Timeline
|
2010 Q2 Late June |
Strange Lake |
Bench scale metallurgical study by Hazen Research for BZone. |
| 2010 Q3 | Strange Lake |
Starting late June, 13,000 m drilling on BZone to upgrade inferred resource to indicated, and test eastern extension of BZone radiometric anomaly, 2,000 m to test eastern peripheral target, winterized camp allows work until Dec and resume in March 2011. |
| 2010 Q3 Early July | Misery Lake |
Start field work including prospecting and geochem sampling, develop targets for August drilling. |
| 2010 Q3 Late July | Strange Lake |
PEA for BZone. |
| 2010 Q3 Late August | Misery Lake |
Fence of 100 m angled holes totaling 2,500 m on mineralized ring structures after reconnaissance drill released from Strange Lake. |
| 2010 Q3 Late September | Strange Lake |
Delivery to Hazen of 20 tonne bulk sample from BZone for pilot plant scale metallurgical study during 2011 with completion expected late 2011. |
| 2011 Q2 Late June | Strange Lake |
Updated 43-101 resource estimate for BZone incorporating drilling from July-Nov 2010, boost inferred to indicated, include extensions if any. |