solution and will fizz out. This is akin to mixing vinegar (acetic acid) and baking soda (sodium bicarbonate) which is done to make volcanos for science projects. None of the other streams appear to account for this excess carbonate or any recovery and recycling of carbon dioxide. This could be a very significant source of carbon dioxide emissions.

                       

                      AXP

  1. And here I am thinking that LAC is in the cat bird seat as they have applied for patents on a new secretive process. 

      1. I posted an opinion of Mr. Wilbert's opinion piece over on the Off Topic Forum.  Just some passing thoughts about his "Claim to Virtue" paint brush for LAC management and LAC stockholders.  Attacks against LAC are going to continue and they won't stop once production has commenced.  Just something that goes with the territory of any company attempting to engage in mining here in the U.S.   Okiedo