Drosrite Analysis - ERROR

Mr. Pascali,

An error in the analysis has been pointed out to me (this is what happens when an unqualified person does these things). Opex was subtracted twice in one calculation and it should read as follows;


$4.9 million CAD - 660k CAD = $4.2 million CAD


$3.7 million CAD - $660K CAD = $3 million CAD

 

$4.53 million CAD - $660K CAD = $3.87 million CAD

 

 

Thank you in advance for your time.


Regards,