Discount Rate?

Could someone with more experience with mining valuation provide some insight for me in terms of the 6% discount rate. From my own experience (not mining related) if I recall correctly, standard discount rates (at least those used by governments) tend to be 7% or more. In the case of the Eagle's Nest, this would unfortunately bring down the NPV... Considering that the 43-101 update used this rate, is this the standard rate accepted for 43-101 reporting? TIA.

pymmer

Join the conversation about Noront Resources.

Reply

Replies

  1. As opposed to other types of project valuation, you shouldn't discount the value of the resource at all (except for a small inconvienience charge since it is not in a form that can be sold easily). Note that: The market price of the mineral is already a risk adjusted present value!

    1. Now, as the resource that we have isn't "proven" (it is a lesser quality) discounting for some risk is probably appropriate. However, I think the discount rate should trend to the risk-free rate as the resource estimate quality is improved.

      I have no mining valuation experience, but I read something along these lines in a financial text book that was outlining valuation of a goldmine.

      1. They finished all the infill drilling at Eagles Nest. They said that the grades will now be higher than the 43-101 states and they moved most of the infered to Indicated. So the existing 43-101 is light anyways. Maybe that is why they used a lower number because they no they can.. TTY

        Sorry if I am not understanding the discount rate correctly.

    2. Sorry goFWR, perhaps I don't understand your point. But my understanding is that the PEA is determining if there is a realistic potential for a profitable mine. From the NR, one of the objectives of the PA was to: "demonstrate the economic potential of Eagle's Nest as a stand alone project." Therefore this PA has to consider whether the costs would be greater than the anticipated revenues. The infrastructure and other costs in order to access those minerals would be occur well before any revenue could be realised from mining those minerals over the trailing 11 years. Therefore the discount rate is a very important factor. It is interesting to see various discount rates applied by different companies such as the example provided by bayboy. (Thanks bayboy for that example)

      pymmer

      1. There is a certain subtlty that is hard to explain! ... I will try to be more clear here with an example (it is based on financial arbitrage):

        If the market price of gold is $1000/oz today, and you think it is going to go to $900/oz tomorrow.. how much would you pay for it today?

        The correct answer is $1000/oz.. which may seem counterintuitive - but if you could get it for any less, you'd just flip it and make an easy buck.

        If you can buy it today but can't sell it until tomorrow how much would you pay? - You would pay $900/(1+riskfree) ... however, the market has already agreed that the price tomorrow is expected (on average) to be $1000*(1+riskgold) - which is a lot higher than your exectation -> otherwise why would people be willing to pay $1000 today? (on average the market pays tomorrows price/(1+riskgold)). When valuing using market pricing - you should use the market's assumption where possible - that means price at time n = 1000*(1+riskgold)^n. Note that the present value after discountng for time and risk is 1000.. (time n price) / ((1+riskgold)^n)

        Now, here is some more practical proof! A market exists to lock in future prices today: the futures market.

        1. Given that you can deliver gold at time 1, or time 2, etc. a company can lock in the price that will be paid for that future gold at time 0.

        2. The price that will be paid in the futures market must be $1000*(1+riskfree)^n - (if prices were lower, people would just by gold at time0, sell a futures contract for time 1, deliver the gold at time 1 and get more than the risk-free rate of interest out of the whole transaction)

        3. discounting that to the present time results in a present value of $1000/oz, -as there is no risk (apart from counterparty) in the transaction you should discount the guranteed cashflows at the risk-free rate

        One more riddle: how else can you value a mine with a certain reserve than: the PV of the mineral (must be the reserve * the market price) less the PV of costs (use the risk-free rate for conservatism)

        Anyway, comments welcome.

  2. Quest Rare Minerals put out a PEA this morning for Strange Lake . They used a conservative 12% discount rate.

    BB