The Delay

Here are my possible explanations for the delay, listed from most likely to least likely:

1. The FS was nearly complete. They found a last minute major flaw in the mine plan and had to scrap it and redo a large portion of the work.

2. The FS was never near completion. Elmer is an excellent geologist but a very poor project manager. He never had very good control of the FS and this allowed Tetra Tech to get very behind schedule.

3. The FS was complete. The results were not very favorable and Elmer decided we would need to incorporate the latest Resource Estimate in order to present a more attractive FS.

4. The FS was nearly complete. Teck wanted us to make some technical changes and this caused the delay.

5. The FS was complete. Teck told us to delay the FS so they could work out a buyout agreement.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. My theory on the delay is simple. There are legitimate staffing issues etc as stated in the NR. I don't think CUU has ever lied, but simply managed the truth as best they can.

    There is only so much they can give away and they already know we take something as simple as a group picture for a charity and extrapolate ideas about potential meetings etc. (that was me.)

    Theory

    The RE2 in July 2011 was cut off at 0.2% Cu equivalent. Quite a few things were known about what was and was not economical from the resource perspective (not the fine details of a mine plan).

    It wouldn't take much (price of steel was mentioned by management) to start challenging the rough model of the mine for RE2011. Add info from some drills. I think Elmer was hoping that some of the drills on the NE corner would be more mineralized as it is a lot of volume and needs to be removed anyways. A whole number of other bigger ticket items could start showing up as issues: for example maybe Ball plants cost 30% more this year than 2008.

    So they had a big meeting and looked at a early draft or a run down on how things are looking and decided that 1) things were not sexy enough and 2) something big had to happen to have a better kick at the can i.e. update the RE with the good Paramount drills, and come at the mine plan a whole other way. Maybe with a different cutoff for the RE? A minor change in the Cu Eq cutoff has pretty big changes - look at the sensitivity analysis in the 2008 PFS. I dont' see TCK having a problem with this. Why spend money going further down a bad road. Let's gear up for the faster lane.

    jmho

    gotta go have a good weekend.

    1. I've racked what's left of my brain for other theories, but come to the same conclusion. The NR was the truth.

      Still good for us, including RE3 into BFS will only help our bargaining position. Looking forward to a surprise some day between now and September.....

      1. If the NR was indeed the truth then the logical conclusions to be drawn by this is that TT was flat out lying about the progress! ES was telling us right up to PDAC that everything was 100% on time and BFS was guaranteed to be out by Q1. As a prof. Eng myself, I find it extremely hard to believe that a Major Engineering firm would be doing this nor do I find it credible that ES, a prof geo with over 30 years experience, was completely oblivious and unaware of the situation. If I had done this as a consulting Eng. I would have been fired.

        1. Agree with cbew here. No way TT was leading Elmer astray about progress. Similarly, no way Elmer had his head in the sand and wasn't on top of things as a CEO should be.

          No way could Elmer be sucker punched by a TT revelation 10 days or so before he had repeatedly reiterated the maximum date for completion of the FS.

          It had to be very close to on schedule. Then bam ... all of a sudden we need a few months.

          Come on ... it doesn't make sense ... things don't add up.

          I think it's weak to think Elmer was as surprised as we were, or that TT is that unprofessional and irresponsible in their duty to give accurate progress reports.

          Elmer needed to delay, and manpower shortage was the least damning excuse.

          More is going on. More time is always needed when bigger and more complicated things need to be worked out.

          The delay and the inclusion of Mr. Gray was needed to sort it all out and ensure that a good representative value of the resource was laid out, and effective costs to bring a mine on board are calculated accordingly.

          And if Elmer thinks he can add 10 billion then maybe Teck wants time to bear that fruit.

          Thats a game changer for sure.

          Let them do their stuff behind the scenes.

          None of it really matters if you stay the course.

          The delay is frustrating but real good.

          We get paid eventually.

          Holding on a little longer means that we paid more.

