Sure, but at this point, if they can add another $400M US to the base case and crank the IRR past 15%, why not wait 6 months? All this should have been done last year, but Teck decided that they needed more time... IMO. MoneyK
In my opinion, the SC PEA is very conservative. The grades are proving to be higher than anticipated, the recoveries are to the floor and the mill is only set at 92%, when 95% is at reach for state of the art mines. With some small improvements, SC could spit a lot more CuEq "almost for free". That goes directly to the bottom line. Lets also not forget that the PEA has a 25% contingency ($586M) and allocated $154M for closure after 21 years. Like if SC will close after that period. Contingency would probably reduce at PFS stage. Also, construction timeline could be reduced by maybe 1 year? Opex still improved with a lower strip ratio? Metal prices now much higher? SC might not have a high…