Here follows David Webb's response to my status request msg.

First, as we’ve published in our news releases, the PFS and DAR are on schedule, both expec ted before the end of June 2010, or within the next 120 to 130 days. Below is a brief summary of tasks which we have been following as provided by our contributing engineers:

**** Prefeasibility Project plan provided was too long to be published here - deleted

The process was to take 12 months, and we are 7 months into it. We sta ted it would be comple ted in Q2 2010, H1 2010, or before the end of June 2010. In each case we’re referring to the same timeframe that we sta ted from day 1, and we are on schedule. No delays.

The DAR is equally complex and has its own set of studies:

**** DAR project plan provided was too long to be published here - deleted

In addition, a number of alternative studies have been conduc ted , each with an exhaustive list of criteria.

In order to start plant fabrication for the next winter trucking season, we would, from June 2010, have roughly 6 months to obtain permits, raise funds (say $150 million) by way of a debt and equity structure, source and purchase all long lead time equipment and have it delivered to Yellowknife . In short, a very very demanding schedule which although technically it might be possible, it is most unlikely.

We believe we’ll continue to move the project forward according to the schedules we announce. We feel that submission of our DAR will lead to discussion among us, the regulators and local communities about longer term plans (roads, hydroelectric plants etc). Ultimately this infrastructure would assist Tyhee by reducing operating and capital costs. Public discussions take time. We also feel that the PFS will identify issues that will need to be addressed. This could be mine sequencing, tailings containment structure (single or multicell), exploration sequencing (should we focus on expansion of reserves/resources at Clan, Goodwin, Ormsby, Bruce, Nicholas?).

To speculate. We’ll continue to meet our goals and targets as announced this year and be guided by the recommendations in the PFS. Our exploration program will continue to build resources, primarily at Clan Lake . It is most likely that the DAR which will be submit ted on time, will lead to discussions and planning adjustments with community input through the fall 2010. We’ll be able to work on some engineering modifications and may be able to start some construction work (site development, roadways, laydown are development), but not any significant fabrication using the 2011 road for access. We’ll be able to plan our financial structure, order our long lead time items, and could plan on using the 2012 winter road for (or perhaps an all-weather road???) for 2012 construction and early 2013 gold production.

Dave

Join the conversation about Tyhee Gold Corp.

Reply

Replies

  1. Thanks Pepi,

    If Tyhee can go into production by early 2013 as Webb suggests, then that would put it not too far from Romarco's anticipated start-up date of somewhere in mid to late 2012, according to its IR person.

    I think that one very important aspect of Romarco's great success is that its investors are hopeful they'll see "payback", in the form of gold production, relatively soon. From Romarco's bankable Feasibility Study in February 2009 to its anticipated first pour, that would be about three years. This is approximately the same time-frame we may anticipate Tyhee to have when it goes from one of these two critical milestones to the other.

    As was the case with Romarco, I think there'll be no shortage of investors who'll take similar notice of Tyhee's "quick" payback time as it reaches and continues to overtake those same milestones that are bringing it closer to production. And, as was the case with Romarco, I expect this to happen with little or no glitzy PR. Just Dave Webb calmly* and confidently looking you in the eye and telling what's going on.

    Baires

    *with the possible exception of when certain assay results come in from Clan Lake.

  2. Pepi,

    In youre summary of DW's reply, there were two items that would not fit due to space. Would you please email them to Baires, so that he can add them to this fourm links?

    **** Prefeasibility Project plan provided was too long to be published here - deleted

    **** DAR project plan provided was too long to be published here - deleted

    Good job, by the way.


    DW seems to underpromise and overdeliver, and has been very consistent....

    SKELEG

    1. In a World Where Anything Can Happen, Dave Webb Should Know By Now.

      From the painful delays Tyhee experienced delivering its robust 2007 Preliminary Assessment Report, to the long unanticipated wait for closing its last summer’s (“Spring”) Private Placement, to the underwhelming results from its Nicholas Lake’s re-sampled cores and Big Sky’s disappointing non-bonanza assays, Dave Webb should by now be one of the most conservative and thoughtful CEO’s alive.

      So, for those who have accused this Forum for being intolerant to any critical views of Tyhee , please take note:

      I am not discounting what this junior’s been through or pretending that its struggles and disappointments didn’t happen and will never again reemerge is some other irksome form. No, we live in world where anything can happen. And, Webb knows that more now than ever before.

      As such, when I see Dave's PFS and DAR schedules, my confidence in Tyhee's success has never been greater.