          Simple, in my opinion.

          1. Here are my thoughts about the delay:

            * I think they knew there was a possibility of a delay on the Feasibility for quite awhile but were pushing hard to get it done.

            * At the same time they were working on the revised Resource Estimate that will increase value significantly.

            * At the same time they were attempting to get the silver included.

            * Bearing in mind if the Feasibility were produced using the 2010 numbers it would be out-of-date even as it was released.

            Maybe the Resource Estimate was starting to show much better numbers and it became obvious that the whole project would be significantly better if the new data from the new Resource Estimate (RE3) were included in the Feasibility and so the decision was taken to just take those extra months. They pulled in Jim Gray, who they have worked with in the past and who was familiar with the project and the historical data. They now have a team together who can complete the Resource Estimate and incorporate it into the Feasibility properly.

            At the end of the day, (or month, or year,) we will have a much better project and more accurate project. . . and more valuable project.

            1. Replying to @Prospekt

              Prospekt, your post including:

              "Maybe the Resource Estimate was starting to show much better numbers and it became obvious that the whole project would be significantly better if the new data from the new Resource Estimate (RE3) were included in the Feasibility and so the decision was taken to just take those extra months. They pulled in Jim Gray, who they have worked with in the past and who was familiar with the project and the historical data. They now have a team together who can complete the Resource Estimate and incorporate it into the Feasibility properly."

              This is a very likely possibility and I think that with the activities that happened this week we were all so pre-occupied thinking about the NR that it took us a few days to calm down and think of possibilites other than our management leading us astray.

              Within the last 2 weeks and the RE3 preliminary numbers in hand, what if ES said to Tetra Tech " We would like the new RE3 to be included in the FS, after seeing the preliminary results, they need to be included " TT says " Well we agree, but we do not have the available manpower right now to get the RE3 included and meet your timeline of March 30"

              If this was the case, the manpower issues are true, Elmer is not lying and it does not mean Tetra Tech "Dropped the Ball" just slightly different context.

              Could the current black out be because the RE3 numbers were acquired earlier than we thought? Say early Feb.

              It might have been better to say to us SH that the RE3 is now going to be included, thus the delay, and we all would have been slightly disappointed but happy for added value and honesty.

              With Jim Gray's involvement in the preliminary FS, I cannot believe that he has not been involved in the FS already, a good move to get him involved. He must have done something right b/c the PFS numbers were good!

              Have a good weekend everyone!

              Cheers!

              1. Replying to @moguely

                Could the current black out be because the RE3 numbers were acquired earlier than we thought? Say early Feb.

                If the company was in posession of a material fact they would have to release it within a specified timeframe. I dont think the FS is done at all and I think the NR was the truth. Everyones dealt with a company thats dropped the ball before...I dont think this is any different just a lot larger and a lot more anticipated. Management and Teck cant just run around with a FS denying its existence.

                That being said I also dont think Teck will act before the FS is out. As of 2009 there were new rules instituted for "buy side shareholder votes". HudBay Minerals proposed an acquisition of Lundin Mining and the OSC stepped in and imposed a shareholder vote on the acquisition, even though there were no applicable rules at the time to this effect. This has since changed. Ironically when the OSC did this the shareholders of HudBay REJECTED the potential acquisition.

                Therefore I think Tecks going to probably have to vote on the acquisition. Any institutional holders in Teck will certainly have proxy advisory firms giving them advice on how to play their cards in any given buyout.

                Buy side shareholder votes also require evidence that they are not overpaying for the potential asset.

                In my eyes....Schaft Creek is too big and is going to cost too much money for Teck just to step out and act. I think their acquisition will be a little more drawn out than that and I think theres going to be a lot of discussion, legalities and notarizing involved.

                Teck can drop the expenditures very quickly.....whats $300 million to Teck? Theyre a $50 billion dollar company. I dont think theyre too worried about shelling out this kind of cash for all the future profit theyre going to be recieving from it.

