Dear Cusam,
Thanks for posting.
To answer your question specifically, the big jump in size
was due to the client reconsidering the scale of their own project and aiming
for a bigger solution that would process more waste.
We had originally announced the potential for the project in
the Q1 MD&A as having a potential contract value of $25-30 million.
In the July 2, 2024 “Response to investor questions” news
release (https://ir.pyrogenesis.com/news-releases/news-release-details/pyrogenesis-provides-responses-investor-questions)
, we stated “Since publication of the Q1 report, this project has evolved and
expanded considerably, and is now being negotiated with a total contract value
of between $115 - $160 million”.
The contract itself was announced on July 29, 2024 (https://ir.pyrogenesis.com/news-releases/news-release-details/pyrogenesis-signs-2-stage-contract-land-based-plasma-waste
) as a 2-stage contract for a land-based waste-to-energy system.
Phase 1 would be a $2 million design phase that would begin
in Q3 2024 and last no longer than Q3 2025, “to confirm, and more precisely
determine, the order of magnitude cost estimate of the system’s construction,
which shall range between $120-160 million (€80-105 million) depending on the
system’s capacity and the selected by-product.”
Phase 2 would be the build of the actual system. “Should
this first stage prove successful, then the parties are committed, subject to
(a) final financing allocation and (b) terms and conditions of the second stage
agreement (which is dependent on the results of the design phase), to move
forward with the project.”
Having said this, we just noted in our financials (Outlook Section)
that “This project is currently on hold as the client lost its first stage
financing. The client is looking for alternate funds. Until such time as those
funds have been secured and the project restarted, $2 million has been removed
from the Company’s reported backlog.”
Hope that Helps
PPP