      Baires

      1. Thanks Pepi, I will post these lists on the "PROFILE" section of the Hub.

        Below is a brief summary of tasks which, according to Dr. Webb, Tyhee's been following as provided by its contributing engineers:

        Task 1: Prefeasibility Criteria
        Establishment of Standards & Reporting Schedule
        - Terms of Reference
        Review of Similar Project Pre-Feasibilty Studies
        Task 2: General Site Information
        Update Site Map for Ormsby
        Detailed Topography and Update Site Map for Nicholas Lake
        Task 3: Geology & Resources
        Desktop Study
        Independent Review: QA/QC of All Resources
        Sampling/Assaying Flow Diagram
        Assay Check Graph
        Block Model Update Using Gemcom
        Site Visits
        Reporting
        Addition of ARD Data to Gemcom
        Geologic Cross-Sections
        Drill Hole Location Map
        Statistics
        Mineral Resource/Reserve Estimate (Mintec)
        Task 4: Groundwater Data
        Project Management and Planning
        Project Management
        Background/GAP Analysis and Program Planning
        Field Program
        Monitoring Wells/Installation Ormsby
        Monitoring Wells/Installation Nicholas Lake
        Packer Tests (in Coordination with Geotech Drill Holes) Ormsby
        Packer Tests (in Coordination with Geotech Drill Holes) Nicholas Lake
        Monitoring Wells-Static and Slug Tests Ormsby
        Monitoring Wells-Static and Slug Tests Nicholas Lake
        Reporting
        Lab Analysis (Water Quality)
        Reporting
        Task 5: Hydrology/Water Balance
        Project Management
        Update Climate Data Input to Water Balance
        Update Hydrology Data Input to Water Balance
        Gathering Hydrogeological and Mining Components
        Compiling Water Balance
        Report
        Site Visit - Installation of Lake Level Monitoring Stations
        Task 6: Mining
        Ormsby
        Method and Plans (Open Pit and Underground)
        - Pit Optimization (Mintec)
        - Final Pit Outline (Mintec)
        - Annual Pit Outline (Mintec)
        - Ramp Design (Mintec)
        - Underground Mine Development (Mintec)
        - Underground Stoping System (Mintec)
        - Equipment Selection (Mintec)
        Waste Dump Design
        - Deliniation of NAG and PAG Volumetrics
        - Final Dump Outline
        - Annual Dump Outline
        Design of PAG Waste Dump Runoff Pond (Other)
        - Geochemistry (Other)
        - Runoff Treatment (Other)
        Production Scheduling
        - Alternatives
        - High Grade Scenario (Mintec)
        Capital & Operating Cost Estimates
        Trade-off Analysis: Open Pit vs Underground
        Nicholas Lake
        Method and Plans (Open Pit and Underground)
        - Pit Optimisation (Mintec)
        - Final Pit Outline (Mintec)
        - Annual Pit Outline (Mintec)
        - Ramp Design (Mintec)
        - Underground Mine Development (Mintec)
        - Underground Stoping System (Mintec)
        - Equipment Selection (Mintec)
        Waste Dump Design
        - Deliniation of NAG and PAG Volumetrics
        - Final Dump Outline
        - Annual Dump Outline
        Design of PAG Waste Dump Runoff Pond (Other)
        - Geochemistry (Other)
        - Runoff Treatment (Other)
        Production Scheduling
        - Alternatives
        - High Grade Scenario (Mintec)
        Capital & Operating Cost Estimates
        Trade-off Analysis: Open Pit vs Underground
        Task 7: Geotechnical Characterization
        Ormsby Gap Analysis and Geotechnical Drill Program Planning
        Nicholas Lake Gap Analysis and Geotechnical Drill Program Planning
        Ormsby Field Program (Drilling and Logging)
        Nicholas Lake Field Program (Drilling and Logging)
        Underground Stope Review/Write Up
        Analysis and Reporting Ormsby
        Analysis and Reporting Nicholas Lake
        Task 8: Ore Transportation Systems
        Trade-off Analysis: All Season Road vs Ice Road
        Schedule Impacts (Winter vs. All Season)
        Design of Nicholas Lake Haul Road to Ormsby
        Capital & Operating Cost Estimates
        Task 9: Ore Processing
        Land Selection for Process Plant
        Method & Plans
        Capital & Operating Cost Estimates
        Trade-off Analysis: Costing for Extraction of Silver and Tungsten
        Task 10: Metallurgy Work
        Gap Study Ormsby
        Gap Study Nicholas Lake
        Sampling and Analysis Ormsby/Nicholas Lake
        Tailings Characterization
        Reporting
        Task 11: Tailings
        Terrain Analysis of Alternate Tailings Storage Areas
        Trade-off Analysis: Tailings Disposal Options
        Tailings and Waste Rock Management Plans
        - Dam Construction Conceptual Design
        - Water Mangement (Overflow, etc…)
        - Geotechnical Instrumentation Requirements
        - Polishing Area
        - Sediment Control Structure
        - Detoxification (Other)
        Scoping for Additional Geotechnical Works
        Capital & Operating Cost Estimates (Meritt)
        Task 12: Infrastructure & Administration Facilities
        Review of Existing Information
        Terrain Analysis of Proposed Structure Locations and Access Road Routing
        Geotechnical Investigation by Coring with Diamond Drill Rig
        - Mill (Met/Assay Lab)
        - Site Roads
        Reporting
        Water Supply and Treatment (Other)
        Sewage Management and Treatment (Other)
        Capital & Operating Cost Estimates (Meritt)
        Task 13: Powerline & Substation
        Capital & Operating Cost Estimates
        Trade-off Analysis: Powerline vs Generator
        Task 14: Environmental & Permitting
        Baseline Environmental Status Review
        Permit List
        Environmental Studies & Permitting
        Task 15: Socio-Economic
        Socio-Economic Impacts Report
        Task 16: Reclamation
        Preliminary Closure Plan
        Task 17: Development Schedule
        Schedule Chart
        Task 18: Economics
        Principal Economic Parameters (Industry Norms)
        Royalties & Taxes
        Cash Flows
        Sensitivities & Risk Analysis
        Gold Market Analysis
        Task 19: Compilation of Prefeasibility Report
        Project Management/Meetings
        Report Compilation & Appendices/Assembly
        Owners Review of Methods, Plans, Costs

