Replied in thread
Re: Where is the feasibility study?
There's a lot more that needs to be done before Teck can sanction the project. The FEED must be done(probably a year), all environmental permits must be in place and contracts signed for power and roads. Then they go through project sanction where the Teck BOD must approve the $…