                They get 75% of Schaft Creek for peanuts. I dont see any reason Teck will turn down billions of dollars of net value for this paltry chunk of change. They can then buy the remaining 25% and vend out a JV with another company that gets all their money back and has the other company paying the production costs. Not a bad deal....50-70% of ownership in Schaft Creek for either free, or very cheap.

                All in all what Im saying is I think the delay is caused by the actual reasons cited and not management and Teck colluding behind the scenes. When the FS is ready....Teck will probably make use of their 120 days to put it out to their shareholders.

                Matter of perception here.......why would Teck put a 120 day clause in effect on their own contract?

                1)To force themselves to act at CUU's behest?

                2)To give them time to get all their ducks in a row with their shareholders after they review the numbers and ramifications of an acquisition of this size?

                Rogue.

                Personally I think 2 is a lot more logical.

              2. Replying to @moguely

                I have been weighing out the post NR messages from everyone here, trying my best to figure out the mystery that is this company and when it will finally play out. I must agree with some posters here that the NR was merely stating the current situation. I disagree with some speculators who feel we must dig deep to find a conspiracy or decode some hidden message within the NR.

                I am still trying to piece together a couple of things that aren't adding up for me though and keep me a little uneasy. I am about 60% sure I will purchase more shares in the coming few months, but a few questions still plague my decision. As many upper level managers on the board have stated, they would have been slaughtered for this type of result and late dissemenation of information, and I have to agree. It does not make sense that everything was on time right up until delivery and then all of a sudden it needs many more months??? Is it wrong of me to assume that management would or should have been getting daily updates from Tech on the status of the FS when we were nearing so close to our deadline of end Q1? I can only assume that our management was informed of the missed deadline between shareholders meetings at PDAC and the apparent date that CUU was "advised of manpower shortages and scheduling difficulties". At the end of the day it is my opinion that Tech was not completely forthcoming with our management about realistically having the FS done on time or a combination of that and our management not keeping Tech as accountable as they possibly should have been. I believe that Jim Gray will be hovering over the shoulders of Tech constantly and scrutinizing details of the FS itself as well as timelines.

                As a disclaimer, I have been following the boards for a while and hold a relatively substantial portion of my holdings in CUU.

                1. Replying to @Terf

                  If it is all that simple then why are some insiders blacked out? We knows this because their options have not expired. Will they be now blacked out until the FS comes out in several month from now? Somehow this doesn't add up

      2. Of course the NR was the truth. However, it is what is going on behind the scenes that is far more important. And the company will never, NEVER divulge anything about that situation. Those wanting more details are going to waiting until later today, tomorrow, Monday, next week or next month until the HALT trading is announced. Then it will all become clear. Crystal clear. I think everyone likes the smell of coffee......especially señor E. What delay?
    2. Okay, lets say there was a legitimate reason for delaying the FS, they could also use the fact of staffing issues as a pretext to cover up that their negociating. There is a strong posibility that there is negociating going on. Also, Just wondering, We know that a great deal of the FS has already been done, right. Could they not grab hold of the part of the report already completed and use that as part of the negociating (meaning of course that there is enough proof for neg. power). And say they do have in hand the whole FS, how long do they have after both parties analyse it to send it public?

    3. Chappy:

      So they had a big meeting and looked at a early draft or a run down on how things are looking and decided that 1) things were not sexy enough and 2) something big had to happen to have a better kick at the can i.e. update the RE with the good Paramount drills, and come at the mine plan a whole other way. Maybe with a different cutoff for the RE? A minor change in the Cu Eq cutoff has pretty big changes - look at the sensitivity analysis in the 2008 PFS. I dont' see TCK having a problem with this. Why spend money going further down a bad road. Let's gear up for the faster lane.

      Chappy, good explanation. That's exactly what it is. Of course the NR was true. At PDAC Elmer told me not to listen to anybody except for official news sources. I also believe that the delay was due to manshortage at TT and mediocre results.