        The process was to take 12 months, and Tyhee is 7 months into it. Tyhee stated it would be completed in Q2 2010, H1 2010, or before the end of June 2010. In each case Tyhee's referring to the same timeframe that it stated from day 1, and it is on schedule. No delays.

        The DAR is equally complex and has its own set of studies:

        1.0 INTRODUCTION
        1.1 Corporate Overview
        1.2 Corporate Governance
        1.3 Environmental Policy
        1.4 Properties
        1.4.1 Yellowknife Gold Project (YGP)
        1.4.2 Gold Resource
        1.5 Mineral Claims and Leases
        1.6 Required Permits, Licences and Authorizations
        2.0 PROJECT DESCRIPTION
        2.1 Rationale for Project
        2.2 Project, Resources and Access
        2.3 Project History
        2.3.1 Discovery Mine
        2.3.2 Previous Exploration – Discovery and Ormsby Zones
        2.3.3 Previous Exploration – Nicholas Lake Main Zone
        2.3.4 Tyhee NWT Corp Exploration – Ormsby, Bruce Lake and Nicholas Lake
        Main Zones
        2.4 Project Alternatives
        2.5 Geology
        2.5.1 Property Geology
        2.5.1.1 Ormsby
        2.5.1.2 Nicholas Lake
        2.5.2 Mineralization
        2.5.3 Resource and Reserve Estimate
        2.5.4 Exploration Potential
        2.5.5 Seismicity
        2.6 Site Preparation and Construction
        2.7 Construction Materials
        2.8 Mine Plan and Operation
        2.9 Mine Production Schedule
        2.10 Mine Life
        2.11 Processing
        2.11.1 Ore Processing
        2.11.2 Process Plant
        2.11.3 Crushing
        2.11.4 Grinding
        2.11.5 Flotation
        2.11.6 Regrinding and Thickening
        2.11.7 Leaching
        2.11.8 Carbon Elution and Regeneration
        2.11.9 Reagents
        2.12 Waste Management
        2.12.1 Acid Rock Drainage (ARD) and Waste Rock Storage Area (WRSA)
        2.12.2 Acid Generation Potential (ARD) for Nicholas Lake Deposit
        2.12.3 Waste Rock Storage Areas
        2.12.4 Tailings Containment Area (TCA)
        2.12.5 Preferred Option for Tailings Containment - Winter Lake
        2.12.5.1 Tailings Containment Area - Operation
        2.12.6 Solid and Hazardous Waste
        2.12.7 Sewage
        2.13 Water Management
        2.13.1 Objectives
        2.13.2 Climate Analysis
        2.13.3 Water Balance
        2.13.4 Water Balance for Nicholas Lake Deposit
        2.14 Support Infrastructure
        2.14.1 Power Plant
        2.14.2 Airstrip
        2.14.3 Changehouse, Compressor House, Offices, Warehouse and Maintenance
        Shops
        2.14.4 Fuel Storage
        2.14.5 Explosives Storage
        2.14.6 Roads
        2.14.7 Camp
        2.14.8 Winter Road
        2.15 Human Resources
        2.15.1 Workforce
        2.15.2 General and Administrative
        2.15.3 Mining
        2.15.4 Process Plant
        2.15.5 Training Program
        2.15.6 Emergency Services
        2.16 Project Schedule
        3.0 DESCRIPTION OF THE ENVIRONMENT
        3.1 Introduction
        3.2 Present Land Uses
        3.3 Environmental Setting
        3.4 Climate
        3.4.1 Climate Monitoring
        3.4.1.1 Wind Speed and Direction
