Hey Okkeg...

Remember how you talked about the Drill Stem Test...I asked Jason about it, and I just got a response now....I thought I would share it with you all:). He wrote....

The drill stem test is challenging in this situation given that we have high temperatures, pressures and an oil based mud system. We have not planned to DST the well, but rather put it on an extended production test after the ice bridge is constructed in early 2008. The extended test will give us more detailed flow and pressure information.
Jason