Paradigm Price Target For Romarco

From Paradigm Capital:

March 11, 2013

Investment Thesis. Romarco’s Haile Gold Project currently hosts total resources (M&I plus inferred) of 4.84Moz of gold, and exploration continues to expand the known mineralization. A Feasibility Study completed in February 2011 outlined P&P reserves of 2.0Moz and robust project economics. The deposit still remains open in most directions, and we believe there is considerable regional “district” potential in the company’s land package. The company is targeting receipt of necessary development permits by late-2013, or early-2014.

Event

An article was published in the (South Carolina) Herald newspaper on March 8, which gave a potentially confusing reference to timing of the Draft Environmental Impact Statement (EIS) for the Haile project. We have confirmed there is no change to our estimated timetable.

Details

- An article entitled “More Water Tests Next Week for Lancaster Gold Mine”1 was published in The Herald (South Carolina) newspaper on March 8.

- The subject of the article was the additional hydrology water well testing for the Haile EIS that is under way. We discussed this in our February 21, 2013 research note, The Delays are Getting Smaller.

- The article quotes Dr. Richard Darden, the US Army Corps of Engineers Project
Manager, as saying he “hoped the draft environmental impact statement could be
completed this year”.

- We spoke with Dr. Darden on March 8 and he stated that the Herald journalist had misquoted him. In fact, Dr. Darden had explained the various steps of the EIS process – the Draft EIS, public hearings, the Final EIS, and Record of Decision – and that he stated that it “would be great if we could get all that done by the end of the year”. So while this is certainly not a firm schedule, he did not state that he hoped only the Draft EIS stage could be completed by year-end as was printed in the article.

Conclusion

There is no change to our estimates of the EIS timetable. Our forecasts assume completion (to Record of Decision) by end of Q1/14. We also spoke with Dr. Darden regarding the US Federal Government “Sequestration” Budget, and believe the potential impact to the Haile EIS process will be minor. There is no change to our fundamental views of the Haile project, which we continue to believe will receive the required permits. We maintain our Speculative Buy rating and C$2.00 target.

Join the conversation about Romarco Minerals Inc.

Reply

Replies

    1. We've had a slight rise off the bottom. Of course the usual suspects would not allow gold to have a good close ahead of a long weekend. Hopefully the POG picks up this month and we aee Romarco back through $1 once again. All the best.

        1. Permits will be the key. The POG needs to cooperate as well. I don't believe the CB's will be able to keep the POG down for long. All the best.

          1. Apparently in Thailand, China and a few other places, vendors are out of gold. The public as well as CB's are buying furiously on the dip in price. SMF