        3.4.1.2 Air Temperature
        3.4.1.3 Incident Solar Radiation
        3.4.1.4 Relative Humidity
        3.4.1.5 Barometric Pressure
        3.4.1.6 Precipitation
        3.4.1.7 Snow Surveys
        3.4.1.8 Evaporation
        3.4.2 Climate Trends
        3.5 Air Quality
        3.5.1 Sources of Emission
        3.5.2 Air Quality Standards
        3.5.3 Ambient Monitoring Data
        3.5.3.1 Total Suspended Particulate (TSP) Concentrations
        3.5.3.2 PM2.5 Concentrations
        3.5.3.3 SO2 Concentrations
        3.5.3.4 NO2 Concentrations
        3.5.3.5 O3 Concentrations
        3.5.4 Site Collection of Ambient Air Quality Data
        3.6 Noise
        3.7 Soils and Vegetation
        3.7.1 Soils
        3.7.2 Vegetation
        3.7.3 Ecosystem Types
        3.7.3.1 Forest and Woodland
        3.7.3.2 Riparian
        3.7.3.3 Wetland
        3.7.3.4 Sparsely Vegeta ted
        3.7.3.5 Water
        3.7.3.6 Other Units
        3.7.4 Broad Ecosystem Units
        3.7.5 Rare Plants and Communities
        3.8 Biodiversity
        3.8.1 Northern Boreal Characteristics
        3.8.2 Species Diversity
        3.8.3 Structural and Functional Diversity
        3.8.4 Landscape-level Diversity
        3.9 Hydrology
        3.9.1 Hydrological Monitoring
        3.9.1.1 Narrow Lake Drainage Basin
        3.9.1.2 Brien Lake Drainage Basin
        3.9.1.3 Winter Lake Drainage Basin
        3.9.1.4 Round Lake Drainage Basin
        3.9.1.5 Northeast Brien Lake Site
        3.9.1.6 Nicholas Lake Drainage Basin
        3.10 Groundwater
        3.10.1 Evaluation of Available Groundwater Information
        3.10.1.1 General
        3.10.1.2 Permafrost influence on groundwater flow patterns
        3.10.1.3 Groundwater Quality
        3.10.1.4 Topography and Surface Watersheds
        3.10.1.5 Stream flow data
        3.10.1.6 Surface Geologic Outcrop and Structure
        3.10.1.7 Packer Test Data
        3.11 Surface Water Quality
        3.11.1 Water Quality Parameters
        3.11.2 Quality Assurance/Quality Control
        3.11.2.1 Travel Blanks
        3.11.2.2 Field Blanks
        3.11.2.3 Duplicates
        3.11.3 Metals
        3.11.3.1 Aluminium
        3.11.3.2 Arsenic
        3.11.3.3 Cadmium
        3.11.3.4 Copper
        3.11.3.5 Iron
        3.11.3.6 Mercury
        3.11.3.7 Nickel
        3.11.3.8 Other Metals
        3.11.4 Nutrients
        3.11.4.1 Ammonia
        3.11.4.2 Nitrate
        3.11.4.3 Total Phosphorous
        3.11.5 Temperature and Dissolved Oxygen
        3.11.5.1 Narrow Lake
        3.11.5.2 Winter Lake
        3.11.6 Water Quality Summary
        3.12 Aquatic Resources
        3.12.1 Background Investigations
        3.12.2 Aquatic Resource Investigations – 2004
        3.12.3 Lake Shoreline Habitat
        3.12.3.1 Round Lake
        3.12.3.2 Winter Lake
        3.12.3.3 Eclipse Lake
        3.12.3.4 Nicholas Lake
        3.12.3.5 Brien Lake
        3.12.3.6 Narrow Lake
        3.12.4 Stream Habitat
        3.12.4.1 Round Lake
        3.12.4.2 Winter Lake
        3.12.4.3 Eclipse Lake
        3.12.4.4 Nicholas Lake
        3.12.4.5 Brien Lake
        3.12.4.6 Narrow Lake
        3.12.5 Fish Population Relative Abundance, Distribution and Species
