Feasible

Does anyone here have any idea what a good budget number would be for a feasiblity study...on the Eagle's nest Blackbird Complex?

Is it possible that this could cost about 15 million - and that this financing is more about the "color of money" being used for this contracted study?

Just thinking out loud....

Kurt

Join the conversation about Noront Resources.

Reply

Replies

  1. Feasibility price depends on amount of information they will need to process on the mine itself. But in their mandate they may also be including calculation of transport and processing costs at a more convenient location (Thunder Bay, Timmins or Sudbury ).

    They will likely also visit the rail line issue.

    It will cost millions $ but I doubt it will be full 15, at least I hope not.

    Micon is a leader in this field and it is no mistake or happen chance that they are involved in other projects that may supply synergy to Noront's study. They were a good and natural choice.

    I am perfectly relaxed about them doing the work at a reasonable cost. Cheers.

    1. Mining Field: Feasibility Studies

      Area: Cost
      • The cost of a detailed feasibility study will be in a range from ½% to 1½% of the total estimated project cost. Source: Frohling and Lewis
      • The cost of a detailed or "bankable" feasibility study is typically in the range of 2% to 5% of the project, if the costs of additional (in-fill) drilling, assaying, metallurgical testing, geotechnical investigations, environmental scrutiny, etc. are added to the direct and indirect costs of the study itself. Source: R. S. Frew

      Area: Time
      • The definitive feasibility study for a small, simple mining project may be completed in as little as 6-8 weeks. For a medium-sized venture it may take 3-4 months, and a large mining project will take 6-9 months. A world-scale mining project may require more than one year. Source: Bob Rappolt and Mike Gray

      http://www.infomine.com/SearchMiningRule.asp

      1. Awesome! Thanks Luker!

        1% of 1.5 billion is 15 million - now haven't numbers in the 1.5 billion range been tossed around as a ballpark as to the cost of infrastructure, concentrator, transportation.....

        Just trying to put out some possiblities as the the timing, purpose, and size of the current financing - also times out nicely with the time lines that Luker found - looks like management is planning in terms of large and big......that works for me! large share price...big profits!

        Kurt