Dear Agoracom Family,

I want to thank all of you for your patience with us over the past 48 hours and apologize for what was admittedly a botched launch of our new site.

As you can see, we have reverted back to the previous version of the site while we address multiple forum functionality flaws that inexplicably made their way into the launch.

To this end:

1.We have identified 8 fundamental but easily fixable flaws that will be corrected in the coming week, so that you can continue to use the forums exactly as you've been accustomed to.

2.Additionally we will also be implementing a couple of design improvements to "tighten up" the look and feel of the forums.

Sincerely,

George et al

Message: Completes Successful Production Well Drilling for Blue Mountain

Completes Successful Production Well Drilling for Blue Mountain

posted on Mar 25, 2009 01:40PM
March 25, 2009
Nevada Geothermal Power Inc. Completes Successful Production Well Drilling for Blue Mountain 'Faulkner 1' Geothermal Power Plant

Construction Update

VANCOUVER, BRITISH COLUMBIA--(Marketwire - March 25, 2009) - Nevada Geothermal Power Inc. (NGP) (TSX VENTURE:NGP)(OTCBB:NGLPF) today announced that production drilling is complete for the Blue Mountain 'Faulkner 1', 49.5 MW (gross) binary cycle geothermal power plant. The latest three production wells (14-14, 15-14 and 17-14) based on initial testing, have similar production capacities (7.0 - 7.5 MW (net) each) to the original three wells (23-14, 25-14 and 26A-14).

NGP has two completed injector wells (58-15 and 58A-15) and is currently drilling two additional injector wells (57-15 and 61-22).

The power plant construction under the fixed price, date certain Engineering Procurement Construction (EPC) contract with Ormat Inc., a subsidiary of Ormat Technologies Inc. (NYES:ORA), has made great strides over the last six weeks, and NGP is delighted to provide you with the following status report:

- Control, administration and maintenance building nearing completion;

- Vaporizers, diffusers, and condensers are installed;

- Three generators delivered and installed on foundations;

- Cooling tower frame erection commenced;

- Ormat to deliver first set of power turbines by the end of March;

- Switchyard structure has advanced to construction;

- 'Faulkner 1' substation construction commenced;

- Wilson Utility has commenced construction of the 21-mile power transmission line (T-line) that connects the 'Faulkner 1' T-line to the NV Energy switching station at Mill City with completion expected at the end of May 2009.

To view progress at Blue Mountain, please click on the link to view slideshow: http://www.nevadageothermal.com/i/Ph... or go to our website: www.nevadageothermal.com and click on Gallery section.

About Nevada Geothermal Power Inc.:

Nevada Geothermal Power Inc. is an emerging renewable energy developer focused on producing clean, efficient and sustainable geothermal electric power from high temperature geothermal resources in the United States. NGP currently owns a 100% leasehold interest in four properties: Blue Mountain, Pumpernickel, and Black Warrior (all of which are ideally situated in Nevada), and Crump Geyser in Oregon. These properties, which are at different levels of exploration and development, are estimated to have the potential for the generation of over 200 MW.

NGP's phase 1 development at Blue Mountain, 'Faulkner 1' 49.5 MW gross power project is On the Road to Revenue and is expected to be Turning on the Power during the fourth quarter of 2009.

Nevada Geothermal Power Inc.

Brian D. Fairbank, P. Eng., President & CEO