        Composition
        3.12.5.1 Round Lake
        3.12.5.2 Winter Lake
        3.12.5.3 Eclipse Lake
        3.12.5.4 Nicholas Lake
        3.12.5.5 Brien Lake
        3.12.5.6 Narrow Lake
        3.12.6 Fish Biological Characteristics
        3.12.6.1 Northern Pike
        3.12.6.2 Lake Trout
        3.12.6.3 Lake Whitefish
        3.12.7 Fish Tissue – Metals Analysis
        3.12.8 Zooplankton
        3.12.8.1 Round Lake
        3.12.8.2 Winter Lake
        3.12.8.3 Eclipse Lake
        3.12.8.4 Nicholas Lake
        3.12.8.5 Brien Lake
        3.12.8.6 Narrow Lake
        3.12.9 Benthic Invertebrates
        3.12.9.1 Lakes
        3.12.10 Streams
        3.12.11 Lake Sediment Quality
        3.12.11.1 Round Lake
        3.12.11.2 Winter Lake
        3.12.11.3 Eclipse Lake
        3.12.11.4 Nicholas Lake
        3.12.11.5 Brien Lake
        3.12.11.6 Narrow Lake
        3.12.12 Aquatic Resource Studies 2005
        3.12.12.1 Fish Species Composition, Relative Abundance, Distribution
        and Age
        3.12.12.2 Winter Lake Habitat
        3.12.12.3 Fish Tissue Metals
        3.12.12.4 Water Quality
        3.12.12.5 Proposed Access Road – Nicholas Lake to Ormsby
        3.13 Wildlife
        3.13.1 Mammals
        3.13.1.1 Caribou
        3.13.1.2 Moose
        3.13.1.3 Black Bears and Grizzly Bears
        3.13.1.4 Wolves
        3.13.1.5 Wolverine
        3.13.1.6 Foxes
        3.13.1.7 Carnivore (Esker Survey)
        3.13.2 Birds
        3.13.2.1 Passerines
        3.13.2.2 Raptors
        3.13.2.3 Peregrine Falcon
        3.13.2.4 Owl Survey
        3.13.2.5 Waterfowl
        3.14 Heritage and Cultural Resources
        3.14.1 2004 Investigations
        3.14.1.1 Existing Conditions
        3.14.1.2 Discovery/Ormsby Area
        3.14.1.3 Nicholas Lake Area
        3.14.1.4 Road between Nicholas Lake and Ormsby Area
        3.14.2 2005 Investigations
        3.14.3 Traditional Land Use Study North Slave Métis Alliance (NSMA)
        3.14.3.1 Métis Traditional Use 1700’s to 1960’s
        3.14.3.2 Current Métis Land Use in the Yellowknife River drainage
        3.14.4 Traditional Land Use Data Yellowknives Dene First Nation (YDFN)
        4.0 PUBLIC CONSULTATION AND COMMUNICATIONS
        4.1 Consultation and Communications Program
        4.1.1 Aboriginal Communities
        4.1.2 Regulatory Agencies
        4.2 Consultation Outcomes
        5.0 ENVIRONMENTAL EFFECTS, MITIGATION AND MONITORING
        5.1 Valued Ecosystem Components
        5.2 Environmental Effects
        5.3 Air Quality
        5.3.1 Description of Impacts
        5.3.2 Air Monitoring Programs
        5.4 Water Quality
        5.4.1 Description of Impacts
        5.4.2 Monitoring Programs
        5.5 Fish and Habitat
        5.5.1 Description of Impacts
        5.5.2 Monitoring Program
        5.6 Wildlife
        5.6.1 Description of Impacts
        5.6.2 Monitoring Program
        5.7 Vegetation
        5.7.1 Description of Impacts
        5.7.2 Monitoring Programs
        5.8 Environmental Management Systems

        In addition, a number of alternative studies have been conducted, each with an exhaustive list of criteria.

        B.