Wildcat Begins Drill Program on Jeep Gold Project

Breaking News

Wildcat Begins Drill Program on Jeep Gold Project, Rice Lake Greenstone Belt, Bissett, MB

09:01 EST Monday, January 18, 2010

WINNIPEG, MANITOBA--(Marketwire - Jan. 18, 2010) - Wildcat Exploration Ltd. (TSX VENTURE:WEL) announces that drilling is scheduled to commence on or around January 22, 2010, on the Company's 100% owned Jeep project, 14 kilometres east of Bissett, MB. The Jeep Property (4,016 ha) hosts the past producing Jeep mine with historical production of approximately 18,000 tons of ore at an average gold grade of 0.78 oz/ton (non 43-101).

Targets of the planned 2,500m drill program include:

1. Downplunge extensions of recent (summer 2009) surface discoveries of gold bearing structures located within a 500 m radius of the Jeep mine shaft.

2. Extensions of gold intersections from Wildcat's past drill programs.

3. Potential downplunge extension of the historical #1 vein below the underground mine workings.

Prior work by the Company has included an airborne electromagnetic and magnetometer survey, a mobile metal ion survey, induced polarization survey and 10,945 m of drilling (45 holes) completed during the 2006-2008 seasons. The drill programs intersected gold and anomalous copper-nickel-platinum group elements concentrations along a 2.2 kilometre trend, striking from the mine shaft area to the SE, along an azimuth of 110 degrees.

John Knowles, Wildcat's CEO, says, "This program has been planned by our geological team under the leadership of Wildcat's newly-appointed V.P. Exploration, Tom Lewis. It marks the first Wildcat program of 2010 and will be funded from our recent, well-received flow through financing."

Join the conversation about Wildcat Exploration Ltd.

Reply

Replies

  1. Now we need another breaking news from the poundmaker JV agreement. (sorry had to throw that in there). Then we have reason to get a little excited especially if these shallow drill holes return poor results.

    r65

          1. Correct me if IM wrong (which is very likely)

            Page 14,15,16,17 of presentatiion show previous cross and long section drill results that have produced not so very great width's. If those were previous mined width's then how was that mine profitable back in the days? The grades are not bad but the width's are low!

            Now looking at the proposed drill holes. I counted 16 proposed holes. divide that by 2500m planned and you have an average of about 156m / 512ft per hole.

            I can tell they have done homework and I guess we have to wait and see if this geo team is a successful one. I cannot remember the last time wildcat ever put together or spent this much time on a drill program. I've only been here 1.5yrs and have not gone into there historical news releases in depth. I try and stay current unlike traps that follows the ancient workings when our ancestor used a pick and hammer. (not a bad thing traps)

            I hope they find something around Jeep. Odds should be stacked in our favor. As the saying goes: "best place to start looking is close to a existing mine"

            Curious to see where the Reed and Foster budget is going to come from.

            1. Replying to @robbertop65

              The average grade was better than the San Antonio. When you look at the average grade reportd by San Gold on the hinge zone so far... they are better on the Jeep.... only difference is SGR has more cash to spend on drilling. If WEL was to drill 120,000 ft I wonder what results WEL would be promoting?

              SGR Nov 13th news release contained:

              Exploration

              The Company drilled 72,740 feet underground during the quarter and 55,364 feet from the surface. This significant surface and underground drilling continues to confirm the geologic model of the Hinge in what is proving to be a predictive model in identifying mineralization in the surrounding area; most notably at the Cohiba and L-13 areas where plans are underway to determine feasibility.

              AND: July 14, 2009

              Dale Ginn, CEO of San Gold Corporation (SGR: TSX-V) is pleased to present the results of the 11,762 ton Hinge

              Zone bulk sampling program that was carried out during the second quarter of 2009. The high grade nature of

              the hinge zones were validated as the stope mining grade reconciled to the mill at 21.7 g/tonne (0.63 oz/ton) with

              the main #1 lens stope contributing 26.3 g/tonne (0.77 oz/ton). Low total operating costs (mine and mill) of Cdn

              $184 ($US 158) per ounce were realized as well as high mill recoveries of 96%. Total expenditures (operating and

              capital) to date in order to build and develop the Hinge Mine are approximately Cdn $6.5 million with nearly 6,000

              ounces recovered to June 30

              th. A table containing the detailed breakdown of stoping, development, mill and cost

              data follows the written portion of this press release.

              Highlights and Observations of the Hinge Zone Bulk Sampling Program include:

              5,938 ounces recovered from 11,762 tons mined and processed.

              Stoping grades of 21.7 g/tonne (0.63 oz/ton) and development grades of 16.9 g/tonne (0.49 oz/ton).

              Main Hinge lens #1 grades 26.3 g/tonne (0.77 oz/ton) in stoping and 21.2 g/tonne (0.62 oz/ton) in development.

              Bulk sample operating costs averaged Cdn $59 per ton for mining and Cdn $19 per ton for milling, for a total direct

              operating cost of Cdn $78 per ton, excluding capital expenditures and exploration drilling.

              Total direct bulk sample operating cost per ounce of gold produced is Cdn $184 per ounce or approximately US

              $158 as at June 30, 2009.

              Total expenditures of Cdn $6.5 million to develop the Hinge Mine.

              Total decline, lateral and raise development of over 8,000 feet completed to June 30

              th

              --------------------------------------------------------------------------------------------

              Compared to the limited exploration to date on the Jeep Property

              Bulk sample results from the Jeep

              - Jeep Mine: past high-grade gold producer

              * "During its two years of operation ending in 1950, it (Jeep Mine) shipped 14,477 tons of ore averaging 0.825 oz per ton to the San Antonio mill…" J. Stephenson, 1972
              * Depth potential untested (Target 1)

              - Magnetic anomaly (prominent “bull’s-eye”) SE of Jeep deposit, not drill tested at depth (~400ft)

              * Coincident chalcopyrite-pyrrhotite mineralization discovered SE of Jeep deposit
              * Possible Ni-Cu target? (Target 2)

              - Anomalous gold 1) along south contact & 2) east end of Jeep gabbro

              - Fault zone with shaft, pits / trenches - north of Jeep mine, not explored or drill tested

              - Underexplored volcanic sequence adjacent Wanipigow fault hosts Presto molybdenum (gold?)and copper showings and a recent discovery of intense iron carbonate alteration & quartz veining (Target 3)

              - PGE: potential of Jeep gabbro has never been evaluated.

              1. Replying to @res-investor

                In short.

                SGR produced 5938 oz from 11762 tones of material.

                The two stope segments averaged 20.6 g/t (0.63 oz/t) over 2,738 tons.

                Four development ore segments averaged 16.0 g/t (0.49 oz/t) over 9,024 tons.

                The entire 11,762 ton bulk sample averaged 18.0 g/t (0.53 oz/t) recovered.

                http://sangoldcorp.com/assets/files/090714_BulkSample.pdf

                And the Jeep produced ( recovered) 11,943 oz from 14,477 tones of bulk sample.

                .825 oz/ tone

                http://www.wildcat.ca/explorationdetailscontent.php?PAGEAREAID=5&AREAID=6