The Sangaw North #1 exploration well is currently drilling ahead at 1,505 metres.
Since the last update on 7 May 2010 two intermediate casing strings have been run; 13 5/8” casing was run and cemented with the casing shoe at 1,053 metres TVD (true vertical depth) and 9 7/8” casing was run and cemented with the casing shoe at 1,448 metres TVD.
The well bore is currently being drilled through the Shiranish horizon, the uppermost of the prospective Cretaceous aged formations in the Sangaw North prospect. While drilling this section gas shows and drill cuttings with fluorescence have been observed, both are indications of hydrocarbons being present in the well bore.
The well plan is to drill through the Shiranish and then continue drilling to evaluate the prospectivity of the Kometan and Qamchuqa horizons in the Cretaceous and the deeper potential reservoirs in the Jurassic.

Alastair Beardsall, Sterling’s Chairman said
“The gas shows while drilling are encouraging; we will continue our drilling and evaluation programme to determine the prospectivity of Sangaw North

Join the conversation about Sterling Energy.

Reply

Replies

  1. Kurdistan - Sangaw North PSC

    Sterling Energy Plc ("Sterling" or "Company"), the AIM listed independent oil & gas, exploration & production, company with interests in the Middle East and Africa, provides the following update on its activities:

    Sangaw North Exploration Well

    Further to the announcement dated 6 August 2010, the repairs to the Sakson drilling rig have now been completed and the rig has resumed operations. Sterling's plan is to continue testing the prospectivity of the Sangaw North #1 exploration well previously identified from the wire-line log data and drilling shows over the open-hole interval of 1,450m to 2,395m.

    It is estimated that the testing will take approximately 10 days to complete, after which the plan is to drill ahead through the remaining Cretaceous section and then to the deeper potential reservoirs in the Jurassic. Due to the delays incurred whilst the rig was undergoing repairs, the well is now expected to reach its planned depth of 3,660m during the 4th quarter of 2010.