    1. The gist I'm hearing is that it is not a 43-101 resource estimate. It's more of a budget for collecting enough data to do one. They need way more holes, and better data from what they already have. Forward-looking budget of $5.8 million to pull it off.

      It'll be on SEDAR by tomorrow. They update overnight, but some data services (e.g. Stockwatch) have it already.

      Lar

      1. Lar:

        Do we have any such document out on SEDAR? Or are we blowing smoke on this one.

        My understanding from Neil was that the 43-101 was to detail - as you put it - "they need way more holes" plus other technical things. The 43-101 is critical for a spring-summer drilling program - assuming the private placement is filled.

        Snug

        1. Okay, I'm baffled that it's not out on SEDAR today. I assumed....you all know what that represents.

          A buddy emailed me a copy. PM me your addy, and I'll send it along.

          Lar

          1. Lar, i see they've not listed reserve estimates, in a nutshell, much more drilling needs to be done, time to fire up the gensets and get drillling. Lots of good information contained throughout the report.

            1. Replying to @notster

              Yes, much more drilling needs to be done. But perhaps not as I much as I had argued was necessary. Despite identifying two intersecting sets of faulting, this report indicated that 200 metre grid lines with 150 metre line spacings would be enough for indicated resource estimation. I'm happy to have been wrong about needing tighter spacing than that.

              "Based on the continuity of the target zone(s) defined by the geophysical surveys, diamond drilling should be conducted initially at 200 m spacing between lines taking 2 holes per line at 150 m apart to define the lateral limit/extent and morphology of the deposit. Simultaneously this drilling will provide representative sample coverage of the deposit.

              The 200 m spacing along strike is based on the authors’ experience of lateral continuity of massive chrome layers while working on similar deposit types where such spacing would, in the absence of structural disruptions, yield an Indicated resource following a variographic analysis."

              I found this quotation to be saddening, but it's consistent with what I already said about Eagle 1 being substantially reduced by erosion:

              "The current geometry as revealed by drill holes is such that the Big Daddy deposit is in the eastern flank of an originally funnel shaped intrusion which has been dislocated/transposed through 90 degrees in a clockwise direction. The western flank of the intrusion has either been displaced/transposed elsewhere or eroded. There is need for a detailed structural interpretation of the greater region to locate or help explain the disappearance of the western flank."

              They're saying they don't expect the chomite to go deeper than 500-700 metres, at least on the grid intersections drilled so far.

              Lar

              1. Replying to @hoov

                Lar:

                You write:

                "They're saying they don't expect the chomite to go deeper than 500-700 metres, at least on the grid intersections drilled so far."

                Damn. I hate when that happens. Instead of 200 billion tons, we only got 100 billion tons.

                Just kidding!!! Tongue in cheek. Please don't broadcast my poor humor as relevant facts!

                Snug

                1. Replying to @snugthejoiner

                  Don't forget that there's that band of possible chromite on McFauld's East, and the core being reconsidered for possible chromite over at McFauld's West. Way too soon to limit thinking to 100 million tonnes. Early returns on PGE also had nice rhodium and iridium values, along side the platinum and palladium. And the geology remains prospective for Ni/Cu, despite none being found so far.

                  I know you're being cheeky, but the report limited some expectations, while opening up other possibilities.

                  Lar

              2. Replying to @hoov

                "The western flank of the intrusion has either been displaced/transposed elsewhere or eroded"

                And if merely displaced or transported (any amount of distance relative to the Main Zone of Mineralization) it remains in tact and available to discovery at some point in time. As for now it appears they have sufficient Strike length to work with toward the East/North East, and generating the IN43-101 on that should prove the Value of the Big Daddy Deposit (or SPQ's portion there of) to any Prospective Deposit Buyer, be it in partnership with FWR's Balck Thor/Lable Deposits (or FWR's portion there of) or independantly of any other Area Explorer.

                As for the prospect that the Western Flank has been eroded, that would be a Shame Tonnage Wise, BUT GREAT in that the Big Daddy Deposit would very likely be exposed at surface directly under the Overburden. AND that means an Open Pit Mine Operation. AND that is by far the most valuable mode of extracting the FULL Mineral Potential contained in the Big Daddy Deposit. AND relatively very cheaply extracted with much reduced Up Front Mine Development Costs, as well.

                Consequently, Massive quantities of Chromite mined Very Inexpensively and with relativelyLow Cost and Quick Mine Start Up time. All very POSITIVE.

                So, Why has NN been quoted recently as appearing to down play his Companies REAL Potential? What REALLY Gives there?

                Old Joe

        2. The technical report is available at SEDAR under KWG. I don't know why it's not up for Spider.

          Lar

    2. Re: FWR, KWG, SPQ 43-101


      Table 20.1 SKF JV Budget Proposals for the Global Definition of Resources of the Big Daddy Deposit PHASE I
      Planning
      $5,000
      Line cutting
      37.5 km (incl. skidoo rental, gasoline, etc
      32,100
      Geophysics
      gradiometer & gravity + standby, mob / de-mob, etc
      67,500
      Re-log
      geologistsm GeoTic licence, mob / demob, XRF & mag susc rental
      128100
      Assays
      includes saw blades, sample shipment, etc
      25,900
      43-101 Report
      includes site visit, assays, etc
      68,300
      Metallurgy
      86,900
      Geo Consultant
      13,200
      Helicopter
      incl fuel
      89,900
      Fixed wing
      49,500
      Drafting
      5,000
      Meals / Camp Costs
      103,500
      Sub total
      674,900
      Contingency (9.6%)
      65,100
      TOTAL
      740,000
      PHASE II
      Planning
      18,300
      Drilling
      16,000m + fuel
      2,222,600
      Geology
      geos, geotecks, GeoTic lic., core racks, XRF & mag susc rental, down hole survey
      673,800
      Assays
      incl assoc. costs
      135,300
      Resources est / 43-101
      82,500
      Env studies
      66,000
      Helicopter
      incl fuel
      906,400
      Fixed Wing
      99,000
      Meals / Camp costs
      426,400
      Sub total
      4,630,000
      Contingency (8.0%)
      370,000
      TOTAL
      5,000,000