  1. The report is 197 pages long.

    Micon based their assumptions on the May 9, 2012 announcement by the Ontario government to support a north-south all-season road infrastructure to the RoF area. Noront is keeping the east-west road in its back pocket as an alternative.

    Nickel-copper concentrate will be sent by truck from the site to Nakina, where it will be loaded onto rail and shipped to a smelter in North America.

    Budget for the next 12 months is some $18.3M including mine design ($6M), Mill Process Design ($1.3M), Infrastructure ($7.8M), Project Management ($1M), and Contingency ($1.9M), all of which Micon believes is reasonable and thus recommends that Noront move forward.

    Pre-production capital expenditures estimated at $609M, with undiscounted payback is estimated to be in 2 years.