Drosrite Analysis - ERROR
Mr. Pascali,
An error in the analysis has been pointed out to me (this is what happens when an unqualified person does these things). Opex was subtracted twice in one calculation and it should read as follows;
$4.9 million CAD - 660k CAD = $4.2 million CAD
$3.7 million CAD - $660K CAD = $3 million CAD
$4.53 million CAD - $660K CAD = $3.87 million CAD
Thank you in advance for your time.
Regards,
Brent
Sign in to ask the company to answer this.
Join the conversation about PyroGenesis Inc.
Reply