Timeline - Update

Updates in bold. Still on schedule in my eyes. Lots of potential for advancement!

drill permit received: beginning of May, 2011 - complete

drills mobilized: by end of May, 2011 - complete (my inference from reading yesterday's NR is that at least one rig was all set to go by the end of May)

drilling: June-July-August, 2011 - in progress (again, my inference is based on yesterday's NR. I believe at least one drill was turning on or around June 1)

results sent to lab and analyzed: Aug-Sept, 2011

assay results released: Oct, 2011

bids for Tesoro from interested parties: Nov-Dec, 2011

evaulation of bids and negotiations with interested party: Jan, 2012 - Feb, 2012

sale of Tesoro: March, 2012

Join the conversation about St. Elias Mines.

Reply

Replies

  1. You forgot to mention - Party on the SS SLI in April!

    I have been too busy with the events and goings on with TRE so finally caught up on the SLI posts. Many thanks to the regulars and board leaders for continued excellence. I have noticed that strength is starting to return even though the markets are gloomy. Long and strong on SLI and buying more soon. Thanks all and have a great weekend.