We expect to be drilling for another couple weeks. The drill rigs only work day shift on some holes due to their proximity to town (noise restraint), while others are 24hr/day. Also, the drilling of some holes on the back end of the program are in part contingent on earlier holes and then-remaining budget. In any event, we anticipate completing the coring by the end of Aug with final logging, sampling & shipping completed the subsequent week. Add at least 3 weeks before we see final assay results from the lab and a short week to collate, conduct our QA/QC review & internally report on results (ie with Goldcorp). All summed, and barring any spectacular intersects that would be material to the company and require earlier disclosure, we’ll probably release results the end of Sept or the first part of Oct.
Regards,
Joe