Question for Peter (Plasma Waste to Energy System)

Hi Peter,


Thanks for answering questions here, appreciate you taking the time.


I was hoping to get some more insight into the Plasma Waste to Energy System project for the European entity. (https://ir.pyrogenesis.com/news-releases/news-release-details/pyrogenesis-signs-2-stage-contract-land-based-plasma-waste)


1. What was the reason behind the big jump in estimated project cost (from $25-30M to $120-160M)?


2. Given your knowledge of the client, will financing be a big hurdle?


3. Phase 1 is supposed to be complete no later than Q3 2025 according to the NR. Is this on track and based on your knowledge of the entity do you expect them to make a decision before end of the year?


cusam

Sign in to ask the company to answer this.

Join the conversation about PyroGenesis Inc.

Reply

Replies

  1. Dear Cusam,

     

    Thanks for posting.


    To answer your question specifically, the big jump in size was due to the client reconsidering the scale of their own project and aiming for a bigger solution that would process more waste.


    We had originally announced the potential for the project in the Q1 MD&A as having a potential contract value of $25-30 million.


    In the July 2, 2024 “Response to investor questions” news release (https://ir.pyrogenesis.com/news-releases/news-release-details/pyrogenesis-provides-responses-investor-questions) , we stated “Since publication of the Q1 report, this project has evolved and expanded considerably, and is now being negotiated with a total contract value of between $115 - $160 million”.


    The contract itself was announced on July 29, 2024 (https://ir.pyrogenesis.com/news-releases/news-release-details/pyrogenesis-signs-2-stage-contract-land-based-plasma-waste ) as a 2-stage contract for a land-based waste-to-energy system.


    Phase 1 would be a $2 million design phase that would begin in Q3 2024 and last no longer than Q3 2025, “to confirm, and more precisely determine, the order of magnitude cost estimate of the system’s construction, which shall range between $120-160 million (€80-105 million) depending on the system’s capacity and the selected by-product.”


    Phase 2 would be the build of the actual system. “Should this first stage prove successful, then the parties are committed, subject to (a) final financing allocation and (b) terms and conditions of the second stage agreement (which is dependent on the results of the design phase), to move forward with the project.”


    Having said this, we just noted in our financials (Outlook Section) that “This project is currently on hold as the client lost its first stage financing. The client is looking for alternate funds. Until such time as those funds have been secured and the project restarted, $2 million has been removed from the Company’s reported backlog.”

     

    Hope that Helps

    PPP