Could you please provide clarification regarding the intended meaning of the following statement from the May-09 Noront NR?

"The remaining work orders for analysis with respect to the anomaly drilling in the vicinity of Eagle One, including Eagle Two are currently being processed and reviewed, results of which will be released as soon as they are available."


Does this statement mean:

1) That the remaining samples(work orders) are still being processed(analyzed) by SGS.

or

2) That all assays referenced in the May-02 NR have been received by Noront and are being processed through Noronts internal systems (QA/QC, Database entry etc..)

Thank You

Join the conversation about Noront Resources.

Reply

Replies

  1. The sentence before states :

    All outstanding work orders are now received and have passed Noront's QA/QC program.

    Hence, the sentence you have quoted relates to Noront processing the received results. All the results are now received from SGS. As you will know there are a lot of results to process and assemble into a good NR.

    SGS would have released the results as they finished each batch.

    I suggest that it is likely that Noront recived DE1's results earlier in the week and assembelled Friday's NR whilst they waited for the rest of the results from SGS. It would be sensible to release the results in some form of order, and Noront would have wanted to know they had the ability to do that, and it would be quite lawful to wait for the entire results before the initial release.

    Let us hope Mr Novak doesn't mind working the weekend.