Cost?

Just wondering if any of the key players have ever estimated costs of setting up the ROF with the required transport / infrastructure? Have Cliffs / NOT / Government conducted assessments?

Join the conversation about Noront Resources.

Reply

Replies

  1. To partially answer your question see below. If you sift through the NR’s of NOT, KWG, & Canada Chrome you will find other information and discussion about this. Happy hunting!

    This is from the M D & A dated December 16, 2011.

    Infrastructure

    The Company continues to meet with government and other industry representatives to discuss options and financial support for infrastructure development in the Ring of Fire. During and subsequent to the six months ended October 31, 2011, the Company has held various meetings with the relevant ministries of the current provincial government as well as with members of the opposition parties. The Company is currently developing a business plan for a stand‐alone infrastructure access corridor into the vicinity of the James Bay Lowlands.

    Items below are from the:

    NI 43-101 TECHNICAL REPORT PRE-FEASIBILITY STUDY McFAULDS LAKE PROPERTY EAGLE’S NEST PROJECT JAMES BAY LOWLANDS ONTARIO, CANADA Effective Date: August 23, 2011 Signing Date: October 6, 2011

    The total estimated pre-production cost of capital is $734 million comprising $170 million for mining and $566 million for the process and infrastructure. This estimate assumes that the costs for certain off-site infrastructure will be shared with other users, with the Project bearing 25% of the cost of an all-weather road, 50% of the cost of a power line, and 50% of the cost of a winter road, required during construction. Assuming the project bears 100% of these cost items the total cost of pre-production capital is estimated to be $838 million.

    18.0 PROJECT INFRASTRUCTURE

    SLI’s capital cost estimate of July, 2011 is based on the following infrastructure elements:

    Mine site facilities including:

    General site development.

    Plant site utilities.

    Permanent camp.

    Off-site facilities at Webequie Junction.

    General site development.

    Power generation.

    90-km concentrate pipeline and associated facilities.

    Concentrate thickening and filtration.

    Access roads.

    Concentrate road-rail transfer facility at Savant Lake

    1. From Cupcake's post:
      Noront infrastructure $566 million
      Noront mining $170 million
      --------------------------------------
      Noront site total $734 million

      Noront's share 4 off-site $104 million*
      ==============================================
      Total to Noront $838 million

      *(25% of the cost of an all-weather road, = $26 million
      50% of the cost of a power line = $52 million
      and 50% of the cost of a winter road = $51 million)

      From Fed news release:
      New INVESTMENTS of approximately $250 million, over the next five years.
      Add $70 million for ? to above. (Probably management and procurement costs.)
      A total of $320 million in funding for assets.

      So distributing the 250 million over the following:

      1.Rehabilitation of the Macdonald-Cartier Bridge. 30 million
      2.Repairs to the Alexandra Bridge and Chaudiere Crossing. 35 million
      3.Replacement of the controls and drives of the Burlington Lift Bridge in Hamilton. 35 million
      4.Reconstruction of the Ontario Latchford Dam. 50 million
      5.Reconstruction of the Des Allumettes Bridge located near Pembroke 50 million
      6.Number of projects along the Alaska Highway in Northern B.C. 50 million
      ( Are they too high?)

      The so called bridge in Pembroke is actually two bridges over the Ottawa River from Pembroke into Quebec province. First onto an island in the river and the second from island into Quebec. Depending on what "reconstruction" means it might be over 50 million. I am just guessing because have no practical experience of these matters and hope that someone reading these posts could shed some light on the guesses of costs.
      ('Rehabilitation' is a word that I have never heard used with construction projects.)

      From above, I still think that is all folks because the total $ package is too small to include even a 10% cost of Ring's needs AND there surely must be some other, just as deserving, projects in Canada with little chance for us. Roads are a provincial matter and I think they will have to fund most of those costs. Exception being branch roads to individual company locations in the Ring. The individual companies will have to fund their own access.
      So this is just bread crumbs to the needy and I do not see a loaf later on.

      1. Edgy, Thanks for your listing of the major projects that were announced for federal infrastructure funding. I am sure that these projects were necessary maintenance and upgrades. One will note that all except one are within 100kms of our southern border. The powers to be are well aware of where their votes come from. Governments ,as well, are always playing catch up due to the lack of long term planning. These announced projects supply good paying jobs likely for the next 2 to 3 years and will thus more likely to be remembered at the next election day. I think in the case of the "Ring of Fire" area that they are realizing the long term benefits for tax revenues as well as job creation for many first nations peoples. As far as capital for many projects, including opening up the north, you will find that most infrastructure projects are multilevel in nature. Partnering to maximize capital imputs is the way things seem to operate. I think what will transpire is that transportation infrastructure will become a combined effort of Federal, Provincial, and municipal governments as well as infusion from industry ( Cliffs, Baosteel, NOT et al). They, I believe, are still in the discussion phase of who will imput what and how much. The whole plan has not yet been fully thought through. As we all are well aware, the wheels of government turn very slowly. (About as fast as molasses at the NOT camp in January). I forsee more project announcements when we see what the spring budgets have in store. I can't believe there will not some funding initiatives once everyone is on board. the deputy

      2. edgy read the announcement again.....

        http://www.conservative.ca/press/news_releases/infrastructure_investment_to_help_create_jobs_and_growth

        Tuesday’s announcements build on historic investments our Government has already made to public infrastructure across the country

        as it says, tuesday announcents "BUILD" on historic investments our gov. "HAS ALREADY MADE"

        ring of fire is new, this announcemtn, has nothing to do with ROF, has to do with projects that are already underway

        hope it clears things up for you

        now lets hope harper gets off his butt, and makes a ROF infrastructure announcement sometime soon

    1. yes 320 million spread out over 5 years is chicken feed .we are looking for about 2 to 3 billion for road and rail ,but we will settle for a road from this budget ,even if they have to use some ferries at the big river crossings to get started..

      BJ

  2. As Cupcake has pointed out, there are all manner of reports and estimates which both gov'ts know about. They are just doing what politicians do........................................................................................................................

    ...........................................................................................................................

    ...........................................................................................................................

    talk and posture....talk and posture....talk and........avoid making decisions until...........