Realistically we won't get any news on financing, (a few pep talks maybe) till next spring (2015). ICL will get us for a song by then, even at 30 or 40 % premiun of SP.
Sorry gals and guys, but something funny is going on behind the scenes here?
I don't agree Marcoll... Allana is progressing as planned... Yes a little slower, but still progressing... Much better than any other potash junior IMO...
Financing q4.... Or later... That means Oct, Nov Dec or later....
I believe the investors meeting will promote the recent a accomplishments with the water recharge rates as well as the large scale cavern tests. That's my opinion...
My two cents, Debt financing will be announced, at least part of it --to get them started ---and a date will be announced for the start of construction. They have run out of down time. the pace of announcements had been slow but steady. Engineers are on site now and will have developed a basic construction plan by now. They must get this project started --- time is money and they know this fact better than we do.
Allana Potash Corp. (TSX:AAA) has solicited the expertise of AMEC Americas Limited to complete Front End Engineering and Design (FEED) on its one million tonne per year MOP Danakhil Potash Project in Ethiopia as preparatory work in anticipation of the completion of project financing and expected start of construction.
According to the company’s press release:
The AMEC team will provide FEED services in support of the Danakhil Project and will cover the following facilities:
Process and process, maintenance and service buildings
During the FEED engineering phase AMEC will also undertake the following:
Prepare the Project Management Plan (PMP) including a Work Breakdown Schedule (WBS) and definition of supply and construction scopes and packages.
Develop a resource-loaded Level 3 project engineering, procurement/contracting and construction schedule, with detailed estimates of construction staffing requirements
Prepare principal design documents such as design criteria, flow sheets, P&IDs, single line diagrams, site plans, and general arrangements, in preparation for final detailed engineering and construction documentation
Complete civil, concrete and steel materials take-offs (MTOs) based on 3D modeling
Complete trade-off and optimization studies related to certain process components, modularization, power supply, materials movement and layout options
Develop the procurement and construction contracting plan, completing the list of qualified prospective suppliers and contractors
Initiate procurement with formal Requests for Quotation (RFQ) for long lead items and items required to be rough set as structural steel is erected and modules configured