Any guesses on what the sp will look like in 2 hours? About the million share mark and suddenly it stalls for lunch. Oddly enough, people take food more serious than investing lol. The last time we had a freak run up before news and this time on news, it should end the same way. But will it? We are way off the last RE level in better times and with a lot more value.

Join the conversation about Copper Fox Metals Inc.

Reply

Replies

  1. Here is my quick and dirty NPV estimate based on the RE; critics and comments welcomed (only difference in right column is the 5% discount rate):

    Daily Processing MT 150,000 150,000
    Recovery 88% 88%
    Copper grade % 0.266 0.266
    Copper/dayMT 351 351
    Copper/day lbs 772,464 772,464
    Copper price ($/lb) $3.50 $3.50
    Copper revenue/day $M $2.70 $2.70
    MO grade % 0.019 0.019
    MO/dayMT 25 25
    MO/day lbs 55,176 55,176
    MO price ($/lb) $14.00 $14.00
    MO revenue/day $M $0.77 $0.77
    AU grade g/t 0.160 0.160
    AU/dayoz 660 660
    AU price ($/oz) $1,300 $1,300
    AU revenue/day $M $0.86 $0.86
    AG grade g/t 1.590 1.590
    AG/dayoz 6,559 6,559
    AG price ($/oz) $26 $26
    AG revenue/day $M $0.17 $0.17
    Total revenue/day $M $4.50 $4.50
    Production cost/day $M $1.03 $1.03
    Net revenue/day $M $3.48 $3.48
    Days/year 340 340
    Revenue/year $M $1,182 $1,182
    CUU's share 25% $M $296 $296
    Total OS shares (M) 400 400
    Disc rate: 8% 5%
    Years of cashflow: 30 30
    PV ($M): 3,327 4,543
    Capital cost: 4,000 4,000
    CUU's cap cost: 1,000 1,000
    NPV Per share: $5.82 $8.86
    Production cost estimate:
    Mining cost per ton $1.35 $1.35
    Processing costs per ton $5.50 $5.50
    total $6.85 $6.85

    The NPV per share before income taxes is $5.82 at 8% and $8.86 at 5% discount rate.

    This is for Schaft Creek only.

    1. Let the profit takers take their profit....you know they'll be back. Don't cry if Teck makes a move over the weekend (just an example)

      The resource is great...but what I like the most is that it's on time.

      This is the 2nd time in a row that management has surprised us. 1st with the completed aerial ...and now with the Resource Estimate.

      Now that the resource is complete they can include it in the Feasibility..Don't forget Jim Gray has been on this for months, it should be well advanced. Tetra Tech did a good job with the resource and I expect they will do a great job on the Feasibility.

      If Management says Feasibility Mid-Late summer (I was told that was conservative)...then we better believe them this time.