In this Financial statement it says that there could be a considerable amount of time yet before all permitting is complete. It was my opinion that this submission in March was the last one required before mine operation. Could someone please enlighten me. Thanks Creeker

Join the conversation about NorZinc Ltd.

Reply

Replies

  1. It's the last one required. The data must be analyzed by various government agencies, and they take a LONG time. The last time frame I saw mentioned was less than a year. Hopefully, we'll get the go-ahead by the end of 2010.

  2. Table 2 provides an estimate of the timelines required for the major milestones in this environmental assessment. These are estimated timelines largely dependent on when the Developer’s Assessment Report is received; the work plan timelines will be updated once this occurs.

    Table 2 – Estimated Schedule for EA0809-002: Prairie Creek Mine MILESTONE (BOLD TEXT INDICATES COMPLETED STEP)

    Estimated completion

    Bold indicates already completed steps as of April, 2009

    Referral environmental assessment and start-up

    August 2008

    Scoping Sessions Preparation

    September 2008

    Scoping Sessions in Dehcho and Yellowknife

    October 2008

    Scoping Submissions by Interested Parties

    October 2008

    Request for Ruling on Scope of Development

    March 2009

    Preparing draft Terms of Reference and Work Plan

    May 2009

    Comments on draft ToR and Work Plan

    June 12, 2009

    Final Terms of Reference and Work Plan

    June 26, 2009

    Developer’s Assessment Report (minimum)2

    November 2009

    Review Board Conformity Check and Deficiency Statement (if required)

    November 2009

    Developer’s response to the Deficiency Statement (if required)

    December 2009

    Technical Session (DAR gap analysis, if required)

    January 2010

    First Round IRs

    January 2010-

    Developer’s response to First Round IRs

    February 2010

    Preparation of Roundtable technical meetings

    February 2010

    Roundtable technical meetings

    March 2010

    Second Round of IRs (if required)

    April 2010

    Responses to Second Round of IR (if required)

    April 2010

    Parties’ technical reports

    May 2010

    Pre-hearing conference

    May 2010

    Preparation for Public and/or Community Hearing(s)

    June 2010

    Conduct of Public (FS) and/or Community Hearing (NB)3

    June 2010

    Undertakings, 3rd Round IRs (if necessary)

    July 2010

    Closure of Public Registry

    July 2010

    Review Board Report of Environmental Assessment

    October 2010

    Review Board’s Report of EA to the Federal Minister

    October 2010

    Federal Minister’s response to the Review Board’s Report of EA

    ---

    ESTIMATED SCHEDULE