I've talked to Jim at length about these difficulties at La Yesca, and frankly, it's a very complicated situation. And it is true, IMHO, that there are current or imminent material facts which limit what Jim can say about e.g. financing and mill start-up. That's just my impression, because Jim stops talking about stuff when materiality becomes a concern. Thus, his answer that information will be provided in a NR is the appropriate answer. I don't know anything you don't, and I won't find out until you do. I like that.
As to the mill modifications, that is itself a very complicated situation. IMHO, the mill should never have been built based on the tailings data and methods developed for the mill process chemistry. The pre-engineering was quite inadequate, IMHO. Jim inherited that problem. The mill, as built, could not be operated economically, even at today's gold and silver prices. He ran the mill briefly last year, and proved that was the case. He then spent a good chunk of change getting the tailings properly sampled, and developing a chemical processing method that could provide an economic yield, with the least modifications to the existing mill equipment. Those modifications are not free, as you can well imagine.
Furthermore, although he could have done a quick PP to fund those modifications, that would have been excessively dilutive because, like many junior explorers, the SP got hammered a year ago. Instead, he's been banging on doors, doing cold calls, trying to get cash financing based on his now proven grades and recovery methods. The delay in doing non-dilutive financing is well worth it, IMHO. So get some patience, people, or get out. You're in the wrong investment if you can't recognize how hard Mr. Voisin has worked on your behalf since becoming the CEO.
Lar