Message: Questerre spuds Fortierville No.1 Horizontal well

Hi Life,

Here's a timetable for you and others:

Based on :

- estimated frack-time 2 weeks
- testperiod 4 weeks
- using the same frack-equipement
- Talisman that has said all 3 wells will be completed late Q2/early Q3

week 18 spudding of Fortierville Hz
week 18 end of thaw period
week 20 start fracking of Gentilly
week 22 start testing of Gentilly
week 23 Fortierville TD
week 23 start fracking of LeClercville(not a Qec well)
week 25 start testing of LeClercville
week 26 results from Gentilly
week 26 start fracking of Fortierville
week 28 start testing of Fortierville
week 29 results from LeClercville
week 32 results from Fortierville

BCQEC

This info came from one of Domus's posts everyone. I only coppied the info off of it to keep in my personal files. LIFE had asked about the time line for activity so I forwarded it and Domus was upset. We try and make sure that as much information on QEC gets out to all the members and when people sign their name at the end of a post it's a courtesy